Pages

Search

Program Manager Approval Question Microsoft Project

Program Manager Approval Question Microsoft Project


Program Manager Approval Question

Posted: 07 Sep 2004 02:21 PM PDT

Thanks for your help. Will past this on and get back
with you if there are questions.

2Fast... 
2003. In order to 
members, you must 
task. On the View My 
to the correct 
while delegating the 
respective PM's View My 
simply click the 
to you for final 
however, there is no 
he/she will need to 
state that the update 
Hope this helps. 
message 
would 

Getting Critical Path to show.

Posted: 07 Sep 2004 08:48 AM PDT

When you say that you "actually have the finish date set", do you mean
that you entered a date by which you want your project to end? If this
is so, then that's what's causing your problems. The point of
scheduling software like MS Project is to tell you, given the amount
of work and number of resources you say you have, when you WILL
finish. If you tell it when you MUST finish, then you essentially
hamstring the software. It becomes basically a spreadsheet.

Sarah

Adjust the height and font of the MS Project Gantt timescale?

Posted: 07 Sep 2004 08:39 AM PDT

my memory's not that good these days :)

"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message
news:phx.gbl... 


Help for beginners

Posted: 07 Sep 2004 06:40 AM PDT

Brian,

You are a world class act, I appologise for being so
defensive. I wish you the best, and I am glad you are
doing well, keep up the good work and good luck.

Jeff 
newsgroup post is a 
well as to discover 
and the solutions to 
message 
Glen, Steve House, 
gaps between the 
group I read every 
other begginners. 
problems that I can 
I know you don't 
life easier!! 

Bar Labels

Posted: 07 Sep 2004 06:36 AM PDT

Hi sw

- i actually did the same thing when i was testing it :)

glad to assist

Cheers
JulieD

"sw" <microsoft.com> wrote in message
news:09e901c494ee$70a782d0$gbl... 


Project 4.0 files

Posted: 07 Sep 2004 04:37 AM PDT

Hi Laurent,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 27. Project 4 to Project 2000

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

Laurent A wrote: 


Leave Reports

Posted: 06 Sep 2004 09:05 PM PDT

Hi,

On my Website I have a macro transforming "Calendar" absences into "Non
Working Time" Taks
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
"Rob Schneider" <net.net> schreef in bericht
news:phx.gbl... 


finding an unlinked object

Posted: 06 Sep 2004 08:39 PM PDT

Hi Ken,

I've no idea! Try resetting the Gantt Chart view EXACTLY the same as when
you created the arrows - same timescale, same date, same tasks.


Mike Glen
Project MVP

microsoft.com wrote: 


OneNote: Add capability to IE to capture a web page in OneNote

Posted: 06 Sep 2004 04:19 PM PDT

Download the latest upgrades to OneNote. This will give you the capacity to
do Screen Clippings.
With OneNote open, all you have to do is press the Windows Logo button and
S. Drag what you want, and it will dump it into OneNote.

"Bill J" <Bill microsoft.com> wrote in message
news:com... 
some 
OneNote. 


How do I create a project without actual dates? (where every mont.

Posted: 06 Sep 2004 02:37 AM PDT

Using elapsed time will allow you to specify your task durations themselves
in terms of equal length 30 day months. The Gantt chart time scale though
is a real civil or fiscal calendar so its months are their actual lengths
even when you display the labels as months from start. If month 1 begins 1
Sep, month 2 starts 1 Oct and month 3 starts 1 Nov and the labels read Month
1, Month 2, Month 3. Since this is a proposal and the durations you list
are going to be very very rough order-of-magnitude approximations until you
develop the actual WBS anyway, does it really matter if the timescale months
are slightly unequal? Would using weeks instead of months in the timescale
solve the problem if it is?
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"chrisnik" <microsoft.com> wrote in message
news:com... 
very 
of 


Week1, Week2...(from end)

Posted: 03 Sep 2004 01:09 PM PDT

Rod:
Thanks a lot! this worked fine. I had not considered that the week start day
would make a dofference.

In regards to you suggestions, I really appreciate it.
In reality, what I am doing is to lay-out a standard process where different
Departments are involved, so in fact I initiated the plan from start (as you
suggest) to find out what the standard timing would be every time the same
process is repeated. After I had all the tasks and lead-times figured out,
that's when I was switching the format so it doesn't go by dates but by weeks
before the main event, which is Pilot run (this is when I got the problem).
This way, every time someone follows this process, they know how many weeks
in advance they need to start and also when they need to do what. Until
today, this process was inconsistent and events happend as people
"remembered". You can imagine how bad the results were. Things are getting
better!
Thanks again,


"Rod Gill" wrote:
 

Enterprise Tasks Codes

Posted: 02 Sep 2004 04:12 PM PDT

Mark E --

I misunderstood what you meant by "Project Portfolio" in your original
question. I thought you were referring to the Project Center views. Sorry.

To answer your questions, only custom Project outline codes and custom
Resource outline codes appear as dimensions in the Portfolio Analyzer. If
you are using custom Project or Resource fields such as Text, Cost, etc.,
they will not appear. You must use custom Project and Resource outline
codes instead. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"Mark E" <com> wrote in message
news:Twn%c.123736$nbnet.nb.ca...