Actual Material Usage Microsoft Project |
- Actual Material Usage
- Creating an Outline with Summary Tasks
- Recurring Tasks! ;-)
- Key Benefits of Portal Integration
- Duration more than difference between Start and end date
- Does anybody know how to output the gantt chart from Microsoft Project to Microsoft Word?
- Immediate Successor
- 2 week look ahead
- 2 week schedule rotation
- Keying in start and end dates for split task sections
- Can I use Virtual PC on my G5 to use MS Project?
- Separting costs for internal and external resources
- Summary Task Duration Adding to Fraction
- More Start and Finish columns
- No task display unless I make it a subtask
Posted: 28 Dec 2004 01:55 AM PST Thanks for reply, That is done but how does it get populated. You know we enter the %complete which is for work complete. but if i say the work is completed 100% but instead of planned usage of 10 units of materials, i have used only 6 units how do i track that. I just wanted to track my planned materials vs actual material consumed. So as we have Planned date and actual date, can we have Planned resources and Actual resources. |
Creating an Outline with Summary Tasks Posted: 27 Dec 2004 08:23 AM PST Hi Ernest, Welcome to this Microsoft Project newsgroup You need to indent the 3 tasks below the summary task to make it a summary. Select the 3 tasks and click the indent button on the toolbar. See my series on Microsoft Project in the TechTrax ezine, particularly #2 about Outlining. at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on Mike Glen MS Project MVP Ernest Rawls wrote: |
Posted: 27 Dec 2004 07:11 AM PST You're welcome, Louise :-) Yes. You will then have to link the components as necessary. If you have many of these, you might consider automating the process with some vba. If so, try posting on the developer newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/. Mike Glen MS Project MVP Ladymuck wrote: |
Key Benefits of Portal Integration Posted: 27 Dec 2004 05:31 AM PST You're welcome, Stefan :-) Mike Glen MS Project MVP Stefan Rauchegger wrote: |
Duration more than difference between Start and end date Posted: 27 Dec 2004 04:32 AM PST Thanks very Much Mike Recreating your project was to only get familiarize with MS project. I have read all your articles and believe me they are great. Well your response solved my first question but not the 2nd. I am still getting mismatch hrs I even checked the Tools->Options->Calendar and the working time, but still the same result. Mike i also wanted a suggestion from you. I am trying to create an Inventory Schedule. I have the list of tasks and the materials(equipments) required to complete the task. Is it possible to know from the schedule the total inventory consumed (in case of works done) and total inventory required for future tasks. This will help me know when to order for new inventory (in future). I hope the above makes sense and appreciate your effort to solve my problem. Thanks Pradeep Mike Glen wrote: articles 15 starts on summary working survey end still same you can seen at Mar of that Jane help |
Does anybody know how to output the gantt chart from Microsoft Project to Microsoft Word? Posted: 26 Dec 2004 04:13 PM PST Hi sic, Welcome to this Microsoft Project newsgroup :-) Please see FAQ Item: 16. Project Viewer. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP sic wrote: |
Posted: 26 Dec 2004 09:08 AM PST Never, ever, under any circumstances, assign resources to summary tasks. Summaries are roll-ups of the performance tasks and in a very real sense don't actually exist as tangible events like "real" tasks do - they are purely artifacts inserted for convenience in organization and reporting. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Ken Kast" <com> wrote in message news:%phx.gbl... |
Posted: 24 Dec 2004 11:41 AM PST John wrote: I was talking about the clicks for using a date picker. -- ___ Brian K Project MVP http://www.projectified.com Project Server Consultant http://www.quantumpm.com |
Posted: 23 Dec 2004 11:51 PM PST Thank you Brian, I'll experiment with this. -Don "Brian K - Project MVP" wrote: |
Keying in start and end dates for split task sections Posted: 23 Dec 2004 08:41 AM PST Yes - I'd forgotton that avenue! Mike Glen Project MVP JulieS wrote: |
Can I use Virtual PC on my G5 to use MS Project? Posted: 23 Dec 2004 08:41 AM PST On 12/24/04 5:26 PM, in article microsoft.com, "Brian K - Project MVP" <com> wrote: I have 2 GB (the max I can put on my iMac G5). I have allocated 256 MB to VPC. For some reason the PC info window says that there are 64 MB of hard ram and 100 of available ram! Go figure! Ken Gorelick |
Separting costs for internal and external resources Posted: 23 Dec 2004 07:11 AM PST Hi ProjectFly, I can arrive at a partial answer using the Resource Group field in a task view. Enter the Internal or External information on the resource sheet in the Group Field. You may then add the Resource Group field to any task view and see which group the assigned resources are from. You can then add one of the custom Cost fields and show costs where only internal or external resources are assigned using a formula like: IIf([Resource Group]= "Internal", [Cost], 0) Use another cost field to test whether the resource group equal "External". The challenge becomes when you have both internal and external resources assigned to a single task. I have not yet be able to come up with a way to parse that information and determine which part of the cost belongs to which resource in Project. Another option is to start with the beginning suggestion (use the resource Group field) and then export that information to Excel. I used the Export Map "Task List with embedded assignment rows" and modified the map to add the Resource Group field. Once in Excel, it becomes much easier to manipulate the data. Hope this helps partially and perhaps another reader can respond with a better answer. I'll keep plugging away and will post with a possible solution when I find one. Julie "ProjectFly" wrote: |
Summary Task Duration Adding to Fraction Posted: 23 Dec 2004 06:17 AM PST You may have an overlap of 2 or more tasks within the summary or there may be a delay in the link between a couple of tasks. The duration of a summary task is not the aritmetic sum of the durations of its component subtasks except by accident. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Tina Winter" <Tina microsoft.com> wrote in message news:com... |
Posted: 22 Dec 2004 05:20 PM PST You're welcome. Thanks very much for the feedback. Julie "headware" wrote: |
No task display unless I make it a subtask Posted: 22 Dec 2004 11:17 AM PST Hi PJ, Is the Gantt bar for the "mystery" task formatted in white? Select the task and choose Format -> Bar from the menu and change the color to some other color. Does it appear now? Julie "PJ" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |