Fixed work/units Microsoft Project |
- Fixed work/units
- Freeze Column for view
- Publishing Projects
- What's the best way to post question
- Project Server Email Problem
- What is a unique Joliet name?
- Recurring Tasks on Saturdays and Sundays?
- Can I use Project for this?
- different work hours for different resources
- New User: Budget?
- Maintaining a Valid Baseline
- Estimated / date or day wise
- Resource Centre, Can't see all resources!
Posted: 23 May 2005 08:46 PM PDT Dear Jeff, Thanks very much for the help. My email id is com. Will you please let me know your mail id so that we can share views and ideas about MS project. Thanks and Regards, Krishna Mohan "Jeff Chapman" wrote: |
Posted: 23 May 2005 03:23 PM PDT Very Tricky Grasshopper... This sort of works, in that it indeed freezes the task name descriptions on the left side of the screen. Unfortunately, the indentiation of sub task is lost making it a bit difficult to read. Any thoughts on how to keep the formatting? Thanks for your response "Reid McTaggart" wrote: |
Posted: 23 May 2005 12:55 PM PDT I've tried all information and project plan. "Reid McTaggart" wrote: |
What's the best way to post question Posted: 23 May 2005 07:58 AM PDT In article <com>, "Garterlover" <com> wrote: David, Yes I use VPC. I presently have VPC 7.0.1 running under OS 10.2.8 but after using VPC 7 for a while I get no clear advantage over my previous install of VPC 5.0.4. I run Project 98, 2K and 2003 depending on the question I need to answer. John Project MVP |
Posted: 23 May 2005 03:59 AM PDT We had notification problem once, antivirus was blocking mail port on the server. "Sami Khan" <microsoft.com> wrote in message news:com... |
Posted: 22 May 2005 08:13 AM PDT "Joliet" is a system level file specification for CDs and the naming rules - length, allowed characters, etc - it requires differ from those of Windows itself. You'll need to rename some files to conform to the rules or zip your files into an archive before saving. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Editor29" <microsoft.com> wrote in message news:com... |
Recurring Tasks on Saturdays and Sundays? Posted: 21 May 2005 03:37 PM PDT Project Standard and Project Pro do have some differences, but I don't know if they would affect this issue. I have found that editing a recurring task once it has been created does not work nicely (as you noted). But creating a recurring task on Saturday or Sunday after first defining the working times does work for me IF I define the duration to be 2hrs and explicitly define the start time (not just the date) in the Start box. To see start times, go to Tools > Options > Views and select a date format that includes time. -- Reid McTaggart Alegient, Inc., Houston Project Server Experts Microsoft Certified Partner "com" wrote: |
Posted: 21 May 2005 07:57 AM PDT "John" <com> wrote in message news:microsoft.com... John- I think I understand the "span" of projects that Project can handle. I'm reading all I can about project management in general, read something today which has me wondering if project management software is the best solution for a musical organization: (I'm paraphrasing the text I read here:) There's a distinction between normal _operations_ of an organization, and _projects_ of an organization. Normal Operations are repetitive, ongoing, activities/processes. Projects are non-repetitive, specialized, finite events. In a musical organization, "Normal Operations" ARE (in a way) repetitive, ongoing, yet unique, finite events. Normal operations to, say, a symphony orchestra, are a series of concerts. Week in, week out, x rehearsals and x concerts. The only major thing that changes is the program (and the date). Yet for each of these, you can identify and quantify all the tasks, durations, resources, costs, etc., which project management software uses to help you. So, do you feel the "normal operations" of a symphony orchestra, as described in the preceding paragraph, are indeed a series of projects? That's how I'm approaching my studies right now. If so, I can more easily adapt the facets of Project that I learn to a musical organization. So I guess when I used the term "overkill", I was heading in that direction: is it even beneficial to use project management software to manage a repetitive series of projects (all of which ARE collectively "normal operations")? Fr@nk |
different work hours for different resources Posted: 20 May 2005 01:46 PM PDT Note that regardless of task type, when you assign the FIRST resource(s) to a task Project assumes that was what you had in mind you were going to do when you made that duration estimate and thus won't change it. Also, Project doesn't have a clue what the work requirement represented by theat duration might be until after you've made the intial resource assignemnt. Joe works an 8 hour day. If I have Task X with a duration of 5 days and assign Joe at 100%, Project calculates the task requires 40 man-hours work. But if I initially assign Joe at 50% instead, Project calculates the task requires 20 man-hours but keeps the duration at the same 5 days. It's only if I assign Joe initially at 100% and then EDIT his assignment to something else will Project calculate a new duration value. The duration of a task is exactly the same whether the calendar of a resource assigned 100% shows he works a 4 hour day or an 8 hour day. But it will take twice as many elapsed time calendar days to "burn up" that duration for a 4 hour a day resource as it does for an 8 hour a day one. If Joe who works an 8 hour day is assigned 100% to a task beginning Monday that requires 40 man-hours, it will finish Friday at 5pm after 40 duration hours. Each workshift is 1 8-hour duration day. If Joe who works an 8 hour day is assigned 100% to a task beginning Monday that requires 20 man-hours, it will finish Wednesday at noon after 20 duration hours. Each workshift is 1 8-hour duration day. If Joe who works an 8 hour day is assigned 50% to a task beginning Monday that requires 20 man-hours, it will finish Friday at 5pm after 40 duration hours. Each workshift is 1 8-hour duration day. If Bill who works a 4 hour day is assigned 100% to a task beginning Monday that requires 40 man-hours, it will finish a week from Friday, 10 working days, but still after 40 duration hours. Each workshift is 1/2 of 1 8-hour duration day and so it takes 2 working shifts, spread over 2 calendar days, to equal 1 duration day. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Kesavan" <microsoft.com> wrote in message news:com... |
Posted: 20 May 2005 11:19 AM PDT The term "budget" is a bit problematic when dealing with MS Project. The everyday usage of the term connotates a maximum dollar amount one is allowed to spend as allocated though some top-down process to distribute monetary resources to the various activities of the firm, which is not quite what Project means by the term. Project's budget is a bottom-up estimate based on projected costs of the materials to be consumed and the labour to be performed for each activity, rolled up into the summary level and project levels to compute total amounts. Fixed costs are a portion of those budgeted costs, representing projected costs associated with tasks and summary tasks but that fall outside the materials and labour categories - rent on office space or airfare for a trip for example. Once the projected costs are saved as a baseline you can think of them as a top-down budget as presumably that baselineing only happened after you've submitted your projections for senior management approval and they've come back with a go decision authorizing you to spend that amount. If the "budget" is actually that first top-down estimate based on a distribution of projected revenues rather than an estimate of required expenditures, I'd suggest using one of the use-defined Cost fields to hold it so I have it handy to compare mny estimates to. If the estimates are less than the budget, great! If the estimates are greater than the budget and managment won't negotiate on budget or scope, update the resume! -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "RTucker" <microsoft.com> wrote in message news:com... |
Posted: 20 May 2005 07:48 AM PDT Yes, I totally agree and am attempting to do just that. use a legitimate baseline. But my file corruption issues prevented me from continuing work with a 5800 line schedule unless I performed the "project import and delink" routine I described. This left me with a Baseline that is now questionable. When I found the milestone with a BLfinish that was before it's BLstart, I became very suspicious of MSP 2003's ability to calculate and maintain data. I traced back through archived files and found the Finish<Start issue existed long before I performed the conversion to correct the VBA issues. Here's what I discovered since then... MS Project does not protect the Baseline fields at all! You can manually overwrite them. So, I can go through all the pains of establishing a baseline, then someone can change the data in Baseline Start/Finish, etc. and resave the file. The "Last saved on..." info is not affected. There is no way to know if someone messes with the schedule data. Microsoft need to put field-level security on this product. And they need to add better error checking into the calculations functionality to prevent time-warping milestones! -- RTucker, PMP "Steve House [Project MVP]" wrote: |
Posted: 19 May 2005 11:45 PM PDT Task and resource also. "Jan De Messemaeker" wrote: |
Resource Centre, Can't see all resources! Posted: 19 May 2005 07:05 PM PDT John, I don't know what you mean by ""switch to Active Directory?"" First you need to have an account with Administrative rights. Once you login using this account you will have access to the Admin menu in Project Web Access. Admin>Manage Users and Groups>Groups>Add group Group Name: [I have entered the same name as that in Active Directory as the group name] Description: [I have entered the same name as that in Active Directory as the group name] Active Directory Group: [enter the name of the Active Directory group you want synchronised here] Click on Save Changes. thats all that should be required to synchronise with AD and you should end up with the list of accounts in the groupname you selected above. Hope this helps. :) -- Gani "johnp1" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |