removing start and finish dates for certain "tasks" Microsoft Project |
- removing start and finish dates for certain "tasks"
- trial version -project
- Formula issue
- Link tasks from multiple, detailed projects into a master project
- update a task to 100% for more than one resource
- Subject: PWA page in Outlook is empty
- Multi Projects
- Linked Tasks
- Create formula that uses resource assignment units in Project?
- How can change the cell's color?
- How do I make the line separators visible when printing?
- Parallel tasks in same project by same person
- Project .mpp files...
- Resource callendar
- lock gantt view
- how do I put a project end date in project
removing start and finish dates for certain "tasks" Posted: 04 Aug 2005 10:56 AM PDT No problem, simply create a new table (View, Table, More tables) and put custom fields in it. Then apply the table when you want to look/edit the data, then re-apply the entry table: no screen space lost. Custom data on the same row as an existing task won't create a new task. For project level data: Select Tools, Options View tab Select Project Summary Task Add data only to the new row 0 -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "schemr" <microsoft.com> wrote in message news:com... |
Posted: 04 Aug 2005 09:32 AM PDT That did not work, because I had activated the trial version already, so I no longer have the "activate product" on my help menu. I do not have the pnone number to call in.... "Renke Holert [MVP]" wrote: |
Posted: 04 Aug 2005 06:39 AM PDT schemr wrote: Glad to help. But if you want you should break it down and see how it works. make some changed to it and see what happens. play around so you wll have a firmer grasp on it. Good luck with that other stuff on your desk! :-) -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Link tasks from multiple, detailed projects into a master project Posted: 04 Aug 2005 05:28 AM PDT In article <com>, "Mark Kyprianou" <microsoft.com> wrote: Mark, No. Unless the default setting was changed when the master was built (Insert/Project), the subprojects will automatically be dynamically linked to the master and vice versa. Updating tasks in either will be reflected in the other. Hope this helps. John Project MVP |
update a task to 100% for more than one resource Posted: 04 Aug 2005 05:08 AM PDT FOON -- If either one updates their assignment as 100%, I assume that this means the task is complete. Therefore, you should use the following process: 1. Accept and update the task progress from PWA into the Microsoft Project plan 2. Click OK and then click Collaborate - Publish - All Information 3. Select the task and click Window - Split 4. In the Task Form (bottom pane), right-click and select the Resource Work details 5. Set the Remaining Work to 0 hours for the team member who did not report 6. Click OK 7. Click Window - Remove Split 8. Click Collaborate - Publish - All Information Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "FOON" <microsoft.com> wrote in message news:com... |
Subject: PWA page in Outlook is empty Posted: 04 Aug 2005 02:01 AM PDT I think it's PWA issue. PWA is part of Project. So that question about Project. IMHO "whatzzup" wrote: |
Posted: 04 Aug 2005 12:21 AM PDT You have to have a common conversion rate otherwise 1d or 1w of work will be mis-interpreted by everyone! Every resource has their own calendar so every resource can work different hours in any particular day. So, Sue can have her calendar edited to work a 7 day week for a particular week then have the following Monday and Tuesday off. Or you can have machinery work 7*24. The conversion rate has nothing to do with hours worked on a particular day. It is purely how 1d and 1w is converted into working hours. Project uses the calculated hours and the resource calendar to calculate the finish date and time of a task. So you want to schedule an all nighter? edit the calendar. So you want to have a task done only on week ends? Create a baseline calendar called Week Ends and in the Advanced tab of the task's Task Information dialog select the Week End calendar. project uses calendars to calculate dates and times for tasks. Conversion rates are for converting days and weeks to hours and should be the same for all projects so you can consolidate. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "John Sitka" <com> wrote in message news:phx.gbl... |
Posted: 03 Aug 2005 07:30 PM PDT Task links are permissive, not obligatory. If I have a task that is linked from a predecessor FS, where the finish of the predecessor is linked to the start of the successor, what that is really saying is that the earliest that the successor can start is when the predecessor has finished. But there are many reasons why it might actually start LATER than that - resource isn't available, parts haven't arrived, etc. If we have multiple predecessors lkinked FS to a single successor, the succesor isn't allowed to start until the latest finishing successor is done. In the case of a SF link, the successor tasks is allowed to be declared "finished" until all the precessors have started, meaning that the earliest its scheduled finish can occur is when the last to start predecessor has started. You could try this. Create summary task and indent your 4 tasks under it. Link the task you want to control as a successor to that summary task, linked in a SF relationship so the start of the summary task is linked to the finish of the successor you need to control. Now the controlled task will be scheduled to finish when the earliest starting of you subtasks begins. Usually it's not a good idea to link to and from summary tasks but there are exceptions to every rule and this may be one of them. I think you'll find that works. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "ArnoS" <microsoft.com> wrote in message news:com... |
Create formula that uses resource assignment units in Project? Posted: 03 Aug 2005 03:35 PM PDT Hi, When there's only one resource you could use Work/Duration HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "SixSigmaGuy" <microsoft.com> schreef in bericht news:com... "Resource still resource. want Units |
How can change the cell's color? Posted: 03 Aug 2005 02:02 PM PDT This is what I thought. Am I the only who thinks they should do something about it? Im back to using excel now |
How do I make the line separators visible when printing? Posted: 03 Aug 2005 09:16 AM PDT Thanks, I should have mentioned that it was the "task list" portion of the printout (left-side). I've since found out that it was a printer issue. I switched to another (newer) printer and the lines come out fine. Our admin mentioned that it could be a printer driver issue. Thanks.... "DonL" wrote: |
Parallel tasks in same project by same person Posted: 03 Aug 2005 09:11 AM PDT Thanks for your help. Levelling fixed the problem! Mark "DonL" wrote: |
Posted: 03 Aug 2005 07:41 AM PDT Yeah...I was afraid of that! Thanks for your quick response... -- Mark Byington, PMP "JackD" wrote: |
Posted: 03 Aug 2005 07:26 AM PDT Hey Shiv, I thought about that but it is NOT what I want, since it doesn't count the hours that it COULD do it's thing during the weekend. Thanks Ian "Shiv" wrote: |
Posted: 03 Aug 2005 05:06 AM PDT Hi again, If you really don't know what I wa talking about this may be long.. 1. You CANNOT read the properties of a view so you CANNOT detect whather it has been altered or not. 2. Fortunately, you don't have to know that; you can reset it to the original state by all means. 3. To be able to reset it to the state you want you have to define and save that state. In other words, you have to store the View (which has all the formatting in it) and the Table (which is the list of columns in teh left side, width and Title) 4. Make a file (could be a copy of the life file) and define the view you want. Also set the columns you want to show. In View, More Views, note the name of the View (probably Gantt Chart) Note that you can rename it etcetera, try it. Also look at the View Menu, Table:..... and note the name of the table. Save this file (let's call it Viewfile) 5. When teh file you want to fix the view of comes along, open it together with Viewfile and go to Tools, Organizer, Views; copy yiour standard view from the Viewfile innto the target file Same with Tools, Organizer, Tables. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Gabriele" <it> schreef in bericht news:googlegroups.com... |
how do I put a project end date in project Posted: 02 Aug 2005 12:25 AM PDT Jan gave you one way. Another would be to use a finish milestone to show the project's end, as Jan suggested. But instead of a MFO constraint, set a deadline of your desired latest finish date on the milestone. When you display slack times, such as in the Schedule table view, you'll see the amount of time each task could theoretically be delayed without pushing the milestone past your latest acceptable finsih while the milestone itself sits on the date where your present schedule will cause it to fall. Project's slack time calculations are identical whether you use constraints or deadlines designate the latest aceptable finish date. But note, as Jan said in neither case will Project spread out the tasks to fill the allotted project length. If you want to do that it's going to be a manual process. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Rich Asher" <Rich microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |