WBS Code set to unordered Character Microsoft Project |
- WBS Code set to unordered Character
- Is it possible to restrict users from baselining their entire proj
- Resource usage - how to seperate duration and hours?
- Not sure how to schedule certain tasks when they are broken up
- why summary tasks show 99% completion
- ole32.dll
- Displaying Microsoft Project Data in .html format
- Calculation error in rolled-up task
- Show Outline Level - state descriptor available?
- Macro and Button
- Ignore completed tasks when leveling resources
- How do I set the print range to a specific date?
- sample custom field formula
- Missing row indicators
WBS Code set to unordered Character Posted: 12 Jul 2005 12:16 PM PDT Reid, I didn't enter the S in the prefix box. I did figure out what went wrong, however. I followed the instructions for displaying WBS in the help file, and it tells you to use the "outline number" field in field name. When I changed it to "WBS", it worked fine. Put this one down to operator error, thanks for the help. John "Reid McTaggart" wrote: |
Is it possible to restrict users from baselining their entire proj Posted: 12 Jul 2005 12:10 PM PDT JackD -- You are WAY too funny! HA! Hope to see you at the MVP Global Summit. :) -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "JackD" <momokuri@gmail> wrote in message news:u%phx.gbl... |
Resource usage - how to seperate duration and hours? Posted: 12 Jul 2005 10:03 AM PDT Hi, There are several ways to achieve this. 1. When assigning the resource, indicate the % 2. Insert a column "Work" and enter work before assigning the resource 3. When teh resource is aleady assigned, put the task type to fixed duration and change the work value. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "New User" <microsoft.com> schreef in bericht news:com... get |
Not sure how to schedule certain tasks when they are broken up Posted: 12 Jul 2005 07:47 AM PDT In article <com>, Gabrielle <microsoft.com> wrote: Gabrielle, Maybe I shouldn't have been so negative. Normally I'm the kind of guy that likes to think outside the box for unique ways to get things done. My company used the Material Requirements Planning (MRP) software to control production although I must admit, I never did like that system - too large, complex and not very flexible in my opinion. And one of my co-workers who was more intimately involved with production planning once said that he felt he could do a better job (than MRP) on a desktop PC running Excel. I don't have any specific recommendations for production planning application software but questions similar to yours have been posted previously on this newsgroup. Why not try a search using the keyword "production". I found 20 posts since Jan of 2004. I didn't read them but there seems to be some good discussions that may prove helpful to you. Hope this helps. John Project MVP |
why summary tasks show 99% completion Posted: 12 Jul 2005 05:58 AM PDT You're welcome, Linda, glad you found a solution :-) Mike Glen MS Project MVP Lindabonita wrote: |
Posted: 12 Jul 2005 05:50 AM PDT Thanks Reid, I dont think its the problem. I'm running on a new P4 1Gb ram computer and in the background the only application thats running is Outlook. both are from office 2003. "Reid McTaggart" wrote: |
Displaying Microsoft Project Data in .html format Posted: 12 Jul 2005 03:20 AM PDT You're welcome, Radish :-) Mike Glen MS Project MVP Radish wrote: |
Calculation error in rolled-up task Posted: 12 Jul 2005 12:41 AM PDT The better! I'm still convinced a resource was assigned to theh summary task... Greetings -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "W Mather" <microsoft.com> schreef in bericht news:com... it the reduces work. double with |
Show Outline Level - state descriptor available? Posted: 11 Jul 2005 07:19 PM PDT In article <phx.gbl>, "G Lykos" <com> wrote: George, I agree with Jan's suggestion. The best way to "capture" the current displayed tasks is to use the ActiveSelection approach. I'll add just one thing to Jan's reply. I would clear the flag field before using it to identify the active tasks just in case that flag is set for some other reason. John Project MVP |
Posted: 11 Jul 2005 04:36 PM PDT Thanks, John. I think I may have to write a VBA macro with a drop down menu for different files/macro. "John" wrote: |
Ignore completed tasks when leveling resources Posted: 11 Jul 2005 03:16 PM PDT You're welcome! -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Richard Lytle" <Richard microsoft.com> schreef in bericht news:com... wrong. they message tasks why work |
How do I set the print range to a specific date? Posted: 11 Jul 2005 01:30 PM PDT Thanks Don... we were on the same page :) I was talking about Gantt charts but typed reports. :) Thanks again your directions to File, Print was what I was looking for... "DonL" wrote: |
Posted: 11 Jul 2005 12:01 PM PDT I still do not know what that means. Do you want to validate the input? That is do you want to make sure that the user enters a value between 0 and 255? If so you need to do some more complicated programming. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "wejiv" <microsoft.com> wrote in message news:com... is http://zo-d.com/blog/archives/programming/working-with-custom-field-formulas.html in to |
Posted: 10 Jul 2005 07:50 PM PDT ..Gérard, Thank you for replying. Certainly what you say is accurate. I am aware that the successor shows in the sub-project ghosted, but in the master project it still amazes me that Project changes the row numbering like that. It only happens when the tasks (Milestone) in the master is a successor vs a predecessor. When this is published, it will totally confuse the viewer who is not that familiar with MS Project. I will hear the samae question over and over again...Why are you hiding rows? Unchecking both external predecessors and successors, still does not stop the row numbers from changing. But, at least I can say with confidence that it is the application and not a corruption. Thanks a million! Kay "Gérard Ducouret" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |