Use for MS Project by patent attorneys? Microsoft Project |
- Use for MS Project by patent attorneys?
- Progress Bars
- New to MS Project 02. How do you schedule vacation time.
- How can I export a Project Gantt chart as a picture, a .doc or an.
- Exporting a report to Excel
- Updating Milestone Dates
- Can I turn off Work Unit Duration Calculation? Fixed Duration & Wo
- Linked embedded PDF object does not show icon
- File Name in Summary Title Box
Use for MS Project by patent attorneys? Posted: 05 Apr 2005 12:02 PM PDT Just put-in an order for it... not a bad deal at <$17 with shipping. Thanks. |
Posted: 05 Apr 2005 10:13 AM PDT Rick Martin wrote: Cut that line and paste it below the summary bar line in that dialog. Bars are drawn from the top down so bars lower in the dialog are shown on top. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
New to MS Project 02. How do you schedule vacation time. Posted: 05 Apr 2005 07:29 AM PDT I could schedule it all at the end of the year. We were using a product called Project WorkBench, which allowed us to spread it out over the year. "Jan De Messemaeker" wrote: |
How can I export a Project Gantt chart as a picture, a .doc or an. Posted: 05 Apr 2005 07:17 AM PDT you're welcome -- Cheers JulieD check out www.hcts.net.au/tipsandtricks.htm ....well i'm working on it anyway "Evan" <microsoft.com> wrote in message news:com... |
Posted: 05 Apr 2005 04:19 AM PDT In article <Wxy4e.1219$bigpond.net.au>, "Jack Shearer" <com> wrote: Jack, The Cash Flow report is a timephased report, therefore you need something that will export timephased data. There are several choices, some better some not. The easiest but most tedious is a copy and paste. Probably not what you want. Another method you might try is to use the "Analyze timescaled data in Excel" utility found on the Analysis toolbar. Try exporting from the Task Usage view. It is likely you will have to do some manipulation of the data to get the format you want. The most flexible method is via a custom VBA macro. Using that method you can get whatever report data and format you need, including automated data manipulation in Excel. I use this method all the time. Hope this helps. John Project MVP |
Posted: 05 Apr 2005 04:09 AM PDT I'm a bing believer that there are no such things as "milestone dates." There are milestone *events* - signifigant things that happen during the course of a project and of course they happen at specific points in time, but the milestone is the event itself and not the date on which it happens to occur. Project's basic function is calculating dates. Left to its own devices, it will calculate the date on which a certain milestone will occur if you work the plan in the way it is currently outlined. If you want the milestone to occur on a different date from the one you see, you must do something proactive to the scheduling of the predecessor driving events to make it so - simply decalring that it will happen on XX date is not in and of itsxelf sufficient to make it happen then. The milestone is at the tail end of a chain of causality and it will happen whenever that chain off events causes to to happen. Now that's not to say it may not have a requirement that you have to meet - far from it, it very likely has such a requirement. You can best represent that requirement with a deadline - now you'll see that date you have to hit and the date the schedule as you've perently designed it ordains that you will hit. If the milestone event doesn't occur when you need it to, you need to change the driving forces so that it does and comparing the calculated date where it does occur with the deadline date where it should occur tells you if you have been successful or not in planning your strategy. Steve House MS Project MVP "Steve Scott" <microsoft.com> wrote in message news:com... order |
Can I turn off Work Unit Duration Calculation? Fixed Duration & Wo Posted: 04 Apr 2005 05:49 PM PDT There's nothing in the W-D-U identity that precludes Project doing this calculation exactly the way you want it. You're overlooking the "U" in that equation. Joe spending 20 days to do 2 days of work represents at 10% units(if he was working at 100% and needed to do 2 days work, the duration wouldn't 20 days, it would be 2 days). Jane spending 20 days to do 5 days of work means she's working at 25% units. After changing the duration to 15 days, Project will recalculate Joe's units required to produce 2 days of work over a 15 day duration at ~13% with Jane will now be 33%. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Vic W" <microsoft.com> wrote in message news:com... |
Linked embedded PDF object does not show icon Posted: 04 Apr 2005 08:55 AM PDT Thanks. We are trying to segregate using an hyperlink address to retrieve current data as opposed to using a notes field to link to a source within a directory. "JulieS" wrote: |
File Name in Summary Title Box Posted: 01 Apr 2005 02:03 PM PST Brian, Thank you very much. This help get major kudos from my boss. "Brian K - Project MVP" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |