Pick Lists Microsoft Project

Pick Lists Microsoft Project


Pick Lists

Posted: 01 Aug 2005 02:03 AM PDT

Hi Dave,

Not as such.
You could create a VBA form to allow selection through a Macro but a true
Value list, No.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Dave Eade" <microsoft.com> schreef in bericht
news:com... 
de 
set 


Administrative Projects -

Posted: 31 Jul 2005 11:07 AM PDT

PG --

You can find the Project Server 2003 database schema at the following link:

http://www.microsoft.com/downloads/details.aspx?FamilyID=ac5cc775-1367-4b66-870d-f280c054efe2&DisplayLang=en

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"PG" <microsoft.com> wrote in message
news:com... 


Calendar Colors

Posted: 30 Jul 2005 05:05 AM PDT

Ok, thanks.


"Rod Gill" wrote:
 

Adding a predecessor does not change date?

Posted: 29 Jul 2005 10:22 PM PDT

You have indeed mentioned the sort of situations an SNET is designed for.
I'd prefer to use "semi-hard" constraints rather than say the dates are set
in stone. You can't begin a task until the required tools arrive so that
part is certain, BUT you could begin later if other circumstances conspire
to make it impossible to start as soon as the tools show up. A hard
constraint, Must Start On, says the task *WILL* start on that date, no if's,
and's or but's and there is absolutely nothing in the universe, no
eventuality known to man or action of anyone working on the project would
make it start otherwise. Short of acts of nature that just doesn't happen
very often.


--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"bob" <com> wrote in message
news:com... 

Estimated work vs actual

Posted: 29 Jul 2005 04:57 PM PDT

Remember to set the baseline first as well. That will calculate your 10h
variance after you enter actual work.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"Brian K - Project MVP" <com> wrote in message
news:microsoft.com... 


Hiding tasks within Project 2003

Posted: 29 Jul 2005 10:59 AM PDT

I've just put up an article about hiding SOME project information (mostly
stuff which project does not use to calculate schedules) on my website:
http://zo-d.com/blog/archives/programming.html

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"JackD" <momokuri@gmail> wrote in message
news:phx.gbl... 
project 
access 
views? 
and 


task note indicator

Posted: 29 Jul 2005 08:04 AM PDT

Thank you Sarah, I tend to think too much out of box.

"Sarah" wrote:
 

Can I import my team's schedules from Outlook into Project?

Posted: 29 Jul 2005 07:12 AM PDT

Thank you for your assistance!
--
aespb


"Gérard Ducouret" wrote:
 

Customised reporting

Posted: 29 Jul 2005 06:57 AM PDT

Hi John,
I got someone to knock up the macro below and it has succeeded in enabling
me to add the custom columns in resource usage view. However, when I run it,
it only seems to populate the info on the very first line (against the
resource.) All the tasks are listed below but the rest of the fields
associated with them are empty. The tasks are also strangely listed under the
resource name column. Nearly there, so a bit frustrating! Any suggestions
appreciated.

....
Dim t As Task
Dim r As Resource

On Error Resume Next
For Each t In ActiveProject.Tasks
For Each r In t.Resources
r.Text1 = t.Text1
r.Text2 = t.Text2
r.Text3 = t.Text3
r.Text4 = t.Text4
r.Text5 = t.Text5
r.Text6 = t.Text6
r.Text7 = t.Text7
Next r
Next t
--------------

How can I track a duration with an Actual Duration?

Posted: 29 Jul 2005 05:53 AM PDT

You're welcome, Gabrielle.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Gabrielle" <microsoft.com> schreef in bericht
news:com... 
Actual 


how do i set reminder in project 2003?

Posted: 28 Jul 2005 09:16 PM PDT

These notifications will be send via email.

Gérard Ducouret

"bryannolan111" <microsoft.com> a écrit dans le
message de news:com... 
me 


how to activate active directory in MS Project 2003

Posted: 28 Jul 2005 07:31 PM PDT

Grace wrote:
 

If you are talking about the Insert | Resource from... | Active Directory
menu item then verify that you are in a resource view (like the Resource
Sheet view) and then try it. It is always greyed out when in a Task based
view.

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Copy Picture to Office Wizard

Posted: 28 Jul 2005 04:31 PM PDT

Thanks David. This partly addresses what I am trying to accomplish but not
entirely. I'd like to be able to remove the Microsoft Project logo in the
bottom left hand corner of the template, and none of the designs seems to be
able to do this.
--
Phil Goodge


"Redneck David" wrote:
 

I change some fonts and other fonts change that are not selected.

Posted: 28 Jul 2005 03:41 PM PDT

gandude wrote:
 

How is he making changes to the formats? What mouse\menu clicks is he
making to make the changes?

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Resource < 100%

Posted: 28 Jul 2005 03:37 PM PDT

Hi Thomas,

One can't be everything to all people...
As you say, the 100% approach works for scheduling, and it makes optimum use
of resource leveling.
I heard the remark about reporting before... a partial solution is to only
show for time registratiuon the tasks planned to start say within next
fortnight.

A customer of mine had an other solution... All "permanent" tasks were
entered with percentages
(f.i. 5% administration, 7% meeting) but then ALL other tasks (the
productive taks) were entered with an 88% load (never 25 or 6 or 49) - that
makes a lot of sense!

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Thomas" <com> schreef in bericht
news:eEvU#phx.gbl... 
Project's 
to 
task 


Setting unchangeable start & end project and task dates

Posted: 28 Jul 2005 02:35 PM PDT

You could remove all predecessor/successor links, set all task start dates
manually, set all tasks to Fixed Duration, and then edit the durations to
achieve the Finish Dates you want.

Voila! You have just disabled the key functionality of Project.

It might be easier just to use Excel, Visio, or PowerPoint to create such
static plans. The puspose of Project is to help you make and manage rational
project plans. If you already know that everything is going to happen
exactly according to the original plan, then you do not need a dynamic
scheduling tool such as Project.
--
Reid McTaggart
EPM Architect
Microsoft


"Dave" wrote:
 

How do I delete some of the default fields in workgroup messages?

Posted: 28 Jul 2005 06:52 AM PDT

ajsamuels1 wrote:
 

If I remember right there is no way to changes these messages. Sorry

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com