MPX in 2003 and MindJet / Mindmanager. Microsoft Project

MPX in 2003 and MindJet / Mindmanager. Microsoft Project


MPX in 2003 and MindJet / Mindmanager.

Posted: 16 Nov 2005 01:56 AM PST

Gérard

I stand corrected :)

My notes on this are a disgrace

--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer


"Gérard Ducouret" wrote:
 

project professional trial expired never even used it yet

Posted: 15 Nov 2005 06:43 PM PST

Mari,

1. Start / Run / Regedit
2. For Microsoft Project 2002 :
HKEY_CURRENT_USER\Software/Microsoft\Office\10.0\MS Project\Options\General
3. For Microsoft Project 2003 :
HKEY_CURRENT_USER\Software\Microsoft\Office\11.0\M S Project\Options\General
4. Dans le panneau de droite, Double Clic sur l'entrée FirstBoot
Dans la boîte valeur : remplacer la valeur 0 par 1

Gérard Ducouret

"Mari" <microsoft.com> a écrit dans le message de
news:com... 


export MS Project report to file

Posted: 15 Nov 2005 04:58 PM PST

Hi m,

Welcome to this Microsoft Project newsgroup :-)

Don't hold your breath! I've been asking Microsoft for this facility for
the 8 years I've been an MVP!

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

m wrote: 



Unique Project Management and MS Project problem

Posted: 15 Nov 2005 03:30 PM PST

Hi Bob,

Indeed, when you say you don't want the solution as it is, there is no
solution left.
You don't want to measure the resources, well yhen you lose the weighting
factor (Work) Project applies.
Apply the right level of resources to each task, use all work related
measurements and forget about duration as a measurement: that is how Project
is conceived.
Good Luck!

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Bob Inwater" <microsoft.com> schreef in bericht
news:com... 
detail 
second 
terms 
is 
since 


Custom Fields - Importing

Posted: 15 Nov 2005 12:50 PM PST

Hello Rick,
The pool file must be in read/write mode of course. So open it first.
The "Import Custom Field" button imort only the content of athe field in
question. Not its name.
The Organizer is more efficient for that : Tools / Organizer...

Hope this helps,

Gérard Ducouret


"Rick" <microsoft.com> a écrit dans le message de
news:com... 
here 
tasks 
default 
resource 
happened. 
pool" 
Only 


Can I attach a word doc to a project task?

Posted: 15 Nov 2005 12:30 PM PST

The short answer is yes. In Project Standard you can hyperlink to a
Word Doent through the Insert pulldown menu Insert => Hyperlink
(Ctrl + K). In the Professional version with Project Server, there are
several other options to connect Word files etc to a project.

Good luck.

--dwolf

When I update actual work in Project baseline updates, why?

Posted: 15 Nov 2005 11:21 AM PST

Never seen that.
Actual Work immediately updates Work, but I've never seen it update
BaselineWork
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"CJ" <microsoft.com> schreef in bericht
news:com... 
actual 


Resource pool changes schedule

Posted: 15 Nov 2005 10:22 AM PST

Just so you know, I believe you can link to the resource pool without opening
it. So the other person can use that pool and not have to open it as he/she
was instructed not to do.



"Tina S" wrote:
 

duration error

Posted: 15 Nov 2005 08:42 AM PST

Thanks. I love that it was that easy.

"Chris Marriott" wrote:
 

Remaining Work View

Posted: 15 Nov 2005 08:35 AM PST

Emma

I may be missing the point so please bear with me ...

You can add the remaining work column to the view (table)

Right click the column header where you would like to insert the new
information

Select the Remaining work field

If I have missed the point here please let me know ...
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer


"EmmaG25" wrote:
 

how can I set a printed Network Diagram properties ?

Posted: 15 Nov 2005 07:16 AM PST

If only I could import into VISIO !!!
--
Dave Eade
Global Project Solutions



"Gérard Ducouret" wrote:
 

I want to show a wbs structure as a picture like a network diagram

Posted: 15 Nov 2005 06:52 AM PST

Thanks Brian.

BUT, when I go to add/remove programs and MS Office Project Professional
2003, the options are 'MO Project for Windows', 'office shared features' and
'office tools' - I can't find any mention of 'toolbars' in any of these
'directories' - any ideas where it is ??
--
Dave Eade
Global Project Solutions



"Brian K - Project MVP" wrote:
 

Is there a Microsoft Project Viewer(free) available for download?

Posted: 15 Nov 2005 06:02 AM PST

Hi Maumau051 ,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

wrote:



How can I show roll-up by on the immidiate summary bar only?

Posted: 15 Nov 2005 03:28 AM PST

You need to individually set the summary bar to show it rolling up.
Another alternative is to create a new type summary bar from the format menu
/ barstyles for rolled up tasks that are flagged with a particular flag. I'm
not certain this will get exactly what you want, but it does offer a way to
control the display.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Chris Marriott" <com> wrote in message
news:com... 
level 
show 
the 
bars 
bar. 


Can cost/use be used differently

Posted: 14 Nov 2005 11:11 PM PST

The "cost per use" is attributed for each assignment to the task. You can
accrue it at the start, the end, or prorated. If you need to do it some
other fashion, break the task into smaller subtasks. If you have a 4 week
task with the cost accrued at the end of each week, make it a summary task
with 4 1-week subtasks. Assign the resource to the subtasks only, set the
cost-per-use to the weekly rate, and its accrual to the end of the task.

Do be very very careful - Project is a work scheduling and labour/material
resource cost estimating program first and formost. It is emphatically NOT
a cost accounting system and doesn't do a very accurate job of it -- in
fact, it completely ignores capital and cost of capital, opportunity cost,
ROI, etc so anything you do in that regard is a kludge with all the pitfalls
inherent in forcing a square peg down a round hole..
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Steve NCC" <com.(remove)> wrote in message
news:com... 

Using colour blocks for the task names columns in Project?

Posted: 14 Nov 2005 02:30 PM PST

Hi cgorley ,

Welcome to this Microsoft Project newsgroup :-)

You might like to see FAQ Item: 37 - Custom Fields in Tables. FAQs,
companion products and other useful Project information can be seen at this
web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP
wrote: 



Project File Size Grows w/o Adding New Task

Posted: 14 Nov 2005 10:58 AM PST

I don't know of a way to prevent corruption other that what's in the FAQ. I
would immediately take another backup copy as your nightly backups are
backing up the corruption.

Maybe someone else has something to offer?


Mike Glen
Project MVP



Catfish Hunter wrote: 



How get row height to auto adjust for wrap text in merged cells

Posted: 14 Nov 2005 09:06 AM PST

Hi,

I thought so.
This newsgroup is about Microsoft project.
I'm sure there is a newsgroup on all Excel matters!

God Luck,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional