User defined Fields & Filters Microsoft Project |
- User defined Fields & Filters
- Task Start Time
- Setting up the timeline
- Resetting dates in Project 2003
- Adjusting the dates in the Project
- Standard Project field Names
- Earned value calculation vs work contour
- Leveling part-time resources
- Exporting sub projects to html
- Conditional Color Coding
- Conditional formatting task usage view
- Project should let me hide non-working time on printing a Gantt Ch
- Earned Value in MSP
Posted: 21 Mar 2005 07:29 AM PST Hi Niels, 1. That depends as to what are "Special Fields". The symbol for the standard cost fields is defined in Tools, Options, View You can (through a formula) use a different symbol but only isn custom text fields. 2. Yes. As a value for the filter give "The prompt text here"? Make sure the quetion mark IMMEDIATELY follows the double quotes. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Niels Brabandt" <de> schreef in bericht news:com... from |
Posted: 21 Mar 2005 07:09 AM PST Hi Blur, Welcome to this Microsoft Project newsgroup :-) You are advised against entering dates and times as Project will apply a constraint which might affect the flexibility of your project. Enter Durations and precedence links and let Project do the calculations for you. For the first task, in Project/Project Information enter the project date with a start time and Project will schedule your tasks from then. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP blur wrote: |
Posted: 19 Mar 2005 08:49 PM PST Hi Steve (and others), I'm glad to see your response, as I've used this solution for the similar, yet different, issue of tracking distribution or contacts (where the contacts aren't truly resources) associated with a task. In my case, a task might be "Distribute report" and I've created a checklist (with checkboxes) in Word and inserted it into the Notes section. However, when one hovers over the Notes indicator, it does not show the "picture" of the checklist. Is there a way to show this visually, without actually opening up the task information box? Much thanks...L "Steve House [MVP]" wrote: |
Resetting dates in Project 2003 Posted: 18 Mar 2005 02:09 PM PST In article <com>, Tom <microsoft.com> wrote: Tom, I checked Steve's response to see if he addressed your remaining questions but he only re-iterated and expanded upon my third comment on tasks with progress. Here is more information about my original comments. A) To set (or check) the calculation setting go to, Tools/Options/Calculation tab. The default is "automatic", however if it was changed to "manual" at some point, it would keep dates from moving when the file was changed. Note that this setting is a Global setting. That is, it is applied to all projects opened rather than just to the active project. B) There are two Constraint fields - Date and Type. When talking about constraints, I normally refer to the Constraint Type field. The default entry is "As-soon-as-possible". However some users (usually new users) have a tendency to want to enter Start and/or Finish dates for tasks directly. Doing so, automatically sets a constraint depending on which was entered last. For example, if a Start date is manually entered, a constraint of "Start-no-earlier-than" is set. If the Finish date is then also manually entered, a constraint of "Finish-no-earlier-than" will be set. There is no outward indication that a constraint is being set unless the Constraint Type field or the Constraint Date field is shown in the view. However if the user makes a change and doesn't see task dates move, the reason might be due to a constraint. The fact that you checked and found "NA" in the Constraint Date field also indicates no constraint is set on those tasks. C) I think Steve's response expanded on the issue of tasks with progress. Tasks with progress will not move because they basically switch from being "the plan schedule" to the "actual schedule". Reality gets applied and "locks" the tasks in place. Hopefully this more detailed explanation helps. If not post back. John Project MVP |
Adjusting the dates in the Project Posted: 18 Mar 2005 01:57 PM PST Hi KT, See FAQ 46. "Analysis Toolbar" at: http://www.mvps.org/project/faqs.htm for a possible fix. Hope this helps. Let us know how you get along. Julie "KT" wrote: |
Posted: 18 Mar 2005 11:27 AM PST Thanks. I'll modify my responses in the future. I'm wondering if I'll ever actually use Proj 2003... More likely, I'll just wait for the next version. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Gary L. Chefetz (MVP)" <gary.nospam at chefetz.org> wrote in message news:%phx.gbl... if |
Earned value calculation vs work contour Posted: 18 Mar 2005 10:37 AM PST Hi Steve, I agree with you except for one thing. In your example, Joe only worked 3 days out of 5. Letâs suppose he was sick on Tuesday and Wednesday. Actual work for those days would be 0 and MS Project would reschedule 16 hours of work in the future. The new project end date is scheduled to be 2 days later, but duration is still 10 days because itâs based on working days, not elapsed days. In your example(at the end of day 5): % complete = 3 working days/10 days = 30% % work complete = 24 h/ 80h = 30% BCWS = 40 BCWP = 24 SPI = 0.6 CPI = 1 Those numbers are correct. Now what if Joe was not sick but had something more important to do and only managed to work the following hours on the project: Monday:2h, Tuesday:3h, Wednesday:3h, Thursday:8h, Friday:8h. Again, there are 24 hours that were performed during five days and the project end date is still delayed by two days. But duration is now 12 days instead of 10. New values are: % complete = 5 working days / 12 days = 42% % work complete = 24h / 80h = 30% BCWS = 40 BCWP = 33.73 (based on % complete) SPI = 0.84 CPI = 1.41??? In both cases Joe managed to put in the same 24 h of work during the very same 5 day period. Since we did not revise the remaining work, I can see no reason for BCWP not to be the same at the end of day 5! How do you explain a CPI of 1.41 in the second example, since Joe is not going to work less or more hours than the 80 hours that have been planned? For more fun, apply a back loaded work contour to the assignment and enter the actual values as per example one: no work on Tuesday and Wednesday. Take a look at BCWP, CPI and SPI and see how funny they have become! Now try this: apply the Task usage view, insert % complete and % work complete columns, then simulate the above examples. You will find that at the assignment level, BCWP is calculated with % work complete. But at the task level, BCWP is calculated with % complete. Every time % complete is different from % work complete, assignment and task wonât get the same BCWP even with only one resource assigned to the task. That doesnât make any sense to me. My point is that I would like MS Project to show consistency in the way earned value is calculated. Personally, I do think that % work complete is a better estimate than any tricky formulas based on duration (as demonstrated by example 2) and I would like Microsoft to add this feature to the software. Jan "Steve House [MVP]" wrote: |
Posted: 18 Mar 2005 09:03 AM PST I would suggest the difference between 4 hrs and 2.4 hours in a week is too small to worry about - just accept the over-allocation . Beware of micro management! Mike Glen Project MVP JulieD wrote: |
Exporting sub projects to html Posted: 18 Mar 2005 08:19 AM PST Julie already said that above. On the Formatting toolbar, click Show>All Subtasks. |
Posted: 18 Mar 2005 06:13 AM PST VBA will do it, based on an if statement. Let me know if you need information on how to do it in VBA. Joel com "PK Bear" wrote: |
Conditional formatting task usage view Posted: 18 Mar 2005 05:47 AM PST OOOPS. A thousand pardons. I neglected to read the subject line closely enough...... Julie |
Project should let me hide non-working time on printing a Gantt Ch Posted: 18 Mar 2005 04:31 AM PST Or you could start from the MS project web site here: http://office.microsoft.com/en-us/FX010857951033.aspx and select Suggest new content. Mike Glen Project MVP JulieD wrote: |
Posted: 17 Mar 2005 08:06 AM PST Try my add-in at www.oakinc.com/ranger - I built it to deal with hours and done/not-done reporting. Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones <com> wrote in message news:phx.gbl... Earned upon |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |