Graphs for more than one resource Microsoft Project |
- Graphs for more than one resource
- Flow Charts?
- How do I set up a work group in Project 2003?
- Resource Pool file mishap on save
- Changing the Task Owner
- Resource Usage in Server
- can i group resources into teams in Project 2000
- Graphical Indicators
- How do I save/send a report/view that includes large notes?
- Lot production schedule which identifies the Numbers of Lots Released over time?
- Version
- Pasted Dates from Excel Off
- Recommendations for Project Management software, people,report,ti.
- Small amounts of total slack taking tasks of critical path
- descriptive network diagram
- View fields
- Comparison: MS Project vs. eProject
- Viewing Project Names in Resource Usage View
- Assign Resources to Crews and Crews to Tasks ??
- Row Selection Column
- Multiple Resources add to a task
- Downgrade
- Time reporting...
- Percentage Complete field not updating automatically
- Trial version of MS Project Server 2003
Graphs for more than one resource Posted: 11 Feb 2005 06:31 AM PST Tha master has spoken! So mote it be! Thanks, Jan, didn't think this would be a "yes", but you have to ask, don't you? Have a good weekend! Pete "Jan De Messemaeker" wrote: |
Posted: 10 Feb 2005 07:19 PM PST On Fri, 11 Feb 2005 17:27:34 +1300, Rod Gill donned fireproof underwear and scratched on the wall: You could also in O2K use the drawing tools. Visio was good, but has become way too bloated, IMO. I still use it at work, but have abandoned it at home. You could also use kvivio (http://www.thekompany.com/projects/kivio/) for a more professional look. I've been using it more often for my projects. It is very nice and - unlike the Visio-pig - puts out standard XML formatted documents. HTH -- kai www.perfectreign.com a palm tree nodded at me last night, he said, you look so pale... |
How do I set up a work group in Project 2003? Posted: 10 Feb 2005 06:59 PM PST Hi, As Rod mentions the preferred method is Project Server. However the Workgroup features using mail are available as a separate download. See: http://support.microsoft.com/default.aspx?scid=kb;en-us;818337 Hope this helps. Let us know how you get along. Julie "psdcc" wrote: |
Resource Pool file mishap on save Posted: 10 Feb 2005 12:23 PM PST I suspect you have corrupted your resource pool. If at any time you over-wrote a copy of one of your projects, renamed it or moved it without first disengaging from the pool you will sooner or later get a corruption. Be very careful. Open the pool In each file select use own resources and SAVE Delete the pool file and create a new blank project for the new pool Share in each project. All resources are copied automatically to the pool. Close and SAVE all projects. Never, move, copy or over-write any of the four files without first unsharing. -- Rod Gill Project MVP "Ol' MSCS Hack" <net(spammers suck)> wrote in message news:com... |
Posted: 10 Feb 2005 09:43 AM PST Priyu -- That guy needs to open the project on his own computer and do the following: 1. Click Collaborate - Publish - All Information 2. Make sure the "Entire project" option is selected at the top of the dialog 3. Select the "Become the manager for these assignments" option 4. Click OK Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Priyu Nayak" <microsoft.com> wrote in message news:com... |
Posted: 10 Feb 2005 09:35 AM PST Ignacio -- In Project Server 2002 and 2003, when you apply the Resource Usage view, you see each resource's assignments across all projects in the portfolio. For each project team member, you will see the individual tasks in any project you have open, plus a single line representing the tasks in all other projects in the system. The software is performing as expected. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Ignacio" <microsoft.com> wrote in message news:com... |
can i group resources into teams in Project 2000 Posted: 10 Feb 2005 09:03 AM PST Ian, I had a similar problem - I have a multi project plan, on which 19 resources, split into four teams may work. Have you tried inserting a new field into your plan, renaming it as (somewhat imaginatively) "Team", and entering "Team01", "Team02" etc into this field? This is also really useful when you want to filter your plan to show just the work carried out by a particular team or teams. Hope this helps Pete "Ian Louth" wrote: |
Posted: 10 Feb 2005 01:57 AM PST Hi Steve, Hopefully it was pointing you to review the printer driver setup for the failing PC. Check it has the latest drivers. Mike Glen Project MVP Steve Scott wrote: |
