how do I schedule defragmentation, spryware, etc ? Microsoft Project

how do I schedule defragmentation, spryware, etc ? Microsoft Project


how do I schedule defragmentation, spryware, etc ?

Posted: 26 Jul 2005 04:47 AM PDT

John wrote:
 

And spryware is that new kind of software that is young and energetic,
right? ;-)

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Does MS Project have possibility to draw S curve automatically?

Posted: 26 Jul 2005 04:34 AM PDT

Thank you it really helped. I have visited your site and marked it in
favourites to come back.
I am working in small company, after rather big experience on big projects
in big company. Now I miss data base for unit productivities (in construction
and maintenance of oil production plants). Do you have some links to places
where exchange of experience can be done without membership fees. I am ready
to give samples of schedules for tank maintenance works: rebottoming,
painting etc.
Best regards
Domagoj Bacic
71000 Sarajevo
com

"JackD" wrote:
 

Manually allocating time over several months

Posted: 26 Jul 2005 12:42 AM PDT

Oh.. that's embarrassingly easy.

Thanks very much!

<Reminder to self - explore more views>

Regards,
Roger


"Jan De Messemaeker" wrote:
 

Mirosoft Project 2000

Posted: 25 Jul 2005 10:37 AM PDT

Thank you John, I appreciate your quick response.

We were thinking that the corruption had something to do with the fact that
the file was password protected. However, we decided to go back in and
re-create the file.

"John" wrote:
 

Exporting Time-phased data

Posted: 25 Jul 2005 07:20 AM PDT

Hi John,

Yes. I've tried the "Analyze Timescaled Data in Excel", however I am
constrained to using only the task name field to identify the rows in my
resulting spreadsheet; I want to include data from other columns as well
to help in the sorting/analysis of the entire data set.

For example, I want to summarize costs by WBS, or by resource group, or
other custom resource fields I've created.

Is there a way to create an export map for the "Analyze Timescaled Data
in Excel" the same way you can export other data using export maps?

~ Don

John wrote:
 

VBA for Project

Posted: 25 Jul 2005 06:51 AM PDT

Thanks, all you guys for your comments they really helped.
Everything is working just the way i want it to

Cost factors of material resources

Posted: 25 Jul 2005 05:13 AM PDT

Hi Eswer,
I'm assuming you are trying to assign an extra cost (you call it a burden)
onto your material cost? This is common accounting practice.
If this is this is the case and if the burden is a constant (e.g. Add a set
% to the material cost) you can create a custom field which uses the material
cost as the base and multipy it by the constant.
When I say the burden needs to be standardised I mean it should be a fixed
%, i.e. the business want to add 20% to all material costs!! The 20% is fixed
and can therefore be used in the formula based custom field.

Paul

Hope this clarifies my answer.
--
Paul K - Dublin


"eswar" wrote:
 

Ignoring Resource Calenders While Scheduling

Posted: 25 Jul 2005 12:15 AM PDT

hi gerard,
thanks for that. i think this reason is good enough for me to stop
implementing such setup

regards
eswar

"Gérard Ducouret" wrote:
 

MSP98 and 2000 compatible?

Posted: 23 Jul 2005 11:43 AM PDT

Great! Thanks!


"Gérard Ducouret" <fr> wrote in message
news:phx.gbl... 
home? 


How do I get my project summary bar back after deleting it in erro

Posted: 22 Jul 2005 12:57 PM PDT


Hi Lois,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../View tab and at the bottom, tick the box for Show
Project Summary.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Lois07 wrote: 



Why is BCWP zero?

Posted: 22 Jul 2005 12:17 PM PDT

People would generally turn it off or ignore it.
They may not know what BCWP is when they start out.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Joe" <microsoft.com> wrote in message
news:com... 
asking 
and 
for 


vba datedifference type mismatch?

Posted: 22 Jul 2005 10:46 AM PDT

Hey

Jack, you seems to be the expert.

yeah i noticed that i missed the parantece. but its not that.

Sorry if ive explained the problem a little bit diffuse.
but its not a problem to get a object to a string. but the problem is to get
"activity.calendar" to be an object.

but it is possible to write Activity.Calendar in VBA?

if i dont get this to work , it is possible to send you a sample project
file. so that you can try it? just see if its just my computer or
something....

Thanks

- Bjorn








"JackD" <momokuri@gmail> skrev i melding
news:%phx.gbl... 


Removing tasks from a timesheet

Posted: 22 Jul 2005 07:52 AM PDT

Joe --

What you say is absolutely true. There is no default method in Project
Server to delete completed tasks for an individual project only. Thanks for
clarifying that for everyone! :)

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"Joe" <microsoft.com> wrote in message
news:com... 


filter blank lines in gantt chart

Posted: 22 Jul 2005 07:48 AM PDT



"Brian K - Project MVP" wrote: 

Thanks for that Brian, I can stop searching then. Will give your tip a try
and as it's the only solution it will have to do.

Viewer for Project?

Posted: 22 Jul 2005 07:47 AM PDT


You're welcome, Bill :-)

Mike Glen
MS Project MVP


Bill Starbuck wrote: 



Need help using xlt. file

Posted: 22 Jul 2005 07:24 AM PDT

Sorry, I'm new to this discussion group thing and apparently I chose the
wrong group. I was just surfing on the discussion group website and chose
this group. Again I am sorry.

"Mike Glen" wrote:
 

Remove a task from the critical path

Posted: 21 Jul 2005 11:29 PM PDT

Kevin wrote:
 


Great. I knew something did not sound right! :-)

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

Material Resource overload

Posted: 21 Jul 2005 02:21 PM PDT

How could you set a max even if Project allowed it? Material resources are
things that are incorporated into the deliverable or consumed during its
production. If I have a wall that will require 500 bricks I can't just
arbitrarily stop building when I've used 250. If I did the wall won't ever
be finished and the project will be deemed a failure. Project's tracking of
material resources is to insure you know how many to order so you will have
enough on hand to do the job required. Essentially you can't load based on
materials - if the budgeted allowance isn't sufficient to complete the
required deliverables you only have three options - buy more materials,
reduce the project scope, or abandon it altogether.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Hadi" <microsoft.com> wrote in message
news:com... 

Scheduling with a deadline while behind schedule

Posted: 21 Jul 2005 02:03 PM PDT

Hi,

When you use the reschedule work function, it shifts the unfinished work to
today (or tomorrow, depends), that is true.
It ignores predecessors of this work, logical isn't it, that's the past, you
only plan the future.
But it doesn't ignore the successors to these tasks, these are shifted just
as well.
You will probably get negative slack (if you fixed the end date with a hard
constraint) or a schedule overrun (when you only put a delay on the final
task).

Now by all means you're to move: can you increase resources (only few people
can, you know); can you use subcontreacting to speed up, etc.;LS project has
no way of guessing this and I wonder if any software will know your
possibilities to improve the schedule..

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"joshroberts" <microsoft.com> schreef in bericht
news:com... 
time 
no 
business 
that 
and 
I've 

add 
as 
ends 
schedule 
I'm 
window 
overallocations. 
be 
date 
full 
review, 
may 
is 
some 
some 
sequential 
the 
end 
become 
required by 
the 


Slip task

Posted: 21 Jul 2005 11:17 AM PDT

Reading your post a question came to mind - was any work performed on the
11th? The task was originally scheduled to start on the 11th. If work was
NOT performed on it, we don't have a task being interrupted, we have a
task's start being delayed which is not the same thing at all. A task is
interrupted if work starts and then stands-down for some reason. If work
was performed on the 11th, the day of work for the 11th is "used up" in the
overall task duration and the interruption begins with the first moment work
should have happened but didn't, which is to say, the morning of the 12th,
NOT the moment the work that was performed finished, the afternoon of the
11th. If we work 8-5, work was done the 11th from 8 to 5 and the
interruption begins 8am the morning of the 12th, not 5pm the afternoon of
the 11th because non-working time, the hours from 5pm->8am, is ignored by
the calendars and might as well not even exist as far as the project is
concerned. The easiest way to post this to your schedule would be to enter
any actual work for that task on the day(s) it took place and then with that
task selected, use from the menu Tools / Tracking / UpdateProject and with
the radio button for "Selected Tasks" in the dialog box selected, use the
"Reschedule Uncompleted Work to Begin After..." option.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sandieve" <microsoft.com> wrote in message
news:com... 

Outlook Integration Wizard / Addin for Project 2003

Posted: 21 Jul 2005 10:47 AM PDT

OK, I found this. I know it does the job for me, hope it will for you.

Project 2003 Workgroup Message Handler
http://office.microsoft.com/fr-fr/officeupdate/CD010798401033.aspx

Don't forget to read the installation instructions, you have to add a
registry key



"Mike Brester" <microsoft.com> a écrit dans le
message de news: com... 


How to change pjDate_Www_dd ?

Posted: 21 Jul 2005 10:16 AM PDT

Well, it sounds strange, but the first date will be Dec 27'04, for 2005
calendar. This is, thas last week of Dec will be w1/1 ->w1/7. Part of the
problem could be that the last week of Dec is in MP, as of today, w53, and a
lot of companies only use 52 weeks for a calendar year. One of those
companies that use this format, that I know , is Intel

"Rod Gill" wrote:
 

How can I get the Adobe PDF Maker 7.0 toolbar into MS Project 03?

Posted: 21 Jul 2005 08:27 AM PDT

The PDF Maker toolbar for Project is a feature of Acrobat Professional only
and not available with Acrobat Standard.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"ClairNeedsHelp" <microsoft.com> wrote in message
news:com... 

Can I network 2 computers 1 with ME and one with XP?

Posted: 21 Jul 2005 08:06 AM PDT

In article <com>,
"ssmalley" <microsoft.com> wrote:
 

ssmalley,
This is a Microsoft Project newsgroup. I suggest you try a newsgroup
that deals with various operating system configurations.

John
Project MVP

Automatic Gannt Bar formatted based on the resource assigned?

Posted: 21 Jul 2005 07:01 AM PDT


Hi Tom,

Welcome to this Microsoft Project newsgroup :-)

You might like to see FAQ Item: 31. Customizing Task Bars.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

tom s wrote: