duration one day, ends next day instead of same day Microsoft Project

duration one day, ends next day instead of same day Microsoft Project


duration one day, ends next day instead of same day

Posted: 21 Dec 2004 09:07 AM PST

Hi Luigui,

First, set your date format to show you time as well as dates. (Tool
->Options, View tab, set the Date format to show time.) Project calculates
information to the minute, so viewing time as well as the date can frequently
help track down problems.

On the Calendar tab in the Options dialog box, correct the default start and
end times as well as modify the number of hours in a day and a week. It is
this definition of "days" and "weeks" that Project uses when you enter task
durations. So if your project calendar was modified for a 7.5 hour work day,
but the definition of a "day" was 8 hours, the task will not end until 1/2 on
an hour into the next working day.

You may also want to check the start time of your Project (Project ->
Project Information) to verify that the project is starting at the correct
time.

Hope this helps. Let us know how you get along.

Julie

"Luigui" wrote:
 

How can I access a project 97 document when I have 2003?

Posted: 21 Dec 2004 07:53 AM PST

Hi Deb,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 27. Project 4 to Project 2000

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP


deb wrote: 



Unable to outdent first task below summary task in Project 2003

Posted: 21 Dec 2004 05:36 AM PST

Thanks to both of you for a fast reply!

/Joacim


"Joacim Stappe" <com> skrev i meddelandet
news:OFVxd.11664$telia.net... 
indenting 


Customize Report Columns

Posted: 21 Dec 2004 05:29 AM PST

You are welcome Nestor. Glad to have helped out and thanks for the feedback.

Julie

"nestor" wrote:
 

MS Project 03 - Will not save file, gives "file cannot be opened".

Posted: 20 Dec 2004 02:13 PM PST

You're welcome, and thanks for the feedback :-)

Mike Glen
MS Project MVP





Brian wrote: 



DateDiff funtion - what is interval?

Posted: 20 Dec 2004 01:26 PM PST

From VB help for datediff (which, I strongly suspect, is the model for
pjdatediff):

yyyy Year
q Quarter
m Month
y Day of year
d Day
w Weekday
ww Week
h Hour
n Minute
s Second


"Steve House [MVP]" wrote:
 

What is slippage?

Posted: 20 Dec 2004 12:25 PM PST

Hi Steve

should they have used a finish / start relationship between the "pack
sleigh" and predecessor tasks in this situation?

Cheers
JulieD


"Steve House [MVP]" <send.hotmail.com> wrote in
message news:phx.gbl... 


What happens when I drag a Gantt bar in 2003?

Posted: 20 Dec 2004 12:20 PM PST

Hi Dave,

Were the tasks 100% complete? I can happily drag a completed task around
without constraining it - it just changes the actual start and finish dates.

Just a thought.

Julie


"davegb" wrote:
 

How to assign quantity of resources?

Posted: 20 Dec 2004 12:05 PM PST

Hi Glenda,

Welcome to this Microsoft Project newsgroup :-)

As I understand you, you just assign the group by name and the number of
units you require. If you do that, you cannot then assign an individual on
another task - its the group or the individuals by name.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :-))

Mike Glen
MS Project MVP



Glenda Padilla wrote: 



What column reflects actual duration of the project?

Posted: 20 Dec 2004 09:13 AM PST

Yes, I think you've nailed it. Thanks a bunch.

"Steve House [MVP]" wrote:
 

Phases question

Posted: 20 Dec 2004 08:23 AM PST

Hi Jack,

Since your Phase column appears to be an alias for Text4;
And since Text4 is a custom field;
It will BY NO MEANS change anything (unles somebody programmed a macro)
So it is indeed just a matter of indenting.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
"Jack" <microsoft.com> schreef in bericht
news:com... 
indenting 


How do I export the Ganatt Chart in *.html and keep the colorful .

Posted: 20 Dec 2004 07:45 AM PST

Hi Matt

use the camera icon (standard toolbar) to take a gif of the gantt chart
- format the timescale correctly first and then select the task names of the
tasks to include - i then use "selected rows" when creating the picture

then use the file / save as web page wizard to create a html page
incorporating the gif. (in the wizard you'll see a check box about
incorporating an image file in the HTML page)

Cheers
JulieD

"matt" <microsoft.com> wrote in message
news:com... 


project 2003 will not display baseline or progress

Posted: 19 Dec 2004 11:13 PM PST

Hello John,
What is the name of the View your are working in ? Gantt Chart ? Tracking
Gantt ?
Have you checked in Format / Bar Styles... that you have the following bar
styles :
- Progress : From Actual Start, To complete Through
- Baseline : From Baseline Start, To Baseline Finish


Gérard Ducouret


"John S" <John microsoft.com> a écrit dans le message de
news:com... 
reformating. 
some 
baseline?


Customize Fields Formula

Posted: 18 Dec 2004 10:41 PM PST

You might also check to be sure that the file itself does not contain the
old customized fields.
Do it the same way with the organizer, but look on the right side and see
what is embedded in the file itself.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
message news:phx.gbl... 
and 
fields 
occurs 
tried 
occur 
can