Resoource Usage View Microsoft Project

Resoource Usage View Microsoft Project


Resoource Usage View

Posted: 19 Jul 2004 04:54 PM PDT


Steve,
I'm not sure exactly what you mean by "nominal value" but let me expand
a bit on what Jack said. Lets say a task started in June 2004 and is
scheduled to complete in Aug 2004. Even though the task is shown as 100%
complete in July Actual Work values will show in the Resource Usage view
through the task end in August. An important step was missed. Since the
task in fact completed early, an Actual Finish date representing the
date the task finished needs to be entered by the user. Project has no
way of knowing when the task finished unless you tell it.

John

MS Project 2003 to 2002 file conversion!

Posted: 19 Jul 2004 11:08 AM PDT

You are most welcome!
Julie 
you 
open 
however, 
do 
Office 
Project 
or 
don't 
2000 
Microsoft 
go 
2003 
do 

Subprojects display in a Master Project

Posted: 19 Jul 2004 08:03 AM PDT

Hi Jay,

Welcome to this Microsoft Project newsgroup :-)

You might also like to see FAQ Item: 31. Customizing Task Bars - Project
2000 .

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

"John" <com> wrote in message
news:microsoft.com... 


Compilation / Syntax Error

Posted: 18 Jul 2004 05:50 PM PDT

Your post and this response is in the newsgroup called
microsoft.public.project. Try posting your message to
microsoft.public.windowsxp.general newsgroup where the experts in windowsxp
hang out. :)

Mike Glen
Project MVP


"Markbie" <microsoft.com> wrote in message
news:com... 


Export reports to Excel

Posted: 17 Jul 2004 04:30 PM PDT

As John says, VBA is the way.
What exactly do you want to export?

-Jack

"Mike Huston" <microsoft.com> wrote in message
news:2f5d201c46c56$00dbf960$gbl...