Project Predecessors should have mouse over to ID the Task Name Microsoft Project |
- Project Predecessors should have mouse over to ID the Task Name
- Link To-do lists to Tasks
- Non checked out project shows checked out
- Can I create a project template?
- Can I use multiple resouces for 1 task?
- Hierarchy structure in MS Project
- multiple baseline compare
- Printing reports with a date range
- Resource Usage View Project 2003 Server Master Project Plan
- how do I add a delay to the entire project
- Save as MPP vs. Publish to Project Server
- Managing Time Worked
- how do i display week numbers in project?
- Rookie question
- Custom Milestone not working
- Remaining hours extending project
- Many Small Problems
- assigning tasks to "sub PMs" to schedule them
- Views with Gantt Chart Wizard.
- i want to know the first start date in a number of duplicate tasks
- In Microsoft Project, No Enterprise Options under the tools menu?
- How do I view any baseline?
- Gantt Charting - Help Needed
- Losing settings in Global.MPT
- Forward Pass
Project Predecessors should have mouse over to ID the Task Name Posted: 18 Aug 2005 01:57 PM PDT In article <phx.gbl>, "JackD" <momokuri@gmail> wrote: Jack, I wasn't aware of that, but now I am. Thanks John |
Posted: 18 Aug 2005 01:21 PM PDT Hi ATL, Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP ATL wrote: |
Non checked out project shows checked out Posted: 18 Aug 2005 12:19 PM PDT Hi la0d0g , Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP la0d0g wrote: |
Can I create a project template? Posted: 18 Aug 2005 11:58 AM PDT Please let us know if there is anything else we can help with! angie -- This posting is provided "AS IS" with no warranties, and confers no rights. "Sam" wrote: |
Can I use multiple resouces for 1 task? Posted: 18 Aug 2005 08:19 AM PDT John, Unfortunately I have not worked with Project for years and I have forgotten a lot. Thank you for your time in responding to my question. I will look into the link that you sent also. "John" wrote: |
Hierarchy structure in MS Project Posted: 18 Aug 2005 05:12 AM PDT schemr -- In the Enterprise Global file, create a new custom enterprise Project outline code called Sales Manager. Make this a required field and list all of our sales managers in the outline code structure. Save and close the Enterprise Global and then exit and relaunch Microsoft Project Professional. Ask each PM to open all of his/her projects and click Project - Project Information, select the Sales Manager for each project, and then save and publish each project using Collaborate - Publish - Project Plan. Add the new Sales Manager field to each Project Center view in PWA. You might also want to create a custom Project Center view called Sales Manager that has grouping applied by default on this outline code. You might also want to create a custom Portfolio Analyzer view that summarizes project data by the Sales Manager outline code. After you and the PM's complete the above series of steps, anyone who can view the Project Center page will be able to apply grouping or sorting on the Sales Manager outline code. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "schemr" <microsoft.com> wrote in message news:com... |
Posted: 18 Aug 2005 01:33 AM PDT Hi, 1. To compare two dates (for instance two baselinestartx) Tools, Customize, Fields, select a number field Activate Formula [Baselinestartx]-[Baselinestarty] returns a value in days projdatediff( [],[], Calendar name) returns a value in minutes When you select a duration field projdatediff will be expressed in the normal duration units 2. To show nonstandard bars in the Gantt Chart (such as haveing a hape to indicate Baselinestart7 or a bar between baselinestart5 and Start) see http://www.mvps.org/project/faqs.htm Faq 31. Customizing Task Bars HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "MAT" <microsoft.com> schreef in bericht news:com... gantt? |
Printing reports with a date range Posted: 17 Aug 2005 11:24 AM PDT LadyBean01, You are correct that Date Range filters out the tasks. To get the timephased info you are looking for, try temporarily changing your project start date to June 1. >Project, >Project Information Hope this helps! |
Resource Usage View Project 2003 Server Master Project Plan Posted: 17 Aug 2005 11:18 AM PDT Hi, All of this is perfectly possible without Project Server, even in Project Standard, but not knowing Project Server very well I hesitate to gieve a recipe in a Server environment. -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Jerryinnc" <microsoft.com> schreef in bericht news:com... the the to is the levels. |
how do I add a delay to the entire project Posted: 17 Aug 2005 10:57 AM PDT brandon erndt wrote: You could set the status date to equal the date the work will resume for this project and then hit the 'Reschedule' button on the Tracking Toolbar. This will move the unfinished portions of all tasks so that they start after the new status date. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Save as MPP vs. Publish to Project Server Posted: 17 Aug 2005 08:20 AM PDT Okay, Mike. All, Please go to microsoft.public.project.server to follow this thread. Thanks, Jim "Mike Glen" <glenATmvps.org> wrote in message news:phx.gbl... |
Posted: 16 Aug 2005 01:16 PM PDT I know it happens a lot and can't quite figure out why. If clients like yours don't want to take advantage of the greatly enhanced business controls detailed project management that using tools like Project server can provide, why buy it at all? It seems rather like buying a Ferrari racing car and never driving it over 25km/hr. Sure one can do it, but why in the world would you WANT to, what's the point of spending the money and never fully exploiting what you've paid for? -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:%phx.gbl... |
how do i display week numbers in project? Posted: 16 Aug 2005 12:55 PM PDT In article <com>, Rompie <microsoft.com> wrote: Rompie, I have probably heard of ISO week numbers but have never used them. I also do not use Outlook. Because one MS application (or even several of them) can do a particular thing doesn't mean all MS applications can do it. A good example is that in Excel individual Worksheet cells can be formatted. We get many posts in the Project newsgroup asking how that can be done in Project, particularly in either of the Usage views. Unfortunately individual field cell formatting is not an option in Project. The only formatting available for the timescale in Project is that available in the selection lists for Units and labels found in the Timescale edit window. That window can be accessed by either double clicking on the timescale or by going to Format/Timescale. Hope this helps. John Project MVP |
Posted: 16 Aug 2005 12:04 PM PDT Project works with Tasks and Resources. When a resource is working on a task it is called an assignment. Assignments consist of an amount of work that the resource is going to do on that specific task. The work on a task consists of the sum of work in all assignments. When the resource assignment is removed, then that work is removed. Work represents the number of resource hours/days/weeks/minutes that is being expended. Further Project uses the equation Work = Duration * Units to determine what work is. Units refers to the number of resource units. Altering one of the values in the equation will affect at least one of the other values. You can see that an increase in work will require a proportional increase in duration or Units. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. <com> wrote in message news:googlegroups.com... |
Posted: 16 Aug 2005 11:25 AM PDT In article <com>, DBD <microsoft.com> wrote: DBD, You're welcome. I think the approach of treating the meeting itself as a separate task and the milestone as the completion of that task will work much better in the long run. John Project MVP |
Remaining hours extending project Posted: 16 Aug 2005 10:56 AM PDT Think about it for a minute - the duration HAS to change. Joe was assigned 100% to a task that would take 5 days. He worked 3 days and then estimates that there are still 4 days of work to do, the original 5 day estimate was off. You really only have 2 choices. He either works 8 hours a day for 4 days to do the required work, extending the curation to a total of 7 days in the process, or he somehow magically gets the 4 days of remaining work accomplished in the 2 days of time left in the the original duration, generating 16 hours of work during each 8 hour workday thus working at 200% allocation. But that's actually not possible - 100% means the resource is already working as fast as they can possibly work and the only way you really can exceeed that is to get someone else to work along with him to carry part of the load. There really aren't any other physical ways that scene could play out. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "G" <microsoft.com> wrote in message news:com... |
Posted: 16 Aug 2005 10:43 AM PDT David -- Ask your IT people to ready the following KB article: http://support.microsoft.com/?kbid=837240 In that article, they will see how many bug fixes in the Microsoft Project Professional 2003 SP1 concern how the software works with Project Server 2003. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "David" <microsoft.com> wrote in message news:com... |
assigning tasks to "sub PMs" to schedule them Posted: 16 Aug 2005 09:56 AM PDT Hi Schemir, this approach can be used if you have project server. This is a link to PowerPoint demo, how top-down planning can be done with Project Sever: http://www.bogdanov-associates.com/imgrubrs.asp?art_id=85&img=file -- Regards, Vadim Bogdanov OLAP Extender - add any custom data to the OLAP cube http://www.bogdanov-associates.com/eng.asp?rubr_id=484 "schemr" <microsoft.com> wrote in message news:com... |
Views with Gantt Chart Wizard. Posted: 16 Aug 2005 09:23 AM PDT Hi Dave, You could create a new private project. Create your views there and then transfer them via the Organizer to the working projects. Then, if one gets changed significantly, you can recover it from your private project. Mike Glen MS Project MVP Dave wrote: |
i want to know the first start date in a number of duplicate tasks Posted: 16 Aug 2005 07:26 AM PDT Did you make the dependency from the start of the milestone to the start of the task or the other way around? The first should work. The second will give the result you describe. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "Martin Theobald" <microsoft.com> wrote in message news:com... each |
In Microsoft Project, No Enterprise Options under the tools menu? Posted: 16 Aug 2005 06:55 AM PDT Hi Randall , Next time you might like to try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP Randall wrote: |
Posted: 15 Aug 2005 06:08 PM PDT Hi Bill, Welcome to this Microsoft Project newsgroup :-) Please see FAQ Item: 14. Viewing Multiple Baselines FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP John wrote: |
Posted: 15 Aug 2005 02:39 PM PDT You're welcome, Jothi:-) Mike Glen MS Project MVP Ganesh wrote: |
Posted: 15 Aug 2005 02:07 PM PDT THanks Mike. I'll try that. -- LeeY "Mike Glen" wrote: |
Posted: 15 Aug 2005 12:42 PM PDT Terry Montgomery wrote: Terry, I've been teaching CPM for years. This is hard to explain in detail here. If you'd like to contact me, I'd be happy to go over it with you. Email me if you're interested. Dave |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |