Pages

Search

Project Predecessors should have mouse over to ID the Task Name Microsoft Project

Project Predecessors should have mouse over to ID the Task Name Microsoft Project


Project Predecessors should have mouse over to ID the Task Name

Posted: 18 Aug 2005 01:57 PM PDT

In article <phx.gbl>,
"JackD" <momokuri@gmail> wrote:
 
Jack,
I wasn't aware of that, but now I am. Thanks

John

Link To-do lists to Tasks

Posted: 18 Aug 2005 01:21 PM PDT


Hi ATL,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP


ATL wrote: 



Non checked out project shows checked out

Posted: 18 Aug 2005 12:19 PM PDT


Hi la0d0g ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP

la0d0g wrote: 



Can I create a project template?

Posted: 18 Aug 2005 11:58 AM PDT

Please let us know if there is anything else we can help with!
angie
--
This posting is provided "AS IS" with no warranties, and confers no rights.


"Sam" wrote:
 

Can I use multiple resouces for 1 task?

Posted: 18 Aug 2005 08:19 AM PDT

John,

Unfortunately I have not worked with Project for years and I have forgotten
a lot. Thank you for your time in responding to my question. I will look
into the link that you sent also.


"John" wrote:
 

Hierarchy structure in MS Project

Posted: 18 Aug 2005 05:12 AM PDT

schemr --

In the Enterprise Global file, create a new custom enterprise Project
outline code called Sales Manager. Make this a required field and list all
of our sales managers in the outline code structure. Save and close the
Enterprise Global and then exit and relaunch Microsoft Project Professional.
Ask each PM to open all of his/her projects and click Project - Project
Information, select the Sales Manager for each project, and then save and
publish each project using Collaborate - Publish - Project Plan. Add the
new Sales Manager field to each Project Center view in PWA. You might also
want to create a custom Project Center view called Sales Manager that has
grouping applied by default on this outline code. You might also want to
create a custom Portfolio Analyzer view that summarizes project data by the
Sales Manager outline code.

After you and the PM's complete the above series of steps, anyone who can
view the Project Center page will be able to apply grouping or sorting on
the Sales Manager outline code. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"schemr" <microsoft.com> wrote in message
news:com... 


multiple baseline compare

Posted: 18 Aug 2005 01:33 AM PDT

Hi,

1. To compare two dates (for instance two baselinestartx)
Tools, Customize, Fields, select a number field
Activate Formula
[Baselinestartx]-[Baselinestarty] returns a value in days
projdatediff( [],[], Calendar name) returns a value in minutes
When you select a duration field projdatediff will be expressed in the
normal duration units

2. To show nonstandard bars in the Gantt Chart (such as haveing a hape to
indicate Baselinestart7 or a bar between baselinestart5 and Start)
see
http://www.mvps.org/project/faqs.htm

Faq 31. Customizing Task Bars

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"MAT" <microsoft.com> schreef in bericht
news:com... 
gantt? 


Printing reports with a date range

Posted: 17 Aug 2005 11:24 AM PDT

LadyBean01,
You are correct that Date Range filters out the tasks.
To get the timephased info you are looking for, try temporarily
changing your project start date to June 1. >Project, >Project
Information

Hope this helps!

Resource Usage View Project 2003 Server Master Project Plan

Posted: 17 Aug 2005 11:18 AM PDT

Hi,

All of this is perfectly possible without Project Server, even in Project
Standard, but not knowing Project Server very well I hesitate to gieve a
recipe in a Server environment.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Jerryinnc" <microsoft.com> schreef in bericht
news:com... 
the 
the 
to 
is 
the 
levels. 


how do I add a delay to the entire project

Posted: 17 Aug 2005 10:57 AM PDT

brandon erndt wrote:
 

You could set the status date to equal the date the work will resume for
this project and then hit the 'Reschedule' button on the Tracking Toolbar.
This will move the unfinished portions of all tasks so that they start
after the new status date.

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Save as MPP vs. Publish to Project Server

Posted: 17 Aug 2005 08:20 AM PDT

Okay, Mike.

All,
Please go to
microsoft.public.project.server
to follow this thread.

Thanks,
Jim


"Mike Glen" <glenATmvps.org> wrote in message
news:phx.gbl... 


Managing Time Worked

Posted: 16 Aug 2005 01:16 PM PDT

I know it happens a lot and can't quite figure out why. If clients like
yours don't want to take advantage of the greatly enhanced business controls
detailed project management that using tools like Project server can
provide, why buy it at all? It seems rather like buying a Ferrari racing
car and never driving it over 25km/hr. Sure one can do it, but why in the
world would you WANT to, what's the point of spending the money and never
fully exploiting what you've paid for?
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message
news:%phx.gbl... 

how do i display week numbers in project?

Posted: 16 Aug 2005 12:55 PM PDT

In article <com>,
Rompie <microsoft.com> wrote:
 

Rompie,
I have probably heard of ISO week numbers but have never used them. I
also do not use Outlook. Because one MS application (or even several of
them) can do a particular thing doesn't mean all MS applications can do
it. A good example is that in Excel individual Worksheet cells can be
formatted. We get many posts in the Project newsgroup asking how that
can be done in Project, particularly in either of the Usage views.
Unfortunately individual field cell formatting is not an option in
Project.

The only formatting available for the timescale in Project is that
available in the selection lists for Units and labels found in the
Timescale edit window. That window can be accessed by either double
clicking on the timescale or by going to Format/Timescale.

Hope this helps.
John
Project MVP

Rookie question

Posted: 16 Aug 2005 12:04 PM PDT

Project works with Tasks and Resources.
When a resource is working on a task it is called an assignment.
Assignments consist of an amount of work that the resource is going to do on
that specific task.
The work on a task consists of the sum of work in all assignments.
When the resource assignment is removed, then that work is removed.
Work represents the number of resource hours/days/weeks/minutes that is
being expended.
Further Project uses the equation Work = Duration * Units to determine what
work is.
Units refers to the number of resource units.
Altering one of the values in the equation will affect at least one of the
other values.
You can see that an increase in work will require a proportional increase in
duration or Units.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
<com> wrote in message
news:googlegroups.com... 


Custom Milestone not working

Posted: 16 Aug 2005 11:25 AM PDT

In article <com>,
DBD <microsoft.com> wrote:
 

DBD,
You're welcome. I think the approach of treating the meeting itself as a
separate task and the milestone as the completion of that task will work
much better in the long run.

John
Project MVP

Remaining hours extending project

Posted: 16 Aug 2005 10:56 AM PDT

Think about it for a minute - the duration HAS to change. Joe was assigned
100% to a task that would take 5 days. He worked 3 days and then estimates
that there are still 4 days of work to do, the original 5 day estimate was
off. You really only have 2 choices. He either works 8 hours a day for 4
days to do the required work, extending the curation to a total of 7 days in
the process, or he somehow magically gets the 4 days of remaining work
accomplished in the 2 days of time left in the the original duration,
generating 16 hours of work during each 8 hour workday thus working at 200%
allocation. But that's actually not possible - 100% means the resource is
already working as fast as they can possibly work and the only way you
really can exceeed that is to get someone else to work along with him to
carry part of the load. There really aren't any other physical ways that
scene could play out.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"G" <microsoft.com> wrote in message
news:com... 

Many Small Problems

Posted: 16 Aug 2005 10:43 AM PDT

David --

Ask your IT people to ready the following KB article:

http://support.microsoft.com/?kbid=837240

In that article, they will see how many bug fixes in the Microsoft Project
Professional 2003 SP1 concern how the software works with Project Server
2003. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"David" <microsoft.com> wrote in message
news:com... 


assigning tasks to "sub PMs" to schedule them

Posted: 16 Aug 2005 09:56 AM PDT

Hi Schemir,

this approach can be used if you have project server.

This is a link to PowerPoint demo, how top-down planning can be done with
Project Sever:
http://www.bogdanov-associates.com/imgrubrs.asp?art_id=85&img=file


--
Regards,
Vadim Bogdanov
OLAP Extender - add any custom data to the OLAP cube
http://www.bogdanov-associates.com/eng.asp?rubr_id=484



"schemr" <microsoft.com> wrote in message
news:com... 


Views with Gantt Chart Wizard.

Posted: 16 Aug 2005 09:23 AM PDT


Hi Dave,

You could create a new private project. Create your views there and then
transfer them via the Organizer to the working projects. Then, if one gets
changed significantly, you can recover it from your private project.

Mike Glen
MS Project MVP

Dave wrote: 



i want to know the first start date in a number of duplicate tasks

Posted: 16 Aug 2005 07:26 AM PDT

Did you make the dependency from the start of the milestone to the start of
the task or the other way around?
The first should work. The second will give the result you describe.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Martin Theobald" <microsoft.com> wrote in
message news:com... 
each 


In Microsoft Project, No Enterprise Options under the tools menu?

Posted: 16 Aug 2005 06:55 AM PDT


Hi Randall ,

Next time you might like to try posting on the server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Mike Glen
Project MVP


Randall wrote: 



How do I view any baseline?

Posted: 15 Aug 2005 06:08 PM PDT


Hi Bill,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 14. Viewing Multiple Baselines

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

John wrote: 



Gantt Charting - Help Needed

Posted: 15 Aug 2005 02:39 PM PDT


You're welcome, Jothi:-)

Mike Glen
MS Project MVP


Ganesh wrote: 



Losing settings in Global.MPT

Posted: 15 Aug 2005 02:07 PM PDT

THanks Mike. I'll try that.
--
LeeY


"Mike Glen" wrote:
 

Forward Pass

Posted: 15 Aug 2005 12:42 PM PDT


Terry Montgomery wrote: 

Terry,
I've been teaching CPM for years. This is hard to explain in detail
here. If you'd like to contact me, I'd be happy to go over it with you.
Email me if you're interested.
Dave