MS Project 2004 - Fill color, for a cell, 'Task Name' column - How Microsoft Project |
- MS Project 2004 - Fill color, for a cell, 'Task Name' column - How
- Im building a webpage how do I access access 2002, any indepth so.
- relative start/stop times
- Earned Value Graph
- Variance Formula incorporating multiple baselines needed
- Changing Work and Duration Based on Resource Utilization
- Keeping some resource local
- Task completes before due date
- Excel link to percent complete?
- Realistic Project Resourcing
- front page
- Moving large amount of data
- Report names
- How do I write recommendation letter
- Actual hours posted to future dates
- Creating resource pool from multiple project plans
- Why Changing the hours per day in one calendar affects all others?
MS Project 2004 - Fill color, for a cell, 'Task Name' column - How Posted: 25 Mar 2005 07:37 AM PST Hi Jack on that topic .. any ideas on when the next version will be out (not that i want another version!) Cheers JulieD "JackD" <momokuri@gmail> wrote in message news:phx.gbl... |
Im building a webpage how do I access access 2002, any indepth so. Posted: 25 Mar 2005 06:39 AM PST Hi Donna if you're using Frontpage to build the website then there's a good article on the topic at http://support.microsoft.com/default.aspx?scid=kb;en-us;825502 Cheers JulieD "Donna" <microsoft.com> wrote in message news:com... |
Posted: 25 Mar 2005 02:19 AM PST ProjDateDiff works like a charm! I tried the DateDiff earlier but that gave "#ERROR" in every field. Thanks, hans "Jan De Messemaeker" wrote: |
Posted: 24 Mar 2005 06:19 PM PST Have you tried the "Analyze timescaled data in excel" add-in that comes with Project? It should export what you need to excel and you can then chart away. If you want something simpler you can write some VBA code. The following requires that you have resources assigned to each task and that the resource has a cost associated with it. If you do not have a resource loaded schedule, you can simply make a dummy resource with a cost of 1 and assign it to all tasks. Then baseline the project and run this macro. It exports into a .csv file that can be opened with excel MyFile = "c:\" & "HardwareBreakout" & ActiveProject.Name & "_" & Date$ & ".csv" fnum = FreeFile() Open MyFile For Output As fnum mystring = ActiveProject.Name & " " & ActiveProject.LastSaveDate & " " & Application.UserName Write #fnum, mystring 'write project info Write #fnum, ' Write blank line. jPeriod = 7 'select time reporting period 1 = 1 day, 7 = 1 week jStart = ActiveProject.ProjectSummaryTask.Start jEnd = ActiveProject.ProjectSummaryTask.Finish jStatus = jStart myBCWS = 0 myACWP = 0 Do While jStatus <= jEnd + jPeriod ActiveProject.StatusDate = jStatus 'CalculateProject myBCWS = 0 myACWP = 0 For Each myTask In ActiveProject.Tasks If (Not myTask Is Nothing) And (Not myTask.summary) Then myBCWS = myBCWS + myTask.BCWS myACWP = myACWP + myTask.ACWP End If Next myTask mystring = jStatus & ", " & myBCWS & ", " & myACWP Write #fnum, mystring 'write project info jStatus = jStatus + jPeriod Loop Close #fnum End Sub -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Paul" <microsoft.com> wrote in message news:com... stocks completion info but boss 700-task do this I do |
Variance Formula incorporating multiple baselines needed Posted: 24 Mar 2005 01:45 PM PST Hi CJ, I suggest you check for no baseline first using >50000 for Baseline NA and I think you could simplify the logic by doing that. Also, I use current date (reporting date) as the compare date. Also, why check for baseline start and baseline finish. Just one or the other. I check for an active baseline finish and compare . Whilst I am not checking for multi baselines perhaps use the following as a guide.(where 0 = no basline, 1 = black (completed), 2 = green, 3= yellow, 4 = Red): IIf([Baseline Finish]>50000,0,IIf([Baseline Finish]<=([Current Date]-7) And [% Complete]<100,4,IIf([Baseline Finish]<=[Current Date] And [% Complete]<100,3,IIf([Baseline Finish]>=[Current Date] And [% Complete]<100,2,1)))) Good luck with it...............Pratta "JackD" wrote: |
Changing Work and Duration Based on Resource Utilization Posted: 24 Mar 2005 01:25 PM PST Hi John I think you have to decide whether it is a fixed duration, fixed work or fixed units task. I tend to plan in duration so set all tasks by default to fixed duration; and control in work (after I baseline). I don't like fixed units. But you sound like you want the resource units to remain at 80%, so set the task to fixed units, and it won't change on you. Its a personal preference thing. You now are the keeper of the units. If you add the resource at 80% and set to Fixed Units the first time you add the resource, duration must now alter (increase) and does to 6.25 days. If you dont like that then reduce the duration to 5 days and work will decrease to 32 hrs. W=D*U, and something has to give and it sounds like you don't want it to be the resource. Regards.............Pratta "Rod Gill" wrote: |
Posted: 24 Mar 2005 12:25 PM PST Thank you so much! I would not hav eknown to take those steps. I appreciate your help. "Dale Howard [MVP]" wrote: |
Task completes before due date Posted: 24 Mar 2005 12:05 PM PST Hi KT Dales sugegstion is excellent. I am going to try that. I was just going to add that to ensure you show all tasks when you baseline to ensure baseline and EV data is recorded at the task level, and that cost data is recorded against each resource. Also, when rebaselining, tick to rollup to summary boxes. Of course, you must also key time accurately at the task level and use a timesheet tool or the Task Usage view to record time. Regards............Pratta "KT" wrote: |
Excel link to percent complete? Posted: 24 Mar 2005 10:11 AM PST In article <com>, Gueuze <microsoft.com> wrote: Gueuze, No, I'm not brilliant but I'm glad it works for you. John |
Posted: 24 Mar 2005 07:37 AM PST Hi, When the earliest start date of this additional work allows for it leveling WILL detect it and schedule it through the dips. Of course if you have scheduled this addi work to be later (be it by a constraint or by a dependency) leveling will not make it happen earlier. When you say we cannot majke the roof before the walls, the fact that the roofmakers are available does not make any change does it? HTH -- Jan De Messemaeker Microsoft Project MVP +32 495 300 620 http://users.online.be/prom-ade "Tosh" <com> wrote in message news:4242e019$0$22500$news.newnet.co.uk... |
Posted: 24 Mar 2005 07:33 AM PST Hi Frontpage is a Microsoft Product which is available for purchase - you can however, create web pages using Publisher without having Frontpage. check out microsoft.public.publisher for a publisher related newsgroup and microsoft.public.frontpage.client for front page questions Cheers JulieD "Charlain" <microsoft.com> wrote in message news:com... |
Posted: 24 Mar 2005 07:29 AM PST You get best answers in an Excel newsgroup, but the quick answer is to select the data, do Edit Copy, then Edit Paste Special, Transpose. But rmemeber, there are only 256 columns so if you're transposing rows into columns and columns into rows, you can only have a maximum of 255 rows in your source data before you run out of room in the target range. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "WHSCC" <microsoft.com> wrote in message news:com... |
Posted: 24 Mar 2005 04:25 AM PST Simpler method, go to File>Properties and change the name there. SarahK |
How do I write recommendation letter Posted: 24 Mar 2005 02:09 AM PST In article <googlegroups.com>, "davegb" <com> wrote: Dave, My lips is sealed. John |
Actual hours posted to future dates Posted: 23 Mar 2005 11:45 PM PST No, but you identified an important factor I should have included in my original post. "Rod Gill" wrote: |
Creating resource pool from multiple project plans Posted: 23 Mar 2005 05:07 PM PST Hi Baba Create the new resource file and share it with the required files files. It should have no tasks, only resources. Tools, Share Resources and set to "pool takes precedence" and ensure the drop down includes the files you intended. Also ensure that the old files are still not connected by checking both the respool and the old files i nTools Resoures/Resource Sharing All calendar setting should be done within this respool file. This should work fine for what you are doing. I woud password protect the Respool file, to preclude schedule owners from adding resources themselves. This should stop most of the problems Mike was mentioning from occurring. The respool needs to be managed centrally. I also set all calendars in the respool file. On most occasions there is no need to open the respool file for update when editing the schedules. This shoud be done weekly by the PM or administrator. Regards......Pratta "baba1970" wrote: |
Why Changing the hours per day in one calendar affects all others? Posted: 23 Mar 2005 11:01 AM PST The "hours per day" "hours per week" and "days per month" fields on the calendar options page does NOT change any of the calendars. I know that sounds like I'm crazy but none the less it's true. Those settings are conversion factors used strictly for convenience when you enter or Project displays durations, to allow you to work with data in your plan without having to mentally convert everything to hours. Project stores all its data in minutes. If you enter a task and set its duration to 3 days, Project has to know how many working hours "3 days" actually stands for. Do you work 8 hours a day so it means 24 working hours or do you work 7 hours a day so it means 21 working hours? The "hours per day" field on the calendar options page does exactly that - it tells Project *how many* hours out of the 24-hour day should considered the standard length of the working time. The calendar, accessed through the Tools menu, tells Project *which* of the minutes in the day are working time. The "hours per day" should agree with your Project calendar but setting hours per day DOES NOT change any of the calendars themselves. Also, hours per day is a global setting so you might have other calendars with differing numbers of work hours. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "subzizo" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |