Hyperlink Microsoft Project |
- Hyperlink
- Print preview shows the old calendar date
- Sorting the resouce drop-down list in the Task Entry form
- Resource or task usage view - summary units
- How do I span a 50 hrs task throughout the 3 months of my project.
- Leveling - Resources are not leveled
- multipy 2 values in a cell?
- Can't I save a MS Project Report?
- Duration ?
- when was the project baselined
- Coordinating multiple projects
- How do I import an existing enterprise resource pool from Project.
- Read-only from command prompt
Posted: 19 Sep 2004 08:03 PM PDT Hi, I had tried the double quotes. It does not work either. If I don't put <> before and after, the only the part of the link up to a space will be hyperlinked. ex: file://c:/my documents/january This would be underlined and blue up to "my". Hence I need the <> for the whole thing the be underlined and blue. Yet, the link does not work. Max "Rob Schneider" wrote: |
Print preview shows the old calendar date Posted: 19 Sep 2004 06:35 PM PDT Hello guys, Check also the Start date in Project / Project Information... Gérard Ducouret "Rob Schneider" <net.net> a écrit dans le message de news:phx.gbl... date |
Sorting the resouce drop-down list in the Task Entry form Posted: 19 Sep 2004 03:40 PM PDT Well said, I forgot this "Permanently renumber resources" option while I used it several month before... ;-( Gérard Ducouret "Sarah" <com> a écrit dans le message de news:google.com... |
Resource or task usage view - summary units Posted: 19 Sep 2004 01:55 AM PDT Hi, I tried on both 2002 and 2003 versions : it works fine for me on the Work field too. All the work values are using the same unit (hr or day) I choose in Tools / Options / Schedule. Gérard Ducouret "ein" <microsoft.com> a écrit dans le message de news:com... rows. |
How do I span a 50 hrs task throughout the 3 months of my project. Posted: 18 Sep 2004 06:01 AM PDT Steve, A valid point........and an omission on my part to include the final step of amending the task-type....if so required. This was mainly due to the fact that you'd conveyed a pretty good understanding of the underlying principles in your initial answer. I felt, however, that your answer could have become lost amongst such "principles". I feel equally as strongly as you, about the way project programming needs to be approached. As such, I also get the urge to convey the basic principles. However, my experience also tells me that, when a person is looking for an answer, especially a written one, they need it at the beginning of the "reply", and with minimal additional "data". By all means convey the supporting principles and caveats associated with any particular answer....but even then, it has to be in short, sharp chunks, post answering the initial question. Cheers. James.G "Steve House [MVP]" wrote: |
Leveling - Resources are not leveled Posted: 17 Sep 2004 12:43 PM PDT "Start no earlier" and "must start on" are two very different critters. And yes, the SNE is perfectly valid for the situation where the task can't start because the hardware isn't available prior to a certain date - modeling that reality is exactly why such constraints exist. But your original message said the tasks have "must start on" constraints. SNE usually won't interfere with leveling while MSO, "Must Finish On," and "Finish No Later Than" constraints on tasks following the overallocations almost always will. MSO means it simply will happen on that date regardless of anything the resources or PM does, like the scheduling of when Christmas comes you literally have no control over it. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Francis" <microsoft.com> wrote in message news:com... |
Posted: 17 Sep 2004 12:14 PM PDT Hi Jack, Thank you for your respond. I have already "Number 1" for value entry and "Number 7" for the product based on the micro. This micro is summing the valuesfor the the filterd projects by the date range and I am absolutely okay with it. With respect to my problem, is there any way to customize the customized column "number 1" to allow me to multiply two numbers? Maybe I should create another column let say "number 3" and link the product "number 3" to my "number 7" which has the micro? Please advisae. Regards, Majid It does not allow formula to return the their product using message |
Can't I save a MS Project Report? Posted: 17 Sep 2004 09:42 AM PDT Melissa, I might as well throw my hat in the ring also. As Mike noted, Project does not allow built-in Reports to be saved, directly. However, if you have some experience with VBA, you can develop a macro that takes the same information in any of the built-in Reports and exports it to another application. I do it all the time by exporting to Excel. This approach also allows the report to be customized to your exact needs. At least this is another option. John |
Posted: 17 Sep 2004 06:35 AM PDT There are a couple ways to do this but I think the easiest to follow is this .... You don't need to worry about the task type or anything like that, the default "fixed units" type will work fine. Remember duration is the time span from when work first begins until when it's done - it is NOT the "window" during which the work might be done before some deadline. So saying your task is 2 weeks duration and requires 16 man-hours of work means that the resource is going to be spending a part of each day on it, but not his full work day, spread out for a period of 2 weeks. For him to accomplish 16 hours of work (2 workday's worth) output spread out over 2 weeks (10 workdays) means he is devoting, on average, 20% of his energy each day to the task. Thus over the course of 10 days he creates the same output that would have taken him 2 days if he had worked on it full-tilt. So enter the task with either a 10 day or 2 week duration, they're the same thing if you work a 5 day week, and assign the resource at a 20% assignment level in the resource assignment window. Project will calculate the task's work for you to be 16 hours and you're done. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs <microsoft.com> wrote in message news:18c601c49cc9$998200d0$gbl... |
when was the project baselined Posted: 16 Sep 2004 04:56 PM PDT Hi Trevor (how's life "over east"?) if you're using Project 2002 or 2003 the date is displayed next to the baseline level under tools / tracking / save baseline. I'm not sure how you can do it in earlier versions. Cheers JulieD "Trevor Rabey" <com.au> wrote in message news:google.com... |
Coordinating multiple projects Posted: 16 Sep 2004 01:15 PM PDT Hi, I don't understand the logic of not immediately updating. Use deadlines to show when something in another schedule is needed in yours. I use deadlines, because showing all tasks swamps the user. Milestones are easier to manage. The code I've written is for Project 2003 and wouldn't work on Project 2000.. -- For VBA posts, please use the public.project.developer group. For any version of Project use public.project For any version of Project Server use public. project.server Rod Gill Project MVP For Microsoft Project companion projects, best practices and Project VBA development services visit www.project-systems.co.nz/ Email rodg AT project-systems DOT co DOT nz "Steve" <co.uk> wrote in message news:cifd97$lb1$btinternet.com... know with plans What I why by propogate owners. |
How do I import an existing enterprise resource pool from Project. Posted: 16 Sep 2004 10:27 AM PDT Blake -- Exactly where do you see this calendar error? While importing the resources using the Import Resources Wizard, you do not need to have any projects open or the Enterprise Global open either. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Blake Edwards" <microsoft.com> wrote in message news:com... |
Posted: 15 Sep 2004 04:21 PM PDT If you're running from a cmd prompt - why not just set the file attribute +R first - and then open the file? /Lars Hammarberg www.camako.se "Conrad Santiago" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |