How do I view my Gantt chart in WORK rather DURATION? Microsoft Project |
- How do I view my Gantt chart in WORK rather DURATION?
- Bug Tracking with Project Pro 2003
- VB error: "Error accessing file. Network connection may be lost."
- How do I change the Gantt Chart Report Begin Date?
- Discrepancy with work hours
- Integrating an Access Query into Project
- View tracking information
- Import Project Standard 2003 tasks and deadlines to Outlook 2003
- Compare Project Versions - Run-time error '13': Type mismatch
- Max File Size in Proj Pro / Server
- Project PWA Project Center views
- How do I split a microsoft project task that takes x hours over .
- Is there a good Lag time report I can run?
- Specifying Time of Day Task is due
- Gap in the schedule
- Report problems
- change font color of tasks or color of bars from VBA
- How do I set up an MS Project where resources are working on the .
- Progress Bar Not Showing
- One Gantt Bar showing 3 different data
- Calendar Goes to 1987
- Project 2000 calendars driving me mad! Help pls.
- How do I force a resource to work on a task until it's done?
- Blocking out Holidays and row adjustment questions
- Actuals in PWA vs. actuals in MS Project Pro
How do I view my Gantt chart in WORK rather DURATION? Posted: 18 Oct 2004 05:05 AM PDT Hi GaffaUK, You cannot actually view a Gantt Chart for "work", because the Gantt Chart shows the Start/Finish dates for the task, and not the work content. You can, however, insert column called "work". Moreover, If you care to go to the Task Usage, or Resource Usage views, you can then see how the work is profiled on a daily, weekly, monthly basis. I have a concern, though, that you might be incorrectly interpreting the Units. They are not an "efficiency" rating. It is their "level-of-effort" on the task, thus normally shown in hours. If the resource is going to take 5 days (full-time) to execute a task, then it's still 5days x 8 hrs/day = 40 hrs.....and the "units" should reflect the true content of the work and their true level-of-effort (1.0 or 100%). The fact that it should take only 4 days x 8 hrs/day = 32 hrs is an irrelevance....although this could be shown in the baseline. If your interpretation is: "There is four days of full-time work, but spread over five days", then that's fine....your level-of-effort (units) is correctly showing 0.8 (80%). This means, however, that the resource is only working on your task for 80% of his time, and is nothing to do with efficiency. HTH. James. G "GaffaUK" wrote: |
Bug Tracking with Project Pro 2003 Posted: 17 Oct 2004 07:20 PM PDT "Sam-I-Am" <com> wrote in message news:<phx.gbl>... You might want to take a look at Visual Intercept at: www.elsitech.com. This company produces a line of defect and issue tracking tools that includes integration to the latest version of Project. Regards, Ian |
VB error: "Error accessing file. Network connection may be lost." Posted: 15 Oct 2004 01:38 PM PDT I don't think so, since we all log in using our Windows authentication logins. I found it happens with someone else, too, so our MS guys have put in a ticket with Microsoft. If I find out what's wrong, I'll post the answer here. Thanks! Phyl "Steve House [MVP]" <send.hotmail.com> wrote in message news:<phx.gbl>... |
How do I change the Gantt Chart Report Begin Date? Posted: 15 Oct 2004 11:29 AM PDT Hi dillehunt , Welcome to this Microsoft Project newsgroup :-) You might have accidentally created a spurious task. Try Project/Sort/Sort by... and select for ID Descending, then check the last task ID (highest ID number) is your last task. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :-)) Mike Glen MS Project MVP wrote: |
Posted: 15 Oct 2004 10:09 AM PDT Steve, I tried one thing. I created a new identical task and delete the 'bad' one, and all seems fine now. I also noticed this across many other tasks in my plan. One thing I did was cut and paste this task many times. Something must have been corrupted. I will manually replace each bad task to correct the problem. By the way, the calendar options appear to be fine. I have worked on over 20 project plans with the same settings, so that wasnât the issue. Thanks for your help. Joe "Steve House [MVP]" wrote: |
Integrating an Access Query into Project Posted: 15 Oct 2004 06:27 AM PDT I am looking for a report showing the time lines of each project to help in scheduling and conflicts. It also will help in budgeting. There are no resources involved. We manage construction projects. If there is something else to do this let me know. I couldn't do it using a graph. "Steve House [MVP]" wrote: |
Posted: 15 Oct 2004 06:03 AM PDT Hi Paul, The only way I found when a customer asked me was to put 1 (and you could even put the monetary unit as Hr) in the resoruces' unit cost HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Paul Seaman" <Paul microsoft.com> schreef in bericht news:com... progress |
Import Project Standard 2003 tasks and deadlines to Outlook 2003 Posted: 14 Oct 2004 05:23 PM PDT I know it refers to Project but trust me, it's an installation package and the files for Outlook are part of it. When you download and expand the archive you'll find the files and instructions in the folder you create to hold the expanded files. Here's the URL for the download page for the Workgroup Message Handler package: http://www.microsoft.com/downloads/details.aspx?familyid=6382c615-1090-452c-8eba-4025b8976c18&displaylang=en if you look at the bottom of the page you'll see the system requirements and the email programs it's compatible with, including Outlook, are listed. It's a two step process starting with Project and that's why what you're seeing is refering only to Project. You have to first activate Project's ability to send messages to email systems. Then on the receiving side you have to configure Outlook so it can understand the messages Project sends to it. In a formal PM scenario you'd configure Project and then email as attachments the email client configuration programs to your resources for them to run on their own machines. Then to get your tasks from a Project file into your own Outlook, you assign yourself as a resource in Project and mail your task assignments to yourself. When Outlook receives it in email, you accept the assignment and it enters them into the to-do list. Of course, if you're using Project in a full-fledged Project management role you'd also be mailing the rest of your resource team their task assignments from Project as well. It's well to be nervous about editing the registry but those direction come straight from the MS horse's mouth and as long as you follow them to the letter and double check against typos you'll be ok. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "buzzlifeyear" <microsoft.com> wrote in message news:com... |
Compare Project Versions - Run-time error '13': Type mismatch Posted: 14 Oct 2004 01:41 PM PDT John Thank you for your input, I took a look at the fields that were being compared and could not find anything obvious. Probably the most interesting test was when I removed all fields with the exception of the ID and Task Name fields I still recieved the error. I have two files that are derived from the project files that gave me the error. The new have three tasks, the error occurs while processing the Version 2 file on the second task. I can e-mail these files and I would aprreciate any help you can provide. Thanks Mike "John" wrote: |
Max File Size in Proj Pro / Server Posted: 14 Oct 2004 01:19 PM PDT Open Project, Go to help menu, select reference then project specifications. I expect that they are identical. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "JH" <microsoft.com> wrote in message news:com... of other 4GB open resource decreases |
Project PWA Project Center views Posted: 14 Oct 2004 11:53 AM PDT Thanks Gary. I assume the new thread at microsoft.puublic.projectserver (?) is at the same discussion group site that you replied to, correct? Will open thread there and supply requested info. "Gary L. Chefetz (MVP)" wrote: |
How do I split a microsoft project task that takes x hours over . Posted: 14 Oct 2004 08:27 AM PDT Sorry, Levi, that referred to the TechTrax article - at the end. Mike Glen Project MVP Levi Page wrote: |
Is there a good Lag time report I can run? Posted: 14 Oct 2004 08:09 AM PDT See my other message to you. I think you're confusing lag time and slack time. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "lamby74" <microsoft.com> wrote in message news:com... |
Specifying Time of Day Task is due Posted: 14 Oct 2004 05:57 AM PDT There is sometimes confusion about what milestones are. They are NOT dates themselves but they do occur on at some specific date and time. The milestone itself is the event that takes place - a contract has been signed, a final report has been completed, a critical part has been delivered, a project phase has been completed, etc - that has some special signifigance in the project. It occurs whenever it occurs and even though there may be a target or desired date, just like any other event the milestone event itself might take place early, on-time, or late. In other words, you have TWO dates associated with your milestone event - the date when it WILL occur and the date by which it SHOULD occur. (I should point out that milestones don't necessarily have a due date - remember the milestone is an event and even though it's important to monitor for project tracking purposes we might not actually care when it happens.) In engineering you could say that the milestone marks a state change - in erecting a building before the milestone "foundation ready" the construction of the foundation is in process. The milestone marks the point where the foundation is complete and we can move on to the next phase. The change of state is "foundation incomplete" -> "foundation ready." In your example the milestone is the receipt of the material. You need it by Oct 15th so that is its deadline. But the delivery might come in a week before, on the 15th, or there might be a trucker's strike and your material might not get there until November. The date shown in the Gantt chart is the estimated date based on links leading to it, including lag times, until it has occured and then the actual date on which it did occur. By entering a deadline on the Task Information sheet, Advanced tab, for the milestone you can put a green arrowhead marker on the Gantt chart to indicate what the "drop dead" date of the milestone is and to see whther you're making the required schedule or not. Moving the milestone will not move the deadline nor should it. If we had to have parts received by 15th October last year does that mean in a similar project next year we'll need the same delivery date? Not very likely. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Fo Mo Co" <microsoft.com> wrote in message news:com... |
Posted: 14 Oct 2004 05:03 AM PDT Hi Aniki have you levelled at an "hour by hour" setting .. (from my experience) project won't "correct" your second problem if you only levelled at a "day by day" setting. As to the first problem i have really no idea, is the "clear levelling values before levelling" check box checked? Let us know how you go. Cheers JulieD "aniki" <microsoft.com> wrote in message news:com... |
Posted: 14 Oct 2004 04:56 AM PDT Hi Jonathan , Welcome to this Microsoft Project newsgroup :-) Please see FAQ Item: 16. Project Viewer. FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Jonathan wrote: |
change font color of tasks or color of bars from VBA Posted: 14 Oct 2004 03:17 AM PDT I have some sample code for turning all the bars green at my website. http://masamiki.com/macros.htm look for the all green macro. There are methods for changing font color too (see John's message). The one thing that can't be done is to change the cell background color. -- -Jack ... For project information and macro examples visit http://masamiki.com/project .. "Werner Koch" <at> wrote in message news:416e521d$0$30240$highway.telekom.at... |
How do I set up an MS Project where resources are working on the . Posted: 13 Oct 2004 05:23 PM PDT How about setting it up as a summary task describing the whole activity with the three instances as subtasks indented underneath it. The subtasks would not be linked to each other. Each resource is assigned to their specific subtask. While usually people advise not to link summay tasks, in this case I think there is an exception and any links coming TO the set of tasks or From it would go through the Summary task, not the subtasks. The duration of the summary will be from whenver the earliest starting subtask begins to where the latest finishing subtask ends, thus automatically setting the end of the group to whichever subtask finishes last. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Alan Eisenberg" <Alan microsoft.com> wrote in message news:com... |
Posted: 13 Oct 2004 02:43 PM PDT You're welcome, Shep:-) Mike Glen MS Project MVP shep wrote: |
One Gantt Bar showing 3 different data Posted: 13 Oct 2004 10:56 AM PDT You use the term "baselined date" in the singular and I'm not aware of such a data point. There's baselined start date, baseline finish date, etc but there's no such as a "baselined date" unless you are referring to the date on which the baseline itself was created or saved. Likewise the current date already is shown on the Gantt chart as a vertical dotted line going from top to bottom of the chart at todays date in the timescale. It's not an attribute of any particular task. Can you be more specific about what you're trying to do here? -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "June" <microsoft.com> wrote in message news:00ca01c4b14d$f22ed490$gbl... |
Posted: 13 Oct 2004 10:23 AM PDT Thanks Mike, I love those Microsoft "features", too. Guess I'll just have to muddle through. I'll be sure to check out the Project MVP site though! Thanks again, Melinda "Mike Glen" wrote: |
Project 2000 calendars driving me mad! Help pls. Posted: 13 Oct 2004 08:51 AM PDT Hi Pete, Welcome to this Microsoft Project newsgroup :-) You might like to see FAQ Item: 5. Default Working Hours FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Pete Bennett wrote: |
How do I force a resource to work on a task until it's done? Posted: 13 Oct 2004 08:07 AM PDT One thing that might help is to see if you can break the task down into smaller units that can then be parcelled out to your two resources individually. The general rule in a WBS is to try for a 1-task/1-resource correspondence, resource in this context being either an individual or a team that must work together as a unit, like a painter and his assistant, both of whom must be present for the job to proceed. Another rule of thumb that can help is the 8/80 Rule - if the tasks are smaller than about 8 man-hours you're trying to excessively micromanage the resources and if they're longer than about 80 man-hours you are likely to be looking at what is really a grouping of a number of different activities rather than a single discrete activity. 1200 man-hours (30 man-weeks) is well over that threshold. If you can separate out the individual components you may be able to split the work in such a way that the overall group is done in the shorted possible time even with the second resource joining late. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Bill Zvonar" <com> wrote in message news:ckuars$j73$ca.nortel.com... |
Blocking out Holidays and row adjustment questions Posted: 13 Oct 2004 07:15 AM PDT June, But you never said exactly what you problem with row height adjustment was. Are you trying to increase the row height or are you trying to decrease the row height? I already gave you some ideas of why you may not be able to decrease row height, but not being able to increase row height is another issue. John |
Actuals in PWA vs. actuals in MS Project Pro Posted: 13 Oct 2004 02:05 AM PDT LimorS -- After updating the project plan with actuals, you need to click Collaborate - Publish - All Information to "push" the latest schedule changes to PWA. Many people miss this step, unfortunately, because the publishing process is not automatic. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "LimorS" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |