Calculations Microsoft Project |
- Calculations
- Baseline Work - wrong total
- Project 2000/Global Template for Many PMs
- File compatibility within Project 2000,2002 and 2003
- approvals for actual hours?
- Hours on a project
- Resource usage based on time estimate
- Resource Pool Corruption
Posted: 18 Jun 2004 06:46 AM PDT To start, can you tell us how planned % complete would be calculated? Based on duration? work? From which baseline? What about tasks without a baseline? Any limitations on the tasks which should have this number? Should it be calculated based on current date or from status date (I recommend status date)? Any other conditions that the calculation needs to take into account? If you can supply answers to those questions then writing the code is fairly straight forward. -Jack "Angela" <microsoft.com> wrote in message news:1e1b601c45561$66ad2b30$gbl... |
Posted: 17 Jun 2004 10:47 AM PDT Dale, I had thought that also, however there are no resources in this document the work was estimated directly without assigning resources... Mark -- __________________________________________________ _______ Mark Durrenberger, PMP Principal, Oak Associates, Inc, www.oakinc.com "Advancing the Theory and Practice of Project Management" __________________________________________________ ______ The nicest thing about NOT planning is that failure comes as a complete surprise and is not preceded by a period of worry and depression. - Sir John Harvey-Jones "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in message news:phx.gbl... |
Project 2000/Global Template for Many PMs Posted: 17 Jun 2004 07:42 AM PDT My thoughts exactly but I thought I'd ask about a magic bullet. Thanks for all your help. "Dale Howard [MVP]" wrote: |
File compatibility within Project 2000,2002 and 2003 Posted: 17 Jun 2004 07:32 AM PDT Many Thanks Gérard versions. écrit dans le message |
Posted: 17 Jun 2004 07:31 AM PDT Dave -- Theoretically, each task in a project could have a different project manager, though that simply is not practical. To set up a project so that multiple managers can each manage a section of a project, do the following: 1. Project manager #1 opens the project and clicks Collaborate - Publish - All Information 2. PM#1 saves and closes the project This step makes PM#1 the manager of every task in the project, and all task updates from resources will be sent to him/her by Project Server. 3. PM#2 opens the project and selects only those tasks that he/she will manage 4. PM #2 clicks Collaborate - Publish - Republish Assignments 5. In the dialog, PM#2 chooses "Selected items" from the pick list at the top of the dialog 6. PM#2 selects the "Become the manager for these assignments" option and clicks OK 7. PM#2 saves and closes the project This sequence of steps makes PM#2 the manager of only the selected tasks, and all task updates for resources on the selected tasks will be redirected to PM#2 by Project Server. Each additional PM will need to complete steps #3-7. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant Denver, Colorado http://www.msprojectexperts.com "We wrote the book on Project Server" "dave" <microsoft.com> wrote in message news:com... can you limit who has access to which tasks? (is this through some security in the product?) different managers? section updated only project have |
Posted: 17 Jun 2004 07:23 AM PDT Thanks I think i am on the right track, Now i just have a question about how the hours are calculated, Some time the projects have the correct hours and other times really night, it looks as if they have Too many hours. Any ideas as you helped a great deal for my first question :) Cheers, Wayne "Gérard Ducouret" <fr> wrote in message news:phx.gbl... Insert and |
Resource usage based on time estimate Posted: 16 Jun 2004 11:00 AM PDT Thank you both. Fixed Work does seem closer to what I'm trying to do. The only problem I have now is that it adjusts the units when I add another resource, but that happens less often. Fixed units for adding resources, and fixed work the rest of the time seems like it would be the best for me. Maybe I'm just a control freak! ;-) I did some reading on assigning and editing resources, and still didn't find a way to do it using hours instead of % usage, so I am keeping track of hours in the notes field. Not perfect, but I can make it work for now. Joel "Rod Gill" <com> wrote in message news:phx.gbl... then need direction. duration, to be I going dates, without am |
Posted: 16 Jun 2004 09:36 AM PDT Jan, thanks for the clarification. Any reccommendations on how to fix a corruped resource poool? Dave Bellamy Bellamy Consulting "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:<phx.gbl>... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |