Tasks end-start relation Microsoft Project

Tasks end-start relation Microsoft Project


Tasks end-start relation

Posted: 09 Sep 2005 01:26 AM PDT

If you typed a date for this task (not recommended, you should always use
links where at all possible) then the default start time will be 8:15 which
is 15 minutes after the calendar start time. Therefore Project has to
schedule an extra 15 minutes on the next working day to fit 8 hours in.

Set the default start time to 8:00 or better yet use links!

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"ArnoS" <microsoft.com> wrote in message
news:com... 


What projects from the server (published) will you see when openin

Posted: 08 Sep 2005 01:24 PM PDT

What is the differenence, please explain.
Thanks
Cindy

"Mike Glen" wrote:
 

Changing work Times

Posted: 08 Sep 2005 11:20 AM PDT


Hi Omar,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


omar wrote: 



Actual Work vs. Target/Baseline

Posted: 08 Sep 2005 10:37 AM PDT

Hi,

It MUST change because you want the rest of the plan to be based on reality
don't you?
I do.
IMHO Project primarily has to show me a correct future plan, what has
happened before is interesting but not critical.
For my own plans, I often simply delete complete tasks.

Original plan is saved as beseline, so no need to keep it alive as a base
for a (wrong) plan.
Do you have a finish variance? You should.
Can't judge about work because for that I need more data like task type.
There is a resoruce attached to teh task isn'there?


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Gil Grissom" <com> schreef in bericht
news:googlegroups.com... 


Resource usage report doesn't match Schedule

Posted: 08 Sep 2005 10:04 AM PDT


Hi Patti,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP




PattiTechWriter wrote: 



URGENT!! Using Lotus Notes email with Project 2003

Posted: 08 Sep 2005 08:31 AM PDT

Hi Vsinc,

Project 2003 no longer offers support for workgroup messaging using email.
(Previous releases did.) Please see:

http://support.microsoft.com/default.aspx?scid=kb;en-us;818337

I have not tried using the workgroup messaging feature with Notes.

Hope this helps. Let us know how you get along.

Julie



"vsinc" <microsoft.com> wrote in message
news:com... 


Cutting and pasting reports

Posted: 08 Sep 2005 06:52 AM PDT


Hi Marshall,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

Marshall wrote: 



Duplicate Resource cannot be removed

Posted: 08 Sep 2005 04:50 AM PDT

In article <com>,
"Steve Scott" <microsoft.com> wrote:
 

Steve,
First, resources should be managed on the Resource Sheet - that's what
it is for. My guess is that there is some subtle difference between the
two resources, meaning that they are not duplicate in Project's "eye".

Another possibility. You didn't mention whether the file is linked to a
resource pool. If both the pool and the file have a resource named "joe"
then these resources are indeed separate and can, under some
circumstances, both be assigned to a task.

Second, given the above is not the case and you suspect corruption, go
to the MVP website at:
http://www.mvps.org/project/faqs.htm
and look at FAQ 43 - File Bloat? - Might be corruption.

Hope this helps.
John
Project MVP

can i add a graphic for a custom date to gantt chart

Posted: 08 Sep 2005 03:37 AM PDT

Hi glen,

Good idea, but I'm already using a deadline for a date further down the
project and thus this is not possible.



"Mike Glen" wrote: 

Lock-down at the subtask level

Posted: 07 Sep 2005 03:05 PM PDT

Yeah, using PDF is always an option with any program. As long as you
have Acrobat installed (not just the reader).

Task duration not netting when resources added.

Posted: 07 Sep 2005 01:05 PM PDT

Hi,

When you add resources to a task that has none attached, the task will react
as fixed duration. So even when you add both resources at once the duration
will not change.
To the contrary, when you allocate one resource, enter, then allocate a
second one and when the effort driven option is on (task information,
advanced) duration will adapt.

OR, when you insert the Work column into your task view, and enter the 16
hrs of work BEFORE allocating resoruces, then even if you allocate both at
once duration adapts.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"almacote" <microsoft.com> schreef in bericht
news:com... 
not 
duration 
no 
un-indent 

My 


Assignment Reporting

Posted: 07 Sep 2005 12:19 PM PDT


Hi Dan,

Next time, try posting on the server newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


John wrote: 



Can Project have multiple users on multi comps?

Posted: 07 Sep 2005 12:17 PM PDT

Hi Sarabare,

Project users can share files with other project users -- doesn't matter if
it is Project Professional or Standard. The only reason to use Project
2003 Professional is if you intend to connect to a Project Server.

Hope this helps. Let us know how you get along.

Julie

"sarabare" <microsoft.com> wrote in message
news:com... 


leveling ignores priority & when to manually level

Posted: 07 Sep 2005 11:11 AM PDT

Hi,

I think we agree on 99% of the issue.
I think however that having the simulation done by the software (especially
on multi-project) gives me time for other things: Project levels 100 times
faster than me by hand.
Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"John Sitka" <com> schreef in bericht
news:#phx.gbl... 
(Project 
done). 
here" 
obviously, but I do hope that 
different 
when it is exposed they run the 
it for now and present a good picture 
underway. Classic 'Ostrich Technique'. I wouldn't 
on each individual who now falls victim 
frequency, discipline 
introduce 
can have no links. 
control and visual 
world WHIMSY is best handled like this. 
545 550 570 
the resource is gone. 
reality. If this task is not done 
applied 
news:%phx.gbl... 
(Project 
done). 
world. 
introduce 
entering 
are 
high 
said 
is 
considered 
message 
calculate 
to 
tasks 
to 
resources. 
view 
addressed 
than 
some 
If 
plan? 
perform 


Why is Project calculating durations incorrectly?

Posted: 07 Sep 2005 08:25 AM PDT

In article <com>,
"Chris - FidelityFlight"
<microsoft.com> wrote:
 

Chris,
Well, everything sounds pretty generic (i.e. default). My last question
about leveling applies to a feature of Project found under
Tools/Resource Leveling. When leveling is activated, it initiates an
algorithm that allows Project to automatically move tasks around (i.e.
shift, delay, split, etc.) to relieve resource conflicts
(overallocation). The default setting is "manual" (i.e. no leveling) but
you might want to check to see if the setting was changed to
"automatic". In the absence of a pure poltergeist (e.g. corruption),
leveling might be germane to the problem you are seeing.

The fact that the problem seemed to "fix itself" while you were out to
lunch (no pun intended), suggests that file corruption may be present.
In that case, go to the MVP website at:
http://www.mvps.org/project/faqs.htm
and take a look at FAQ 43 - File Bloat? - Might be corruption

Hope this helps.
John
Project MVP

Project to Access Dynamic Link

Posted: 06 Sep 2005 05:17 PM PDT

Rod â€" Thanks for the quick reply; appreciated it. Can I ask for more
information? In a test .mpp file, I Saved As ODBC to MS Access, closed
Project, opened the Access file and changed some information (i.e. file
properties in msp_project table, task names in msp_tasks file, etc.). Then I
closed Access and went back to the Project file and there are no changes
there. I also tried (within the Project file) to Open via ODBC, and was
expecting to get the dialogue box I got when opening exel files asking me if
I want to Open as new file, Append or Merge. It simply opens the Access file
as a new Project.

What am I doing wrong? Thanks in advance for any help!!!


"Rod Gill" wrote: