Filtering on late milestones Microsoft Project |
- Filtering on late milestones
- Adding a resource in the middle of the task
- Assigning a numeric value to a month
- entering actual duration question
- pushing back a whole project
- task type question
- Project extension questions
- start & finish dates - what happens to dates inbetween
- How do I weight percentages using Project 2000?
- How do I show the % complete (planned) that will change my status.
- Task completed at 50%
- is venus made of rock or gas
- Administrative projects of Project server
- Calculating Overtime
- Task occurring on the same day each week
Posted: 06 Jan 2005 02:23 PM PST Actually I'm not quite there. In the filter I created I put a line Finish is less than today but what happens is that it plugs in today's date and this date remains the same even when the date on my PC changes. I expected that each time the Filter was applied it would see 'today' and apply the current date. Can anybody tell me how to do this? Thanks Dave "Dave Barr" <com> wrote in message news:%23jjOj$phx.gbl... |
Adding a resource in the middle of the task Posted: 06 Jan 2005 01:36 PM PST Hi Scott, From the Gantt chart split your screen (Window -> Split) to show the task form at the bottom. Click your secondary mouse button in the task form at the bottom to show the shortcut menu. Choose Resource Schedule from the shortcut menu. Pick the resource's name from the drop-down under the Resource Name column, enter the work (if desired) and then in the Start column enter the start date for that resource. Click OK in the task form and you are there. Hope this helps. Let us know how you get along. "ssiegler" wrote: |
Assigning a numeric value to a month Posted: 06 Jan 2005 01:21 PM PST Hi Mark, Not sure if this is what you are looking for, but here's a suggestion: Insert one of the spare number columns into the Task sheet. Create a formula for the column of : Month([Start]) This will return 1 for January, 2 for February etc. If your project starts in May change the formula to: Month([Start])-4 to get May equal to 1. Hope this helps. Let us know how you get along. Julie "Mark" wrote: |
entering actual duration question Posted: 06 Jan 2005 12:11 PM PST Be careful! You said "actual 12 hour duration" and that is incorrect. The actual duration is 12 days, period, accept it. It is essential that you internalize the concepts as MS Project defines them (and MSP follows the ANSI standard PMBOK definitions and practices very closely), not as you think they should be defined <grin>. That being said, yes, if you split the task the gaps are treated as non-working time and the duration would then be shown as 12 hours. Actually, the way you described the task initially, I'd strongly suggest you make it three separate 4-hour tasks altogether and schedule each session as an entity totally independent of the other two - there's nothing that says similar or even identical tasks cannot occur many times during a project. To me that is a far more accurate model of reality. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jack" <microsoft.com> wrote in message news:com... |
Posted: 06 Jan 2005 06:29 AM PST Julie, 37° C ! waho.... I live in Paris. Today, the weather is fine : 10°C it's not too bad during wintertime. Cheers, Gérard "JulieD" <net.au> a écrit dans le message de news:phx.gbl... 1am |
Posted: 06 Jan 2005 06:03 AM PST Thank you for the response, Steve. I understand and agree with everything that you said. But with a situation like this (a Fixed Duration task - a set length meeting where two resources will be there for the whole of 16 hours [which should maen each resource would be at 100% for how could you only be 50% at a meeting where you're there 100% of the time]) wouldn't you agree that MS Project effort-driven feature trully doesn't accomodate the reality of the situation with a Fixed Duration task type? "Steve House [MVP]" wrote: |
Posted: 06 Jan 2005 06:01 AM PST Not really much of a difference, really. The files are the same. The mpt's will be saved by default to the template directory while mpp's are saved to the data directory. Opening and mpp, editing it, and hitting "save" doesn't prompt for a new file name. Opening an mpt and editing prompts for a new filename when saved and changes the extension of the edited file to mpp by default. That's really about it. Here's how I'd use each. Imagine you're a real estate developer building a housing subdivision offering houses with 5 different floor plans. Each model of house has a basic construction plan but each one you build is somewhat customized for the client. I'd create my generic plans for each model and save them as an mpt template. When Mr & Mrs Smith purchase one of your 3 bedroom bungalows, you create a new project file based on the 3btbunglow.mpt template, changing the Project Start date in the new file as approriate and customizing the plan as necessary to incorporate the client's preferences and options, then save it as Smith'sBungalow.mpp, upon which it becomes the working plan for their specific unit. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jack" <microsoft.com> wrote in message news:com... |
start & finish dates - what happens to dates inbetween Posted: 06 Jan 2005 01:55 AM PST Good idea! -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "JulieS" <microsoft.com> wrote in message news:com... |
How do I weight percentages using Project 2000? Posted: 05 Jan 2005 06:25 PM PST Steve, thank you for a very thoughtful response. It seems to make sense and I will give it try tonight. I appreciate your time! I may seek your services again in the future. Mark "Steve House [MVP]" <send.hotmail.com> wrote in message news:phx.gbl... |
How do I show the % complete (planned) that will change my status. Posted: 05 Jan 2005 05:07 PM PST I agree with your logic, AND I am greatful for the help; But I am trying to encourge the users to enter the an appropriate value if they believe they are on target. In the simplest of uses, if I use the default 'status' column it dynamically changes based on the % complete entry. If for example I move the date and "start" the task on the 10th (as you suggest), it changes the value of the status from "late" to "future task" (assuming the same information as below with the 33% complete). According to "Help on Status": How Calculated If the task is 100 percent complete, then Microsoft Office Project 2003 sets the Status field to Complete. If the task start date is greater than the status date, then the Status field contains Future Task. If timephased cumulative percent complete is spread to at least the day before the status date, then the Status field contains On Schedule. If the timephased cumulative percent complete does not reach midnight on the day before the status date, then the Status field contains Late. Therefore what I'm trying to display is the timephases cumulative percent complete as o midnight the day before the status date. "Steve House [MVP]" wrote: |
Posted: 05 Jan 2005 12:49 PM PST Hello Stefan, Yes, ... if you estimate the Remaining Work at 10 hours ! NB : Don't enter the %Complete, but the actual Work and the remaining Work. Project will calculate the %Work Complete. Gérard Ducouret "Stefan Robert" <ca> a écrit dans le message de news:2005010515444475249%.. |
Posted: 05 Jan 2005 12:17 PM PST The planets are grouped into two major categories - the inner planets from Mars inward are referred to as the Rocky planets. The outer planets are called the Gas Giants because they largely consist of methane etc. I think of them as the "Bullwinkles" as in "Rocky and ..." ROFL -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "little miss cutie patutie" <little miss cutie microsoft.com> wrote in message news:com... |
Administrative projects of Project server Posted: 05 Jan 2005 11:17 AM PST Hi Glimmer, Try posting on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen Project MVP glimmer wrote: |
Posted: 05 Jan 2005 09:31 AM PST To the best of my knowledge, Project doesn't calculate OT. You enter OT in the Ovt. Wk column (I usually split the screen while in the Gantt view, right click and select Resource Work). You tell it how many hours of OT the resource will work on the task. Project tracks this work, but doesn't schedule it. Of course, you get see it in the Resource views if you tell it to display Overtime. |
Task occurring on the same day each week Posted: 05 Jan 2005 09:21 AM PST What do you mean by a "top down plan" and how does that contrast with, contradict, or preclude having a recurring task???? I'm familiar with the concepts behind top-down estimating and top-down budgeting but the term "top-down plan" is a new one on me. How is that different from a standard project WBS that starts with the project's major deliverables and breaks them down further and further until you get to the detailed description of all the various pieces of work that create said deliverables? -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Bob Truetken" <cc> wrote in message news:phx.gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |