Pages

Search

Monthly Material Charge Microsoft Project

Monthly Material Charge Microsoft Project


Monthly Material Charge

Posted: 08 Mar 2005 08:13 AM PST

Jan,

Thought about that, but with 120 months and possibly 40 SW maintenance line
items, that would create a rats nest quickly.

Any other suggestions?

Thanks...



"Jan De Messemaeker" wrote:
 

Upgrade from standard to Professional edition

Posted: 08 Mar 2005 08:03 AM PST

Hi,
because i need the professional edition that can work with project server.
The VUP is the project professional version Upgrade.
thanks for your reply


"Jan De Messemaeker" wrote:
 

How to make task duration of 3 calendar months, in MS Project Mana

Posted: 08 Mar 2005 04:33 AM PST

You're welcome Eitan-F. Thanks for the feedback.
Julie

"Eitan-F" wrote:
 


Allow computer administrators control times when other users can .

Posted: 08 Mar 2005 03:53 AM PST

People from Microsoft very rarely visit this site. This is mostly just
users of MS Project. Maybe someone else has another place you could try.

Earned Values are not calculated?

Posted: 08 Mar 2005 01:13 AM PST

Found the answer:
- BEFORE entering any progress it is important to:
- Assure that any resource has a usage cost > 0
- Create a baseline

Doing this after entering progress does not help.


"Roberto" wrote:
 

Levelling Issue

Posted: 08 Mar 2005 01:01 AM PST

Hi Tosh,

When teh priority differences are large enough, Phase 1 tasks WILL get
priority. Try 0999 and 1 f.i.
However, what you have to verify is whether "Leveling can split tasks" is
ON? if not a low-priority phase 2 task that has begun because the resource
was free, will continue through its finish thus sometimes delaying phase 1
tasks

HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Tosh" <com> schreef in bericht
news:gRdXd.661$ntli.net... 
with 

after 
priority 


project should let me change the default start finish times in ca.

Posted: 07 Mar 2005 05:39 PM PST

Hi Richard

if you'ld like to send MS an email about this topic, use the following email
address
com

with Project in the subject line

Cheers
JulieD

"Richard" <microsoft.com> wrote in message
news:com... 


Project 2000 dates not correct when I change project calendar

Posted: 07 Mar 2005 02:45 PM PST

Hi Web project manager ,

Welcome to this Microsoft Project newsgroup :-)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP


Web project manager wrote: 



Project Server Acquisition

Posted: 07 Mar 2005 11:31 AM PST

These are really sales issues while these discussion groups are more for
technical support and usage issues. You might start by visiting the MS
website and reviewing the extensive library of case studies and other white
papers you'll find there. For pricing, your company's MS sales
representative is your best bet.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Harry" <microsoft.com> wrote in message
news:com... 

Tasks STILL splitting

Posted: 07 Mar 2005 08:11 AM PST

Hi Haixiang ,

Microsoft are seldom active in these newsgroups, so why not tell Microsoft
directly at this site: http://tinyurl.com/6oaw3


Mike Glen
MS Project MVP




Haixiang wrote: