Pages

Search

Calculations Microsoft Project

Calculations Microsoft Project


Calculations

Posted: 18 Jun 2004 06:46 AM PDT

To start, can you tell us how planned % complete would be calculated?
Based on duration? work? From which baseline? What about tasks without a
baseline? Any limitations on the tasks which should have this number? Should
it be calculated based on current date or from status date (I recommend
status date)? Any other conditions that the calculation needs to take into
account?

If you can supply answers to those questions then writing the code is fairly
straight forward.

-Jack

"Angela" <microsoft.com> wrote in message
news:1e1b601c45561$66ad2b30$gbl... 


Baseline Work - wrong total

Posted: 17 Jun 2004 10:47 AM PDT

Dale, I had thought that also, however there are no resources in this
document the work was estimated directly without assigning resources...

Mark


--
__________________________________________________ _______
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
__________________________________________________ ______

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
message news:phx.gbl... 


Project 2000/Global Template for Many PMs

Posted: 17 Jun 2004 07:42 AM PDT

My thoughts exactly but I thought I'd ask about a magic bullet. Thanks for all your help.

"Dale Howard [MVP]" wrote:
 

File compatibility within Project 2000,2002 and 2003

Posted: 17 Jun 2004 07:32 AM PDT

Many Thanks Gérard  
versions. 
écrit dans le message 

approvals for actual hours?

Posted: 17 Jun 2004 07:31 AM PDT

Dave --

Theoretically, each task in a project could have a different project
manager, though that simply is not practical. To set up a project so that
multiple managers can each manage a section of a project, do the following:

1. Project manager #1 opens the project and clicks Collaborate - Publish -
All Information
2. PM#1 saves and closes the project

This step makes PM#1 the manager of every task in the project, and all task
updates from resources will be sent to him/her by Project Server.

3. PM#2 opens the project and selects only those tasks that he/she will
manage
4. PM #2 clicks Collaborate - Publish - Republish Assignments
5. In the dialog, PM#2 chooses "Selected items" from the pick list at the
top of the dialog
6. PM#2 selects the "Become the manager for these assignments" option and
clicks OK
7. PM#2 saves and closes the project

This sequence of steps makes PM#2 the manager of only the selected tasks,
and all task updates for resources on the selected tasks will be redirected
to PM#2 by Project Server. Each additional PM will need to complete steps
#3-7. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"dave" <microsoft.com> wrote in message
news:com... 
can you limit who has access to which tasks? (is this through some security
in the product?) 
different managers? 
section 
updated 
only 
project 
have 


Hours on a project

Posted: 17 Jun 2004 07:23 AM PDT


Thanks I think i am on the right track,

Now i just have a question about how the hours are calculated, Some time
the projects have the correct hours and other times really night, it looks
as if they have Too many hours.

Any ideas as you helped a great deal for my first question :)

Cheers,

Wayne

"Gérard Ducouret" <fr> wrote in message
news:phx.gbl... 
Insert 
and 


Resource usage based on time estimate

Posted: 16 Jun 2004 11:00 AM PDT

Thank you both.

Fixed Work does seem closer to what I'm trying to do. The only problem I
have now is that it adjusts the units when I add another resource, but that
happens less often. Fixed units for adding resources, and fixed work the
rest of the time seems like it would be the best for me. Maybe I'm just a
control freak! ;-)

I did some reading on assigning and editing resources, and still didn't find
a way to do it using hours instead of % usage, so I am keeping track of
hours in the notes field. Not perfect, but I can make it work for now.

Joel

"Rod Gill" <com> wrote in message
news:phx.gbl... 
then 
need 
direction. 
duration, 
to 
be 

going 
dates, 
without 
am 


Resource Pool Corruption

Posted: 16 Jun 2004 09:36 AM PDT

Jan,
thanks for the clarification. Any reccommendations on how to fix a
corruped resource poool?

Dave Bellamy
Bellamy Consulting

"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message news:<phx.gbl>...