Hide graphical indicators for summary rows? Microsoft Project

Hide graphical indicators for summary rows? Microsoft Project


Hide graphical indicators for summary rows?

Posted: 17 Dec 2004 02:32 PM PST

Hi bam,
Thanks. After posting I read Rod's reply and had one of those D'OH moments.
Sometimes I overlook the most obvious!
Julie

"bam" wrote:
 

Customized Reports

Posted: 17 Dec 2004 12:41 PM PST

Rod,

Thanks, how would I create a Macro to display all of these requirements in
"one" report? Will all of the required information show on the task sheet or
Gantt that I create?

"Rod Gill" wrote:
 

Anyone know when Project 2003 will be upgraded?

Posted: 17 Dec 2004 11:57 AM PST

Very very unlikely that it will be 2004.


--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"bracr2000" <microsoft.com> wrote in message
news:com... 


Project scheduled unavailable resource

Posted: 17 Dec 2004 11:15 AM PST

Hi Deluth,

If your resources are not available until dates you specified through
modifying their max. units (General Tab on the Resource Information dialog
box), Project will not automatically shift the work to when they are
available. However, leveling should solve the problem and delay the tasks
until the resource is available as long as you allow the Leveling to delay
tasks on the critical path. (Remove the check from "Level only within
available slack" in the Resource Leveling dialog box.)
The only other option is to modify the resource's calendar (the Working time
tab on the Resource Information dialog box) by marking the dates they are not
available as non-working time. Then Project will shift the tasks to time
defined as working time in their calendar. (They may still appear as
overallocated if you assign them to multiple tasks.)

Hope this helps. Let us know how you get along.
Julie

"deluth" wrote:
 

How do I see 2 or more projects in one view

Posted: 17 Dec 2004 09:25 AM PST

You could also try using a master project schedule. Do a search in this
newsgroup and you'll find loads of info on master projects.

Sarah

Status Report "unseen"

Posted: 17 Dec 2004 08:51 AM PST

Nope...

"Dale Howard [MVP]" wrote:
 

What is R/D

Posted: 17 Dec 2004 08:38 AM PST

Hi Norman,

You are welcome and thanks for the feedback.

Julie

"Norman Goldsmith" wrote:
 

Work Calculation questions

Posted: 17 Dec 2004 08:33 AM PST

Generally, yes. You need to be careful about Work, Actual Work and Remaining
Work though.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"ad" <microsoft.com> wrote in message
news:com... 
factors, 
task 
assignment 
that 
task 
get 
the 


ViewDrop

Posted: 17 Dec 2004 08:27 AM PST

Well I never... :)

Thanks Dale

Mike Glen
Project MVP




Dale Howard [MVP] wrote: 



printing a specific time range

Posted: 17 Dec 2004 08:15 AM PST

Hello AMD,
First of all, use a date format with time : Tools / Options / Views : Date
Format : something with 12:33
Then :
File / Print... / Dates From ... To...

Hope this helps,

Gérard Ducouret

"AMD" <microsoft.com> a écrit dans le message de
news:com... 



Project 2002 - remove resources?

Posted: 17 Dec 2004 06:53 AM PST

Hi Josh,

I don't believe there is a way to remove resource's name from the Gantt
chart [Resource Name] field without deleting the resource and removing their
historical data. However, a couple of potential compromises come to mind.
1) In the resource sheet, insert a Flag field and set the flag to "Yes" for
the resources who are no longer available.
Sort the resource sheet by flag field and renumber the resources so the
flagged resources appear at the bottom of the sheet. The [Resource Name]
field in the Gantt chart shows resources sorted by ID.
2) Create a filter and filter out the "Yes" flagged resources. Use the
assign resource button and in the Resource List Options area, select the
filter you created. The flagged resources will not appear in the Assign
Resources dialog box.
3) Edit the list of resource names to add Inactive before their names.
Certainly the least elegant and most labor intensive.

Hope this helps. Let us know how you get along.
Julie

"Josh" wrote:
 

how to recalculate finish date based on 50 hours per week.

Posted: 16 Dec 2004 07:53 PM PST

Hi Andy,

Welcome to this Microsoft Project newsgroup :-)

You also might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP


Andy wrote: 



Using resource pool in 2003

Posted: 16 Dec 2004 05:37 PM PST

Hi Richard,

Yes - use Tools/Resource Sharing/Share Resources.../and select or deselect
to use own resources or those of the pool.

Mike Glen
Project MVP




Rod Gill wrote: 



Deliverable Tracking

Posted: 16 Dec 2004 05:01 PM PST

Kai,
We're using QuickPlace.
Thanks for your input.

Troy

"filesiteguy" wrote:
 

Resource Load on Specific Task

Posted: 16 Dec 2004 09:43 AM PST

That gets me closer. Can I group the bottom window by resource? When I try
to select a group, it is grey for the bottom window.

"Rod Gill" wrote:
 

Non IE Browser with Web Server

Posted: 16 Dec 2004 09:07 AM PST

JackD wrote:
 

Exactly. I have the same issue with a FileNet viewer that we're using.

 

Nah, that's one of the advantages of FF - no ActiveX. ActiveX is baaad,
very bad.

I'd say they should suck up and use IE once in a while. Hell, I use it when
I have to, and I'm running Linux.

Long range, use something that doesn't have an ActiveX control. The world is
moving away from ActiveX anyway.


--
kai
www.filesite.org
"i believe in what i'm doing, but what is it i'm doing here"

bounced

Posted: 16 Dec 2004 02:46 AM PST

and i'm on adsl (broadband) with 300MB per month download limit which i
never ever go anywhere near using so i don't tend to worry about attachments
except from the virus point of view ...

i do however, think it's a good idea to "encourage" people not to add
attachments as most things can be explained and answered without them ...

btw Trevor - i was wondering the other day as to where you had got to as its
been over a year since i've notice a post / reply from you

Cheers
JulieD

"John" <com> wrote in message
news:microsoft.com... 


Project for Macintosh

Posted: 16 Dec 2004 01:07 AM PST

On Thu, 16 Dec 2004 09:07:07 +0000, cwynn46 wrote
(in article <com>):
 

Check out -

FastTrack Schedule <http://www.aecsoft.com/>

Or the recently released LeadingProject
<http://www.leadingproject.com/en/main.php>

Ian
--
Ian Robinson, Belfast, UK - <http://www.canicula.com>
Soapbox - <http://homepage.mac.com/ianrobinson/index.html>