Save Project schedule as pdf? Microsoft Project |
- Save Project schedule as pdf?
- resources viewing reassigned tasks in PWA
- Load an Enterprise project custom text field
- Viewing multiple projects in one report (Project 2000 OR 2003)
- Is it possible..
- Double booking the same person
- Importing timesheet data into Project.
- Milestone list
- How do I move a column
- How do I get total percentage of cost for work completed?
Posted: 28 Oct 2004 02:26 PM PDT Try printing to PDF writer. You will need PDF writer on your machine "kmathis" wrote: |
resources viewing reassigned tasks in PWA Posted: 28 Oct 2004 09:45 AM PDT Andy -- Ask the former resource to select the task on his/her timesheet in PWA and to click the Hide button. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant Denver, Colorado http://www.msprojectexperts.com "We wrote the book on Project Server" "Andy" <microsoft.com> wrote in message news:com... task |
Load an Enterprise project custom text field Posted: 28 Oct 2004 09:39 AM PDT Is it possible to store the data in the database with code? Can I write a VBA macro to load the SQL-Server database table? Which table might hold the enterprise project text 4 field? or how can I identify the right table? Which objects load this field? (I dread typing all these names.) Thanks for your help. "Dale Howard [MVP]" wrote: |
Viewing multiple projects in one report (Project 2000 OR 2003) Posted: 28 Oct 2004 06:41 AM PDT Joey, I suggest you start by creating a consolidated master of the 6 individual projects. First, open a new blank project. Then go to Insert/Project. In the window that appears, select all 6 individual projects and hit "Insert". The default setting will create a dynamically linked master. That is, changes made to the individual files will be reflected in the master and, for the most part, changes made to the master will be reflected in the individual subprojects. Once the master is created, you can create virtually any type of report you want - some by customizing the view parameters, some using the built-in Reports feature and some using VBA. Hope this helps. John Project MVP |
Posted: 28 Oct 2004 06:35 AM PDT Steve, Thank you so very much for your response. I really appreciate it. Thanks again "Steve House [MVP]" wrote: |
Double booking the same person Posted: 28 Oct 2004 04:25 AM PDT That's a tough one and points up the difficulty of using Project for scheduling things that really aren't projects or project tasks at all. Projects have discrete beginning and ending points and a limited set of deliverables and each task within them also have discrete beginnings and endings. They begin when work is first performed and end when the deliverable is completed. Your specing and testing tasks really are on-going line-of-business activities and violate those fundamental definitions of a project task - for example, there is no single deliverable whose creation will cause speccing to cease for all time. The deliverables for on-going activities regenerate themselves - a new one pops up as soon as the current one is completed - and continue marching on one after the other in perpetuity. The work creating them doesn't have a beginning or end but continues on forever at the rate the deliverables materialize. One way to do it, sort of, is to create a task "spec" and a task "test" both with 1 year durations. There are 20 work days in a month, on average. Assign Bill to "spec" at 5/20 or 25% and to "test" at 10/20 or 50%. He can sort out for himself which days he does what. That leaves 25% of his work month for other things. The monkey wrench in the works comes up when you try to actually schedule the 5 day task with a deadline to occur on specific dates in that framework. What should happen? Are we only concerned with averages, as long as we get it done by the deadline, or should work on speccing and testing stop while he does this new task? If so, what happens to the man-hours we would have devoted to speccing and testing? And what do you mean by "5-day task" in the first place - is that 5 days of full time work, 80 man-hours, 5 days at 25% effort, 10 man-hours, or just what? -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Rob List" <Rob microsoft.com> wrote in message news:com... |
Importing timesheet data into Project. Posted: 28 Oct 2004 02:43 AM PDT Hi Noel, Yes VBA is definitely a good lead. Have a look in microsoft.public.project.vba, read Jack D.'s post of today Re: Analyse timescale data in Excel It has a link to his site shere tehre is a code that links timescale data in Project into Excel. It could give you some ideas of how to tackle - I hope VB or VBA aren't that foreign to you? HTH -- Jan De Messemaeker Microsoft Project MVP +32 495 300 620 http://users.online.be/prom-ade "Noel" <microsoft.com> wrote in message news:com... that map, was data the how |
Posted: 27 Oct 2004 11:53 PM PDT Hi, Thank you for the tip, but I can see I need to be more specific. I want to do a milestone list for ALL projects in the server. As project manager, I want an overview of milestones in the different projects. I have tried the Assignment Views, but I cannot manage to make the milestones come up because they are not assigned to any ressource. "Rod Gill" wrote: |
Posted: 27 Oct 2004 05:23 PM PDT Hi Bobs, Welcome to this Microsoft Project newsgroup :-) You might like to see FAQ Item: 11. Hidden Column. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP bobs wrote: |
How do I get total percentage of cost for work completed? Posted: 26 Oct 2004 01:43 PM PDT Glad I could be of help ... "Noel" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |