Pages

Search

how do I import/copy tasks from one project file to another? Microsoft Project

how do I import/copy tasks from one project file to another? Microsoft Project


how do I import/copy tasks from one project file to another?

Posted: 24 Nov 2005 04:22 AM PST

what I should have mentioned is I'm replacing existing info. I'm able to copy
everything but the predecessors, once they go in the dates get messed up. I'm
doing something wrong?

"Jan De Messemaeker" wrote:
 

Booking Type - Propose resource

Posted: 23 Nov 2005 07:40 PM PST

Dale Howard ,
Sorry, next time i wll post Project Server questions to the
microsoft.public.project.server newsgroup.

I think my question have some problem.
I see the below information in microsoft project 2003
"Note that a resource's booking type applies to all their assignments in the
project"

So may i know have any way can set the resource booking type like this.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA (committed)
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA (committed)
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA (Propose)

I will post my question to microsoft.public.project.server newsgroup.

Thanks,
Ng


"Dale Howard [MVP]" wrote:
 

Changing Project Default Settings in an Existing Project

Posted: 23 Nov 2005 11:49 AM PST

Hi Bob,

If you want to change the week in Tools, Options, just do it. It will only
influence the display of the tasks where you explicitly used the week as the
unit to be displayed.

In the macro add within the loop
Job.effortdriven=false
But if you have already done the multiplication don't do it again :-))

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"bob1122" <microsoft.com> schreef in bericht
news:com... 
30h 
what 
in 
were 
work 
there a 


Cost per task

Posted: 23 Nov 2005 09:03 AM PST

Hi,

Yes. Insert the Cost line in the Resource Usage View.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"David M C" <microsoft.com> schreef in bericht
news:com... 
throughout 
use 
the 
that 
was 
or 
he 
You'll 
the 

more 
amount 
Project 
but 


Project specific calendar format change

Posted: 23 Nov 2005 08:25 AM PST

You're welcome mikejw. Thanks for the feedback.
Julie
"mikejw" <microsoft.com> wrote in message
news:com... 


Equipment Resource definitions

Posted: 23 Nov 2005 08:19 AM PST

As Gerarrd said - but note, the Server is a Work resource, not a material
resource. I meantion that because some people think "material" means
"inanimate." But that's not true. Material resources are used up and
incorporated into the delieverable. Your server isn't - it is performing
work that contributes to the task's deliverable, just like a person, but it
isn't used up in the process.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"MED" <microsoft.com> wrote in message
news:com... 

Project diagram view

Posted: 23 Nov 2005 07:48 AM PST

You're welcome, Jimmy :-)

Mike Glen
MS Project MVP


jimmyharris80 wrote: 



constraining tasks by hour

Posted: 23 Nov 2005 07:08 AM PST

I don't know - whenever I see Project being used simply to draw pictures of
a pre-existing schedule I have to wonder why you've spent $1500 for a
product and then only use it to do what could be done just as well by
spending $10 for a wall calendar and box of Magic Markers. At the very
least I'd suggest using it as a reality check, using it to independently
generate a proper schedule in order to confirm whether your pre-existing
master schedule is truly workable, to identify where the potential
bottlenecks may lie in it, and where you might change it to be more
efficient. I think of Project's role as telling ME the best schedule I can
expect to HAVE, given what needs to be done and the assets I'm able to
deploy to achieve it, rather than me telling IT the schedule we're expecting
to work. When you doing the work, building a proper schedule where Project
is calculating the task dates rather than merely parotting the dates you've
input will let you dynamically monitor the downstream effects of actual work
as it's being done so you can keep your "troops" deployed most effectively.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"mikejw" <microsoft.com> wrote in message
news:com... 

using a definite time frame for a task

Posted: 23 Nov 2005 04:30 AM PST

Mark the task non-effort driven, fixed duration.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"jake" <jake @discussions.microsoft.com> wrote in message
news:com... 

Modified Resource Usage View

Posted: 23 Nov 2005 01:58 AM PST

Thanks for the quick response. However this does not quite satisfy what I am
looking for. You see the excel generated by your suggestion provided me with
the following report format.
14-Nov-05 15-Nov-05 16-Nov-05 17-Nov-05 18-Nov-05
Resource A
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs
Resource B
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs
Resource C
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs
Resource D
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs
Resource E
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs
Resource F
Actual Work 8 hrs 8 hrs 8 hrs 8 hrs 8 hrs

The format that I need would look like this:
14-Nov-05 15-Nov-05 16-Nov-05 17-Nov-05 18-Nov-05
Resource A
Task 1 0 0 2 hrs 3 hrs 0
Task 2 8 hrs 8 hrs 6 hrs 5 hrs 8 hrs
Resource B
Task 2 0 1 hrs 1 hrs 0 2 hrs
Task 3 2 hrs 0 0 1 hrs 0
Task 4 6 hrs 7 hrs 7 hrs 7 hrs 6 hrs
Resource C
Task 4 2 hrs 3 hrs 0 0 8 hrs
Task 5 3 hrs 3 hrs 3 hrs 0
Task 6 3 hrs 5 hrs 5 hrs 5 hrs 0
Resource D
Task 2 4 hrs 4 hrs 4 hrs 4 hrs 0
Task 3 4 hrs 4 hrs 4 hrs 4 hrs 8 hrs
Resource E
Task 4 3 hrs 2 hrs 6 hrs 0 0
Task 6 5 hrs 6 hrs 2 hrs 8 hrs 8 hrs
Resource F
Task 1 2 hrs 0 8 hrs 8 hrs 8 hrs
Task 3 1 hrs 0 0 0 0
Task 4 2 hrs 0 0 0 0
Task 5 3 hrs 8 hrs 0 0 0

or the following format may do as well
Name Task Name Date Actual Work
Resource A Task 1 11/16/2005 2
Resource A Task 1 11/17/2005 3
Resource A Task 1 11/18/2005 1
Resource A Task 2 11/14/2005 8
Resource A Task 2 11/15/2005 8
Resource A Task 2 11/16/2005 6
Resource A Task 2 11/17/2005 5
Resource A Task 2 11/18/2005 7
Resource B Task 2 11/15/2005 1
Resource B Task 2 11/16/2005 1
Resource B Task 2 11/18/2005 2
Resource B Task 3 11/14/2005 2
Resource B Task 3 11/17/2005 1
Resource B Task 4 11/14/2005 6
Resource B Task 4 11/15/2005 7
Resource B Task 4 11/16/2005 7
Resource B Task 4 11/17/2005 7
Resource B Task 4 11/18/2005 6
Resource C Task 4 11/14/2005 2
Resource C Task 4 11/15/2005 3
Resource C Task 4 11/18/2005 8

Any suggestions?

Thanks

--
Albert


"Gérard Ducouret" wrote:
 

Converting Finish Variance to total Calendar days

Posted: 22 Nov 2005 07:30 PM PST

Dear Harris and Manmeet

Thank you very much for your helpful response.

Dan

"Haris Rashid" wrote:
 

Rolling up Red, Green, Yellow

Posted: 22 Nov 2005 07:24 PM PST

Hi Glenn,

When you will introduce conditions between fields of several taks you will need VBA.
Formulas are restricted to comparing fields within the task
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Glenn" <com> schreef in bericht news:phx.gbl...
Perfect Gerard!

I was actually using a text field, initially, and wondered how to utilize the rollup feature. I didn't think about trying a number field, but since you mentioned it, it makes perfect sense!

I'm going to take another step... not only will I show red, green, yellow based on completion and date. I will use a number or text field, where I can use it to override the automated settings for tasks that have plenty of time to finish, but have issues that won't allow it to complete on time. This will then show a yellow flag until I discontinue the override.

An example of this would be where if a task is "Install router". Eventhough the date may be a 2 months out and the router can be shipped in 3 weeks and the indicator shows green, If I know the rack can't be installed in time to install the router, I want the ability to force a yellow flag indicator for the task "Install router". Now I need to figure-out how to automagically change the flag to yellow on the "Install router" task, if I force a yellow flag on the predecessor task "Install rack".

I love MS Project! It never ceases to amaze me with it's abilities!!

Glenn
"Gérard Ducouret" <fr> wrote in message news:O%phx.gbl...
Hello Glenn,
You don't say what kind of field you used to these Red, Yellow and Green symbols.
If you used a Number(x) field and if the Red color matches the greatest value, in the Customize Field dialog, for Summaries and groups, select Report : Maximum
Hope this helps, tell us if that work,

Gérard ducouret
"Glenn" <com> a écrit dans le message de news:%23Z%phx.gbl...
I've created a text field formula that allows me graphical indicators to show whether a task is on track.

How do I have the summary row show a specific indicator based on the subtasks below? Although I think I want it to show the worst indicator of the subtasks, I want the flexibility to change as necessary.

Example:

1 ysis (summary row - how do I show RED, based on the below?)
2 Interview Client (subtask - done ontime, GREEN)
3 Create ysis doent (subtask - not done, due yesterday, RED)
4 Review with Resources (subtask - due tomorrow, YELLOW)

Thanks in advance for any assistance
Glenn

General Comment on Custom Functions

Posted: 22 Nov 2005 04:45 PM PST

I would love to know how as well

Majid


"Haris Rashid" wrote:
 

Time Sheet Updates using specific hours per day

Posted: 22 Nov 2005 04:21 PM PST

hi,

you seem to have set a constraint on your task. A task starting on Oct 3
with 10 days duration should finish on Oct 14. Since you have the finish date
of Oct 19 you might have a constraint such as "Finish As Late As Possible",
etc.

When a task is first created, the percent complete is zero percent. As soon
as you enter actual duration, remaining duration, or actual work (which
affects actual duration), Project calculates percent complete as follows:

Percent Complete = (Actual Duration / Duration) * 100

If the % Complete field is set to a value greater than zero, the Actual
Start field is set to the scheduled start date if you have not yet entered an
actual start date. If the % Complete field is set to 100, the Actual Finish
field is set to the scheduled finish date.

If you type a value in the % Complete field, Project automatically
calculates actual duration and remaining duration. Likewise, entering a value
in the Actual Duration or Remaining Duration field automatically recalculates
the other fields.

You can control whether changes to total percent complete are distributed
through the status date or to the end of the task's actual duration so far.
On the Tools menu, click Options. On the Calculation tab, select or clear the
Edits to total task % complete will be spread to the status date check box.

When you enter percent complete, Project might adjust actual and remaining
work around the current status date. If you prefer, you can leave these
tracking fields in the project as originally scheduled, even if completed
work is shown in the future or remaining work is shown in the past. On the
Tools menu, click Options. On the Calculation tab, clear the Move end of
completed parts after status date back to status date and Move start of
remaining parts before status date forward to status date check boxes.

To set the status date to a date other than today's date, click Project
Information on the Project menu, and then enter the date in the Status date
box.

Regards,
-----------------
Haris
http://www.manage-systems.com
----------------------------------------

"Grant" wrote:
 

smart predesessor pasting

Posted: 22 Nov 2005 02:13 PM PST


John wrote: 

I always caution people about having multiple tasks with the same name.
It can lead to a great deal of confusion, both in the Network Diagram
and in a sorted or filtered Gantt. It can be hard to tell with "Review
Drawings" you're looking at if there are several of them. If you ask on
here, someone will have a VBA macro that puts the appropriate summary
task name, if they're unique, into the task name. So your tasks would
be "Preparation Review Drawings" and "Final Review Drawings", etc. Can
save a lot of headaches down the road.
Hope this helps in your world.

Custom report showing dependencies' % complete, estimated complete date, and actual complete date

Posted: 22 Nov 2005 02:11 PM PST

In article <googlegroups.com>,
"com" <com> wrote:
 

anewton,
Sure, just write me direct - I receive a fair amount of "off-list"
queries.

John
Project MVP
mjensenatattheriverdotdotcom
delete obvious redundancies

How do I get my Visual Basic "New Project" dialog box back?

Posted: 22 Nov 2005 08:29 AM PST



"John" wrote:
 

How do I set a project task effort to be a percentage of other tas

Posted: 22 Nov 2005 08:20 AM PST

Oops,

http://www.andythevikingfordham.com/

One hundred ......and forrrrrrtttttyyyyyy! cheer cheer



"John" <com> wrote in message news:microsoft.com... 


Is there a way to lock a completed task in MS Project 2003?

Posted: 22 Nov 2005 07:31 AM PST

In article <com>,
Dan Bridy <microsoft.com> wrote:
 

Dan,
Whew! I'm glad you won't have to shoot anybody either - I hate when that
happens - it's just so messy.

Seriously, you're welcome.

John

Dealing with Effort and Duration

Posted: 22 Nov 2005 06:35 AM PST

I like your approach!!!!! <grin>
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"John Sitka" <com> wrote in message
news:%phx.gbl... 

Disable field after entry

Posted: 22 Nov 2005 05:07 AM PST

Hi Trev,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


Trev wrote: 



Track Actual Hours without changing Start-Finish Date

Posted: 21 Nov 2005 04:37 PM PST

Are you tracking *duration* hours or *work* hours? They are very different
measures. Duration is time and there absolutely positively cannot be more
than 24 duration hours in a day, at least on this planet. Work, OTOH, is
actually "man-hours" and when two people work together for 24 hours, they do
a total of 48 man-hours of work.

Do you really have 24 hour workdays? That means that when a task begins it
doesn't stop until it's completed AND the resources assigned to it work on
it for the entire period of time. If a task lasts 72 hours, that means that
the crew that works on it doesn't rest, eat a meal, take a break or a nap,
or get any time off whatsoever for the entire continuous 3 days. It does
NOT mean that you have people coming and going with some guys working days,
others nights, etc. The 24 hour calendar says that if Joe is assigned
to that task, he joins the task when it starts and doesn't leave for any
reason until it's finished days later. Machines might do that but people
don't - they need at least to sleep and eat a little while out of each day.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Vicky" <microsoft.com> wrote in message
news:com... 

large plots for resource useage

Posted: 21 Nov 2005 01:58 PM PST

Mike,
Thanks but that's not it. I can go boack without any other changes and
make the plot size 30" x 50" (without changing the columns) and it works.
There must be some undoented plot length for data !?
It's really weird, as the backgound plots out fine. The actual data just
gives a '#' and stops filling in the data. I think its a limitation by
number of columns or plot length. It would seem like it would stop plotting
everything instead of just the actual work data.....
If you think of anything let me know but this is no show stopper.

Thanks

--
Best Regards,
Eddie A


"Mike Glen" wrote:
 

Charts and Graphs

Posted: 21 Nov 2005 12:48 PM PST

In article <com>,
"motor_mouth" <microsoft.com> wrote:
 

motor_mouth,
Oh sure, now the whole story comes out ;-)

The Resource Graph view in Project is by resource rather than by task
assignment so you are probably not going to get the information
directly. There are a couple of options. The option I would chose (and
have used on some of my projects) may be a little advanced because it
involves using a VBA macro to export the necessary data to Excel and
then plotting it in a manpower curve. However, an equivalent process can
be used without a custom VBA macro. Starting from the Task Usage view,
use the "yze timescale data in Excel" untility/add-in found on the
"ysis" toolbar (I would export the Work field). Once the data is in
Excel, use Excel's charting capability to develop the graph you want.

Just for reference you might want to consider using a rolling average
instead of exact monthly values when it comes to reviewing manpower
needs, (I used a 3 month rolling average), otherwise you will end up
with hiring/layoff spikes that don't reflect reality.

Hope this helps.
John
Project MVP

Deadline vs. Must Start On

Posted: 21 Nov 2005 11:34 AM PST

Tools menu, Customize, Fields - create a flag field with a formula that
tests for the condition you're monitoring and choose "graphical indicators"
in the dialog box as the results display.

I wonder at the logic of looking at start date with respect to a deadline.
Deadlines describe the required completion date for the task. Checking to
see if a task is started by 90 days before its deadline really only makes
sense if the task requires 90 days to do. The duration of a task is your
best-guess estimate of how long it will actually take to complete the task
once it starts. Comparing a start date with a deadline only gives you useful
information if the time frame you're looking at compares the start with the
deadline minus the duration and it will only be 90, 60, or 15 days if the
task duration also happens to be 90, 60, or 15 days respectively. What
counts is not that it starts 90 days ahead of deadline but rather that it
has started by whatever you have determined is the latest date it should
start so that it can finish by the deadline. Best practice suggests that
when a resource is assigned to a task they will be expected to start it on
the date you have scheduled it to start and work on it full-time until it
has finished. The duration of the task is not how long they are allowed to
finish it - it's your best estimate of how long you think it should take
them to finish it.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"JenEx" <microsoft.com> wrote in message
news:com... 

Microsoft Word - Independence of heading styles while leaving hierarchical numbering intact

Microsoft Word - Independence of heading styles while leaving hierarchical numbering intact


Independence of heading styles while leaving hierarchical numbering intact

Posted: 30 Nov 2014 02:30 PM PST

My Heading styles are hierarchically related in the numbering system, and Heading 2 (e.g. CHapter 4.7) is based on 1 (e.g. Chapter 4), Heading 3 (Chapter 4.7.5) on 2, etc

Because of this,any change made to Heading 1 will be inherited to Heading 2, etc. However, I wanted to change that, in order to make the styles independent from the point of view of font-related changes. So I chose, for HEading 2, "style based on = (no style)". However, more than making it independent from Heading 1, this also took Heading 2 out of the numbering system, such that now, titles who have Heading 2 applied to them are no longer numbered.

How can I make Heading 2 be independent from Heading 1 while keeping it in the numberning system?

THanks!

Setting defaults for the Insert Picture window

Posted: 30 Nov 2014 01:49 PM PST

when the Insert Picture window opens, it always defaults to

1) a large icon view, and

2) to some random system folder that I never use

Can it be made to always open in

1) Details view, and

2) to a specific folder that I indicate?

Repeat picture formatting

Posted: 30 Nov 2014 01:39 PM PST

To repeat (copy) the formatting of a selection of text to another selection of text, the shortcuts Shift+Ctrl+C and Shift+Ctrl+V can be used, for copying and pasting the formatting respectively.

Is there anything similar to repeat the formatting of a picture inserted in a document, with everything that it entails, e.g. picture size, borders, alignment etc?

Word count fails when counting sections with Endnote citations

Posted: 30 Nov 2014 01:32 PM PST

For example if I select only a word followed by a citation in superscipt, like this:   approach9

automatic word count at the bottom of Word gives me exorbitantly large numbers: 295 OF 5310 WORDS

Hopefully though when I press on that to get details it gives me correct statistics (i.e. 1 word). Why is that?

Microsoft Word, equation, numbering, referencing

Posted: 30 Nov 2014 01:26 PM PST

In Microsoft Word it would be nice to have right aligned automatically generated equation numbers. When referencing to an equation it would be nice to get a list of all equations (in 'professional lay-out'), and then you just have to click on the equation you want to reference.

Word Home & Student 2013 Won't double space existing text Windows 8.1

Posted: 30 Nov 2014 01:14 PM PST

Why won't it double space my work?  It will double space from beginning of a document but won't let ,e double space existing documents OR it double spaces a couple of pages!  I go into design and chose paragraph spacing, double space and... nothing happens!  How do i double space exisiting work?

In Word 2010, how can I get my Outline numbering to show both Level 2 and Level 3 with the same numbering but only one has a heading while the other does not?

Posted: 30 Nov 2014 12:52 PM PST

Nov. 30, 2014 - I could use a quick response to this Word 2010 question, if there is an answer - thanks!

I have a 39 page Word 2010 and my outline numbering holds fine.  However, when I get to page 36 of this 39 page document Level 2 Outline Numbering has no headings for Level 2 - starting with 27.1  Definitions.  I am wondering, since I am using 5 levels of numbering in total in this one document, if I can somehow move each of the numbering levels from level 3 down one level and somehow make Level 3 start at 27.1 so that when I get to page 36, this Level 3 numbering would kick in or be applied and show up as 27.1 but absolutely no headings, only paragraph text beside it instead?  I cannot seem to get it to work no matter how I try to make Level 3 numbering to look exactly like Level 2 numbering (i.e., both would look and work exactly the same but only one would have no headings whatsoever and that is Level 3? Has anyone ever tried this or something else that would work in this situation - thanks?

Set a table in the size of an A4 paper

Posted: 30 Nov 2014 10:40 AM PST

I want to print a document that is in an A3 paper size, in which there is a frame in the size of an A4 paper.

After printed, I cut the paper and have a document in the size of A4, with no frames at all.

How could I set up this frame so it would fit to an A4?

Thanks.

Microsoft 2010

Posted: 30 Nov 2014 09:00 AM PST

I just bought a new computer and on my old one I had Word 2010. I cannot find how to transfer this word over to my new computer. I cannot find any free downloads. When I enter the product key on Microsoft's website it tells me that the key is not valid for word 2013. I do not want to pay another $100 when the 2010 version works just fine.

Is there anyway to get 2010 installed on my new PC?

hi dear experts I would like to get a macro for searching every single text contained in a cell (on a Ms word table) in the next right cell only, and replace it with £ character

Posted: 30 Nov 2014 08:45 AM PST

the find and replace process takes place only in the left cell on each row of a Ms table composed of two columns and N rows, then the next row the same search the text in the left cell in the next right cell and repace it with a character for example the pound £. in other words we copy the text in the first left cell and search it in the next right cell which is the last, and then we replace it, no more than this cell, then the same process for then down next row. 

many thanks in advance. 

 

Prob w/ virtual terminals - Forums Linux

Prob w/ virtual terminals - Forums Linux


Prob w/ virtual terminals

Posted: 29 Feb 2008 10:42 AM PST

Two Ravens wrote:

For those that wish to check on the quality of posts made by Tom Newton
try reading this page, http://tinyurl.com/3y5vhe

--
Two Ravens
"Tom Newton, surely the William Topaz McGonagall of
alt.os.linux.slackware, and now, seemingly, comp.os.linux.setup and
comp.os.linux.misc.as well!"

Rebuilding my server

Posted: 27 Feb 2008 03:06 AM PST

Bill Baka wrote: 
 

I doubt a gamer would want that motherboard, but it is perfectly good for a
server or serious workstation. I bought it off-the-shelf; i.e., it was not a
special order.

http://www.supermicro.com/products/motherboard/Xeon/E7501/X5DP8-G2.cfm

Here are some highlights:

1. Dual Intel® Xeon® Support up to 3.2 GHz
2. Intel® E7501 Chipset
3. Up to 16GB DDR 266/200 SDRAM
4. Intel® 82546EB Dual Port Gigabit Ethernet Controller
5. Adaptec AIC-7902 Dual-Channel Ultra320 SCSI
6. 6x 64-bit PCI-X expansion slots
7. ATI RageXL 8MB PCI Graphic Controller
8. Zero-Channel RAID Support

PCI • Max 2x 64-bit 133MHz PCI-X (3.3V) slots
Default:
• 3x 64-bit 100/66MHz PCI-X (3.3V) slot
• 3x 64-bit 66MHz PCI-X (3.3V) slots
• 1x SXB (Supermicrol Extended Bus) slot
IDE • Dual EIDE channels support up to four UDMA IDE devices
• Supports UDMA Mode 5, PIO Mode 4, and ATA/100
USB Up to 5 USB ports
Serial Ports 2 Fast UART 16550 serial ports
Parallel Port 1 ECP/EEP parallel port
Floppy 1 Floppy controller; 1.44 MB, 2.88 MB, 3-mode support
Keyboard / Mouse PS/2 keyboard and mouse ports

There are multiple PCI busses -- actually PCI-X so they are 64-bit, not just
32-bit.
One has three 66 MHz slots.
One has one 100 MHz slot and the dual SCSI controller
One has one 100 MHz slot and the dual gigabit LAN controller
One has one 100 MHz slot and nothing else.

The speeds of these slots can be adjusted in the BIOS among 33MHz, 66 MHz,
100 MHz, and 133 MHz

--
.~. Jean-David Beyer Registered Linux User 85642.
/V\ PGP-Key: 9A2FC99A Registered Machine 241939.
/( )\ Shrewsbury, New Jersey http://counter.li.org
^^-^^ 08:00:01 up 17 days, 14:11, 1 user, load average: 4.16, 4.20, 4.16

Bulletproofing a Linux server

Posted: 25 Feb 2008 09:13 AM PST

On Fri, 29 Feb 2008 01:27:02 +0100, unknown rearranged some electrons to
say:
 

google "sarcasm"

Is there a good console-based POP3/SMTP compatible mail reader?

Posted: 24 Feb 2008 09:03 AM PST

The Natural Philosopher wrote: 
 

I was apparently unclear. Deleting all your POP3 mail accessible mail from the
server the first time you run any POP3 client It should be a *manually
selected option*, not the default that strips it all and s up all your
mailboxes on other clients the first time you turn on the client and have the
network cable connected.

Been there, done that, have the T-shirt of restoring several Gig of important
corporate person's email in their client folders despite their unwillingness
to switch to IMAP or to allow proper backups of their laptop. I shudder at the
memories.

linux-2.6.24 makes /dev/hda inaccessible

Posted: 24 Feb 2008 08:07 AM PST

HamRadio wrote: 


--
Leon
A computer without Microsoft is like a chocolate cake without mustard.
< running Linux >
You may find that if you change the hda whatever to sda whatever things will
start to work.

KDE 4.1 snapshot screenshots [eye kandy]

Posted: 24 Feb 2008 02:54 AM PST

Tom Newton wrote:
 

a) Please quantify the amount of resources you save.

b) what are the better purposes upon which you expend these 'saved'
resources?

--
Two Ravens
Tom Newton, surely the William Topaz McGonagall of
alt.os.linux.slackware!

Bizarre Problem with GRUB

Posted: 21 Feb 2008 02:35 PM PST

On Wed, 27 Feb 2008 08:38:27 -0800, DDave65 wrote:
 
I haven't used CloneZilla, but another tool to consider using is
ntfsclone. I have used it to backup/restore partitions which are
formatted using NTFS. This does not attempt to get information about the
entire disk- just individual partitions.

Here is a command sequence which saves a partition in "special format"
# ntfsclone -s -o ~/sda1.sf.img /dev/sda1

Or use a compression stage to save space:
# ntfsclone -s -o - /dev/sda1 | gzip >~/sda1.sf.img.gz

Here is a command sequence which restores a "special format" image:

# ntfsclone -r -O /dev/sda1 ~/sda1.sf.img


Similarly, for an image which uses compression:

# cat ~/sda1.sf.img.gz | gzip -cd | ntfsclone -r -O /dev/sda1 -

Then this fixup may be required:

# ntfsresize /dev/sda1

The last command is necessary if the "volume size" of the saved image
is smaller than the target partition. It enlarges to final volume to
match the underlying partition size. 
I wouldn't be surprised if CloneZilla is part of the problem you are
having, but I could be wrong. IMO, working with individual partition
images is the way to go. Once you have restored each partition image
separately, then the last step is to fixup the grub loader. This
approach will automatically fixup various mismatches, which I alluded
to in my initial post. IMO, the hard-disk-upgrade mini howto is a good
starting point to begin learning about disk images.

Just for comparison, here are the steps I would follow to do something
similar..

Sequence:
0. Connect target USB device.
1. Use fdisk to setup the target partition layout. BartPE on partition 1,
I think.

2. Preformat linux partitions with the file system of your choice. IIRC,
avoid using ReiserFS. Primarily, I use XFS. It has some neat resize
features, etc.

3. Restore images.
3.a. For NTFS partitions, use ntfsclone. Example shown above.
3.b. For Linux partitions, use tar (tgz archives). Perhaps, using this
sequence:

cat sda2.tgz | gzip -cd | (cd /mnt/sda2 && tar -xvf - --numeric-owner)

4. Fix grub loader.

# grub --no-floppy
grub> geometry (hd1)
grub> root (hd1,1)
grub> setup (hd1)
grub> quit

Note: use geometry (or some other method) to verify how grub has "counted"
your usb disk. "Hit" the proper target.

5. Shutdown and test reboot with usb.

Disclaimers:
1. I hope I didn't make any blatant mistakes. Check my commands carefully
before using them.
2. There are also many assumptions built in to this explanation. Be sure
of any commands you use are appropriate for your system.
3. Understand what you are doing and the underlying principles (hardware,
software, nomenclature, etc.)
4.Practice using the tools which you have selected until you are
comfortable using them.

--
Douglas Mayne

Start up VMware Workstation automatically?

Posted: 20 Feb 2008 10:22 AM PST

On Thu, 2008-02-21 at 01:28 -0800, Nico Kadel-Garcia wrote: 
.... 

Oh. Well... still, FreeNX is something to look at. I think you
should be able to establish something similar where VMware Server
is started up graphically under a FreeNX session and then attach
to that whenever. Of course kick starting all of this (as you
mentioned) is probably the biggest problem. But I would think
it would be possible (???).

Debian kernel compile question.

Posted: 18 Feb 2008 09:40 AM PST



That did it.

Thanks muchly.

Overt

Fedora Core 6 Memory Stick problem

Posted: 06 Feb 2008 04:04 AM PST


Marc Schwartz <net> writes:
 

Well, I upgraded to f8 as Marc Schwartz suggested and that did fix the
Memory Stick problem; but then with f8 I had several other glitches more
critical than the Memory Stick, so I had to revert back to fc6.

But I recently noticed with fc6 that if I suspend and then resume then both
/dev/sda and /dev/sda1 are automatically created and it recognized the
Memory Stick device on /dev/sda1 and all works fine.

So that is a huge clue: What does the suspend/resume do that the boot does
not do? If I can determine this then I can stick a quick hack into
/etc/rc.d/rc.local (until f9 or so) to mimic at boot time what is done on
suspend/resume. If anyone has any clues for me as what suspend/resume does
in terms of rescanning for such devices it would be greatly appreciated.

Thanks

--
William P. Vrotney - net

 

What does "eday" stand for in MS Project 2003 Microsoft Project

What does "eday" stand for in MS Project 2003 Microsoft Project


What does "eday" stand for in MS Project 2003

Posted: 18 Nov 2005 06:16 PM PST

Note that you can enter your task durations in edays as well. This is useful
when you have tasks which do not obey working hours (things like waiting for
concrete to cure are typical examples)

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Gilgamesh" <me.not> wrote in message
news:phx.gbl... 



Linking Tasks in Project 98

Posted: 18 Nov 2005 12:31 PM PST

It should with the exception of using a formula to set the flags. You will
have to set them by hand or use some VBA.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Brian Connolly" <microsoft.com> wrote in message
news:com... 
http://zo-d.com/blog/archives/ms-project-tips/formatting-task-links-in-ms-project.html 
message 
of. 
visit 
dependency 

link 
links). 
know 
all 


adding formula

Posted: 18 Nov 2005 11:57 AM PST

Hi

Square brackets are only required if there are spaces in the field name but
usually I do use them as standard with or without spaces ....


--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer


"JackD" wrote:
 

Symbol for illustrating indented tasks was a + with a box around i

Posted: 18 Nov 2005 09:55 AM PST

Hi Robert,

We need to discover whether it is Project at fault, or whether it's your PC.
Does it occur with this project on other PCs? If you have no other PC, as
it sounds like corruption within Project, try re-installing Project.

Mike Glen
MS Project MVP

com wrote: 



Tracking Tasks that can be Completed Out of Order

Posted: 18 Nov 2005 08:15 AM PST

You might remove the links and use the task priority setting in conjunction
with resource leveling to set the order they will likely be worked on.
Links should not be used to describe the order you *want* to work on tasks,
they should describe the order you MUST work on the tasks because of
something inherent in the process itself. When building a structure we link
"erect walls" as a predecessor to "install roof" not because we usually do
it that way but rather because the law of gravity says we cannot build the
roof in midair and later stuff the walls in underneath it <grin>. Linking
A->B says that A produces as its output something that is needed as an input
for B and as a result B cannot start until A is done. If that's not true,
remove the link and use something else to model the sequencing.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"tgr" <microsoft.com> wrote in message
news:com... 

I thought the smallest units were Minutes?

Posted: 17 Nov 2005 01:32 PM PST

Duration would be deciminute, work milliminute :)

"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in message
news:phx.gbl... 

How to make a backup of a master project

Posted: 17 Nov 2005 01:07 PM PST

Hi Tina,

Thanks for your reply. I do not quite understand what you mean when
saying you change the "high level label inside the master project"

Thanks

ODBC in VBA

Posted: 17 Nov 2005 12:59 PM PST

I didn't know there was a microsoft.public.project.developer's group.
I'll look there. Thanks for your help!

Loading a Project from Excel

Posted: 17 Nov 2005 12:37 PM PST

Thanks Jack. I checked the doentation and it seems relatively
straightforward. One question I can't find: Can we load multiple projects in
one pass (one project per line)? or is it just open an excel file that has
one line of data, create the project, close that projects, then open the next
line, create the project, close the project, etc.). With a thousand projects
to create, that would be a time consuming job.

Thanks.

"JackD" wrote:
 

Filtering for only cross-project links

Posted: 17 Nov 2005 12:15 PM PST

Hi Andrew,

Glad to know the formula worked and thanks for the feedback.

Without seeing your project file, it is only a guess, but I assume the
reason why you only need the first part of the formula in a master project
is that if a task is an external successor to one task, it is also an
external predecessor to another task in the project. Tasks actually entered
into the master are internal -- all others (from the subproject files) are
external.

Hope this helps.

Julie

"Andrew K" <microsoft.com> wrote in message
news:com... 


Viewer for documents created in Project

Posted: 17 Nov 2005 08:17 AM PST

Yes, There is some views. Some are free. See our doent :
http://www.ixila.com/Telecharger/Quel%20lecteur%20Microsoft%20Project%20choisir.pdf
Regards,
Xavier
Ixila

Set a start AND end date for a project?

Posted: 16 Nov 2005 08:39 PM PST

A project mathematically simply cannot have a fixed beginning date AND a
fixed ending date. It may, indeed usually DOES, have a date by which it
needs to end but that's not the same thing as the end date. That's the
TARGET for the end date. The project end date itself is that date on which
the last bit of work is done and the project deliverable is completed. That
event may occur before, on, or after the target end date but it occurs
whenever it occurs - Mother Nature and the laws of physics don't care
whether you're on time or late, only the bossand the client cares about that
<grin>. Project's job is to look at the physical work to be done and the
way you deploy your assets to do it and predict when the physical end is
likely to occur so you can create a workable plan that meets the boss's
objectives. When you schedule from the start date forward, you input the
date you will start work and the structure of the work itself, including
your best estimate of the duration of each component task. Project then
computes when the project would end IF you structured the work and assigned
the resources the way you have proposed. If it meets or is better than your
required target, great. If it's not, you don't just designate the date you
want, you must actually revise the organization of the work and/or the
assignment of the resources in order to materially change the computed
schedule so that it finishes where it should.

All of your 1200 tasks should lead up to a finish milestone. Every task in
the project should be linked to a successor except for that one milestone -
if there's no actual activity that is the successor to a given task, the
finish milestone is its successor. You set a deadline on the finish that is
the client's required date. After building your task list, linking them,
and assigning resources to them, you compare the computed scheduled finish
with the deadline for the finish and if necessary iteratively revise the
plan until it's computed to finish on or before the deadline.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



<com> wrote in message
news:googlegroups.com... 

To do list Report doesn't show Work per resource

Posted: 16 Nov 2005 05:04 PM PST

In article <com>,
Pete C <microsoft.com> wrote:
 

Pete,
Well the Resource Usage view DOES have a single value of work by task
assignment for each resource. What is a little more difficult to obtain
in that view is the assignment (i.e. task) duration and % complete. That
information CAN be added to the view using spare assignment fields. You
might want to take a look at our MVP website:
http://www.mvps.org/project/faqs.htm
FAQ 37 - Custom fields in tables

John
Project MVP