How do I save/send a report/view that includes large notes? Posted: 10 Feb 2005 01:25 AM PST In article <com>, "Mongo" <microsoft.com> wrote: Mongo, See my reply to your other post in this newsgroup. John Project MVP |
Lot production schedule which identifies the Numbers of Lots Released over time? Posted: 09 Feb 2005 10:49 PM PST Thank you for your response Steve. I was kinda hoping that MS Project had a function (or method) that provided a "deliverable" output shedule. The "Lots Released" field is associated with a particular task (Clearance of Titles) and that's where i am trying to derive the report (or output) information (or using the summary task associated with that particular stage). I could complete what i require in Excel, however i prefer to use Project for sheduling the contributing tasks associated with the Development process (as you mention). In that case i'm using two applications to provide output information common to contributing inputs, which is undesirable. I'm going to persue trying to use Project as you've mentioned. Thanks again. Troy send.hotmail.com "Steve House [MVP]" <send.hotmail.com> wrote in message news:phx.gbl... |
Posted: 09 Feb 2005 04:59 PM PST Thanks! that helped. "JackD" wrote: |
Posted: 09 Feb 2005 01:57 PM PST Thanks Bob, That was it! I never heard of the 1904 date system before. I did get the file from someone else. Changing it, changed the source data. I guess it could have added a number to correct for the difference but I just copied the dates to a text file then copied them to MSP from there. Thank again, "Bob" wrote: |
Recommendations for Project Management software, people,report,ti. Posted: 09 Feb 2005 01:29 PM PST Hello, Our company provides solutions that you are looking for. Please visit us at http://www.tenrox.com Thank you "=?Utf-8?B?Y2F0dGltZXNzcXVhcmU=?=" <microsoft.com> wrote in message news:<com>... |
Small amounts of total slack taking tasks of critical path Posted: 09 Feb 2005 01:17 PM PST Big alarm is going off here!!! How did you set the standard calendar to 6 hours per day without changing the working hours in Tools/ChangeWorkingTime? If you are referring to the Tools/Options menu, Calendar page, settings for Hours per Day & Hours per Week plus the settings for Default Start and Default Finish, you need to be aware that those fields do NOT affect the working hours and times of any of the calendars, Standard or otherwise. The Hours per Day and Hours per Week settings are conversion factors to allow you to enter durations in units other than hours. Durations are actually stored in Project in minutes. When you enter a task duration of "3 days," Project needs to convert that into minutes before writing it into its internal data tables. When you look at a duration value, the duration column in the the Gantt chart for example, Project reverses the conversion, retrieves the minutes and converts that value back into the units you like to see the duration dispalyed in. If the Hours per Day setting is the default 8 hours, when I enter Task X and say its duration is 3 days, Project knows I really mean 3*8 or 24 working hours * 60 minutes per hour and stores the value 1440.0 as the task duration. When I look at the Gantt chart, I'll see 3 days. Now here is an interesting observation - if that task starts Monday and we are using the default Standard calendar, it will start Mon 0800 and finish Wed 1700, 24 working hours later. BUT, if I now change the hours per day on the calendar options page to 6 such as I bet you've done, it will now show the duration to be 4 days EVEN THOUGH the task still starts Mon 0800 and ends Wed 1700, no change in the schedule of the task at all. Why? Because we've changed the conversion factor. 24 hours is 3 8-hour workdays but 4 6-hour workdays and all we have actually changed is what we choose to call a day. The *calendar* hasn't changed and still shows work hours of 0800-1200 and 1300-1700, meaning each 24 hour time period according to the clock on the wall now actually contains 1.33 working days, what we're calling a "day," in it. We work 8 hours on each day of the week but a "day" is defined as a 6 hour time block, thus each day of the week regular working shift has more than 1 day's worth of work taking place in it. For Project's calendars to make sense, the work hours defined for the Project calendar and the hours in the "Hours per Day" field should normally be equal but changing one does not automatically change the other. The Default Start and Default Finish fields on that page are equally not what they seem. All date fields in Project are actually date/time fields. When Project calculates a value for one of those it uses the Project Calendar to determine where on the clock to place the time. Likewise, when you use a pull down calendar, like when you click on the pull-down button to pick a constraint or enter the Project Start date, it also uses to Project Calendar at the moment to determine what the start time on the selected date will be. But if you *manually* type a date, for instance by typing the date a task should start, *without* typing a time, Project must supply some value. It gets the one it uses from the Default Start field on that calendar options page. Changing that field DOES NOT change the working hour definitions you see when you're editing the calendar in ChangeWorkingTime. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Len" <microsoft.com> wrote in message news:com... |
Posted: 09 Feb 2005 12:53 PM PST View menu. Select network diagram. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Ramesh" <microsoft.com> wrote in message news:com... project |
Posted: 09 Feb 2005 09:36 AM PST Hi, Yes, you can put the mouse pointer about 1-2 mm to the right of the column to the left of the hidden column and try to drag and drop. I'm personally so clumsy about this that editing the table is way faster :-)) HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "jlbreyer" <com> schreef in bericht news:25bd01c50ecd$debe38a0$gbl... |
Comparison: MS Project vs. eProject Posted: 09 Feb 2005 08:03 AM PST On Wed, 09 Feb 2005 10:03:14 -0600, Mervin Williams donned fireproof underwear and scratched on the wall: Might help if you provided a link to at least eProject's website - http://www.eproject.com. Maybe you could write one? :) -- kai www.perfectreign.com a palm tree nodded at me last night, he said, you look so pale... |
Viewing Project Names in Resource Usage View Posted: 09 Feb 2005 06:33 AM PST Hi Ian, That is absolutely logical. You simply do not see tasks in Resource Usage but assignments (which have text1 etc.fields of their own) You can read all about it in http://www.mvps.org/project/faqs.htm Faq 37: custom fields in tables. OBTW, it would be advisable you use the true names of the views. When you mention Resource Usage Graph, do you mean Resource Usage (which I suspect) or Resource Graph)? HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Ian" <ca> schreef in bericht news:googlegroups.com... |
Assign Resources to Crews and Crews to Tasks ?? Posted: 09 Feb 2005 06:17 AM PST Hi again, I read your comment in the other post. A lot of things can be imagined in VBA (although I never actually programmed this) My answer was strictly on out of the box features! HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Glenn" <microsoft.com> schreef in bericht news:com... |
Posted: 09 Feb 2005 05:41 AM PST Yea! I helped! ;-) Glad the problem is solved. Feel free to ask questions anytime. It gives my life meaning to be able to help others! ;-) Sarah |
Multiple Resources add to a task Posted: 09 Feb 2005 05:41 AM PST Glad we could help - feel free to ask more -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Ignacio" <microsoft.com> wrote in message news:com... |
Posted: 08 Feb 2005 01:38 PM PST Yes, no problem, except they won't be able to see any of the data in fields added in more recent releases (the multiple baselines, for instance). -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Karen" <microsoft.com> wrote in message news:1f7701c50e26$7d0087a0$gbl... |
Posted: 08 Feb 2005 01:17 PM PST Kevin, No, you can't, leastwise easily ;-( This can be done by a VBA procedure, but it's not an easy one. The Import via a map is able to import data in columns, not timephased data. Gérard Ducouret "K Major" <microsoft.com> a écrit dans le message de news:com... there a basis work the it |
Percentage Complete field not updating automatically Posted: 08 Feb 2005 11:25 AM PST Hello Brinda, Aren't you looking at the "Physical % Complete" ? If so, it'll never update by itself ! This field is allways entered by the operator to alter the calculation of the BCWP. Gérard Ducouret "Brinda Bhatt" <Brinda microsoft.com> a écrit dans le message de news:com... update |
Trial version of MS Project Server 2003 Posted: 08 Feb 2005 09:21 AM PST Yes. It is called "Enterprise Project Management Solution Evaluation Kit 2003" 0903 Part No. X10-00604 It is a 120 trial version of Project Professional 2003 and Project Server 2003. "Celtic" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |