Where did the + / - go? Microsoft Project |
- Where did the + / - go?
- Removing Blank Space on Gantt Chart
- Can percent complete be expressed in decimal format?
- Can percent complete be expressed in decimals?
- Sharing Resources Across Multiple Projects
- DotProject references needed
- How do I?
- How to get the end date to change when updating a task?
- How to capture MsgBox result and paste into Excel
- export a project file for printing
- Field Customize
- auto calculation problem
Posted: 15 Aug 2005 07:53 AM PDT Jan De Messemaeker wrote: There is not an Outline toolbar in 2003 Professional, at least not in the English version. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Removing Blank Space on Gantt Chart Posted: 13 Aug 2005 06:45 PM PDT Hi Bob, I'm afraid you can't :-( -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Bob" <microsoft.com> schreef in bericht news:com... them gantt |
Can percent complete be expressed in decimal format? Posted: 12 Aug 2005 08:51 PM PDT If you want the remaining duration to be in whole numbers then enter it in whole numbers and let project calculate % complete. To do this effectively insert the the "actual duration" column and the "remaining duration" column. When you update, enter the new value for actual duration and the amount remaining. Project will then calculate the percent complete for you. Alternatively you could write some VBA which would go through and round remaining duration to the nearest integer after you have updated percent complete. I'm not sure I understand the need for integer values though. Why are they necessary? -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "carey" <microsoft.com> wrote in message news:com... expressed be on 75 |
Can percent complete be expressed in decimals? Posted: 12 Aug 2005 08:48 PM PDT We agree that it should be after the status date and if you reschedule the incomplete work to take place after the status date your early finish will show as it should. What I'm trying to tell you is updating the project's progress involves more than merely setting a percent complete. That's only the first step in a 2 step procedure - and you're leaving out a crucial part of the process. If I have a 2 day task that was scheduled for last week, Mon and Tue, and mark it as 50% complete, it will show work took place on Monday but has not taken place on Tuesday. But as of that moment, Project doesn't know if it really didn't take place and needs to be moved up into the future or if we just haven't gotten around to posting the data for last Tuesday's work yet. If you now reschedule the remaining work, Project will split the task and move the remaining portion forward, in the process also changing the early finish date to the day after your status date as it should. If you don't reschedule uncompleted work, Project doesn't know it's supposed to recalculate those early finish dates. You have to do both tasks - post actuals and reschedule remaining. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "carey" <microsoft.com> wrote in message news:com... |
Sharing Resources Across Multiple Projects Posted: 12 Aug 2005 06:03 PM PDT Fusion, Just in case you meant "resource pool" in an HR way, and not in a MS Project environment.... You would need to connect all of your project plans to a "resource pool" MS Project plan. The way I have done this in the past is to create a project plan solely for the use of this purpose (i.e., resource pool). All of the resources that you have access to use are entered into the resource sheet for this project plan. The only tasks that I have entered were for vacation/sick/training days, but you don't need to actually add any tasks in the plan at all. All of the project plans that contain the "work" are then connected to the resource pool by openning the "pool" and the "work" MS Project files (so that they are both open at the same time) and in the "work" project file selecting Tools | Resource Sharing | Share Resources..., then select the Use resources (From:) radio button, and then select the resource pool project plan from the drop-down. You will need to open and "link" (to) the resource "pool" project plan from each of your "work" plans. You can perform all of the "linkings" first. Then check the resource sheet in the "pool" to see if all of your resources are present. If not, you can add them via the Resource Sheet view. If you have accomplished this feat, then the fun with "Leveling" starts, but thats another subject.... Hope this helps! :) -- Don L. "Brian K - Project MVP" wrote: |
Posted: 12 Aug 2005 03:42 PM PDT You should be able to find some help and assistance for dotproject on its home site support forums located at http://www.dotproject.net/vbulletin/ Hope this helps. Ira "Yves M." wrote: |
Posted: 12 Aug 2005 03:30 PM PDT CBland, Reviewing Mikes TechTrax will give you a more solid understanding of how MS Project "thinks" with respect to Work, Duration and Units. This will help you in the future. For your particular problem at hand, try: 1. Create the task (assumption is a Fixed Unit task Type) 2. Establish the 10 day Duration 3. Assign the 16 hours Work 4. As a last step, assign the Resource Becuase you established the Duration and Work first, then assigned the Resource, MS Project spreads the 16 hours of Work across the 10 day Duration. The end result is the Resource will be assigned to the task at only 20%. Hope this helps! |
How to get the end date to change when updating a task? Posted: 12 Aug 2005 03:00 PM PDT It's hard to understand just what you're expecting to happen here. I have a task that is originally 10 days duration. We've worked on it 4 days. I enter a remaining duration of 15 days. 4 days worked plus 15 to go means we originally underestimated the required time to do the work and it should have been 19 days. Ergo, the duration changes. Now if you need to preserve the original 10 days estimate for tracking purposes, that's what a baseline is all about. When you make updates as above, the scheduled duration changes but the original saved baseline doesn't, giving you a static reference point in order to compare actual performance with original estimates. Whether the early finish would change or not or how it would change really depends on the scenario. I have a 40 hours task starting Mon 8am. It's early finish is Friday 5pm. I show it starts on time and is 20% done - actual duration 1 day, remaining duration 4 days. Early finish stays the same. But if it started Tuesday instead, early finish becomes the following Mon. OR if it starts on time, 1 day actual duration but 3 days remaining, that makes the task 25% done and the early finish moves up to Thurs. So when you enter a start date, an actual duration, and/or a remaining duration the early finish may or may not change depending on the specific mix of parameters you've input. For instance, 1 day shorter duration combined with a 1 day later than scheduled start would result in an early finsh that hasn't changed. The following identities always hold true... ScheduledDuration == ActualDuration + RemainingDuration. % Complete == ActualDuration/ScheduledDuration. For unstarted tasks, EarlyFinish ==ScheduledStart + ScheduledDuration. For in-progress tasks, EarlyFinish==ActualStart + ScheduledDuration As an aside, I can't imagine what advantage you get using manual calculation mostly. Project is fundamentally a schedule calculator. If you don't let it calculate, what's the point in using it? -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "carey" <microsoft.com> wrote in message news:com... |
How to capture MsgBox result and paste into Excel Posted: 12 Aug 2005 02:52 PM PDT Hellow again John, Obviously, I'm not a natural programmer. Your solution is what I want to do, but I can't figure out how to get the calculation results into the text1 field. What code would I use to replace the message box display with placing the total number of the calculation into the text1 field? "John" wrote: |
export a project file for printing Posted: 12 Aug 2005 01:01 PM PDT Hi David, You need to have a software product that can generate PDF files. Then you print the project to the PDF writer. For some links to inexpensive PDF programs see FAQ # 16 "Project Viewer" at www.mvps.org/project Hope this helps. Julie "david" <microsoft.com> wrote in message news:com... |
Posted: 12 Aug 2005 12:09 PM PDT You may also want to use the ProjDateDiff function. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Sarah" <com> wrote in message news:googlegroups.com... |
Posted: 12 Aug 2005 05:56 AM PDT In article <com>, gokhan <microsoft.com> wrote: gakhan, Ok, thanks for the very direct specific responses to my questions. Something I forgot to ask, does this occur with more than one file? If you haven't already you might want to try creating a fresh new test file and see it the Summary Lines calculate properly. If they do, you may have some file corruption in your original file. In that case, go to the MVP website at: http://www.mvps.org/project/faqs.htm and look at FAQ 43 - File Bloat? - Might be Corruption. If it still "fails" on a totally new file I'm not sure what else to suggest other than a complete re-install of Project and the SP-1 update but that is pretty drastic. Hopefully one of the other guys will have a suggestion. John Project MVP |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |