Graphical indicator field to reflect constraint type Microsoft Project |
- Graphical indicator field to reflect constraint type
- Problems With Microsoft Project 2003 Trial Version
- How do I setup a task to last 2 weeks but only take 4 hours
- How can I format tasks with a strike through (crossed-off)
- Group BY Date Time
- Gantt Chart different than Resource Usage
- Missing BCWS values
- How can I find out if all the tasks in the schedule are baselined?
- Why am I unable to see BCWS values for tasks?
- macro execution
- Complex (or not) question about filtered exporting
- external task
- Indented-Outdented tasks
- How to renumber W.B.S. codes
- Outlook Add-In Is Not Working
- Printing Gantt timescale in MSP 2000
- Managing a project with contractors: not intrerested in resource allocation
- How to setup a column containing the summary name for each task?
- questions
- allow highschool students to get educational discounts
- Order of details under Resource in Who does What Report
- Work schedule progress question
- How to ask for updates in MS project
- where can I find a manual for Project 2003
- How do I change cells with #### in Project?
Graphical indicator field to reflect constraint type Posted: 07 Jun 2005 06:48 PM PDT Hello, Wendy. The Constraint Type is a numeric field. 0 = As soon as possible 1 = As late as possible 2 = Must start on 3 = Must finish on 4 = Start no earlier than 5 = Start no later than 6 = Finish no earlier than 7 = Finish no later than Use one of the custom number fields (Number1, Number2, ...), setting it to be equal to the field Constraint Type (the formula is just that: [Constraint Type]) and to use the graphical indicators. Using the examples in your post, 0 = indicator green 7 = indicator blue ... Hope this helps. Cheers, Joaquim Amado Lopes On Tue, 7 Jun 2005 18:48:01 -0700, wendyB <microsoft.com> wrote: |
Problems With Microsoft Project 2003 Trial Version Posted: 07 Jun 2005 05:51 PM PDT I went to Number 6 Trial Booting. It suggested that I: try modifying registry key: HKEY_USERS\S-1-5-21-1661544484-239356022-623648099-500\Software\Microsoft\Office\8.0\MSProject\Option s\General. Change value of FirstBoot from "No" to "Yes". I went to regedit. I do not have the folder cited above. The closest I have are 2 folders that start with HKEY_USERS\S-1-15-21-3935143360. Thanks in advance for all of your assistance! I also am getting the gbui trusted site issues since I have deleted that from Internet Explorer trusted sites. I now have to go Task Manager in order to exit the Project application. "Brian K - Project MVP" wrote: |
How do I setup a task to last 2 weeks but only take 4 hours Posted: 07 Jun 2005 03:33 PM PDT Boybanshee wrote: Are you saying it will take 4 hours of work but that 4 hours will be spread across 2 weeks? -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
How can I format tasks with a strike through (crossed-off) Posted: 07 Jun 2005 03:03 PM PDT In article <com>, Cob100 <microsoft.com> wrote: cob100, I guess you didn't like the answer that Mike and I gave you the first time you posted. But as you can see from Brian's response, the answer hasn't changed. John |
Posted: 07 Jun 2005 02:35 PM PDT "Harry" wrote: Also. When I sort by date and time in sequence order the start times do not appear to be in sequence.. The later start times appear before the earlier start times in a particular date. e.g. 1:00 PM appear before 9:00 AM. Can you please explain what I am doingwrong. Thanks. Harry |
Gantt Chart different than Resource Usage Posted: 07 Jun 2005 01:58 PM PDT Thanks for your response - each task has only one resource assigned. -- Keith Loewen, MBA, PMP "Brian K - Project MVP" wrote: |
Posted: 07 Jun 2005 12:16 PM PDT Yes it will. But your only other choice is to find a copy of the schedule before you made any updates, baseline it correctly and then update it to match your current schedule. Sometimes the best you can do is just start now and ignore any water that has already passed under the bridge. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "nan" <microsoft.com> wrote in message news:com... (BCWS & information. It's |
How can I find out if all the tasks in the schedule are baselined? Posted: 07 Jun 2005 09:37 AM PDT Thanks! "JackD" wrote: |
Why am I unable to see BCWS values for tasks? Posted: 07 Jun 2005 09:25 AM PDT Yes, if you want a baseline with the correct cost information you must set it now. -- -Jack ... For Microsoft Project information and macro examples visit http://masamiki.com/project or http://zo-d.com/blog/index.html .. "nan" <microsoft.com> wrote in message news:com... |
Posted: 07 Jun 2005 09:20 AM PDT That was a great help. Things are much faster and I can limit the tasks to check. Thanks again. "JackD" wrote: |
Complex (or not) question about filtered exporting Posted: 07 Jun 2005 09:06 AM PDT Oops! I meant FAQ# 31. Customizing Task Bars - sorry! You might also like to have a look at my series on Microsoft Project in the TechTrax ezine, particularly # Microsoft Project: 14 and 15 Customizing Fields, at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the article before leaving the site, :) Thanks.) Mike Glen MS Project MVP |
Posted: 07 Jun 2005 01:25 AM PDT Hi Daniela, If you only want clarity by coloring some tasks differently, that's no problem. See http://www.mvps.org/project/faqs.htm Faq 31. Customizing Task Bars HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Guidho" <nospam@mybox> schreef in bericht news:phx.gbl... different |
Posted: 06 Jun 2005 12:11 PM PDT Thanks -- Raymond Beliveau Project Manager for Health Canada "Raymond Beliveau" wrote: |
Posted: 06 Jun 2005 11:18 AM PDT Hey thanks Jim! That is very easy but I never would have figured it out. Bill R. "Jim Spiller" wrote: |
Posted: 06 Jun 2005 09:43 AM PDT I posted on the server newsgroup, maybe 2 weeks ago, no replies. Does this mean that you are unable to help me? In that case I guess I'll just buy the server book when it becomes avaliable. Thanks though, Steve "Mike Glen" wrote: |
Printing Gantt timescale in MSP 2000 Posted: 06 Jun 2005 06:15 AM PDT John: Thanks for the reply. On a technical note, I had a typo in my post and am running MSP2002. To get to your point, I have a fluid range in both the middle and lower tier- years then quarters- no skipping. It appears to be scaled adequately, but basically just shows blank cells when I print. I can see the spaces that would hold text, but they are not populated. I have since tested the file on other PC's at my office and it works fine- I can see the dates in the timescale, so it is a setting on my PC, I just cannot for the life of me figure out which one it is. "John" wrote: |
Managing a project with contractors: not intrerested in resource allocation Posted: 06 Jun 2005 05:58 AM PDT Thanks to all who responded. It looks like Project is a good option in this scenario after all. Dave On 6 Jun 2005 12:26:13 -0700, "davegb" <com> wrote: |
How to setup a column containing the summary name for each task? Posted: 06 Jun 2005 05:40 AM PDT Hi, The VBA macro youneed is quite simpel: Sub SummName dim job as task for each job in activeproject.tasks if not job is nothing then if not job.outlinelevel=1 then job.text7=job.outlineparent.name end if end if next jopb end sub HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "ellebelle" <microsoft.com> schreef in bericht news:com... name |
Posted: 06 Jun 2005 02:34 AM PDT for image(bottom right).page 3* "dan" wrote: |
allow highschool students to get educational discounts Posted: 05 Jun 2005 09:46 AM PDT I hope the person who first asked this question is following this thread. If not, maybe someone can find a way to get this information to them. As a student, they can get the standalone version of Project for $70 at www.journeyed.com. They have to provide proof of the fact that they are a student (or teacher). They can also get almost any other major software package at a large discount at this site. Ken Wright wrote: |
Order of details under Resource in Who does What Report Posted: 04 Jun 2005 03:34 AM PDT Hi Margaret als, Glad to know the tip I gave worked well for you and thanks so much for the feedback. As far as protocol for newsgroups posting, I think this newsgroup is pretty flexible. (Not all newsgroups are.) I usually post my replies at the top (sometimes called "top posting") just because I think it is easier to follow the "conversation" in the post that way. Others post at the bottom. As far as deleting earlier threads in the conversation, I usually delete earlier portions if they are not "important" (in my opinion) to the current posting. I usually delete it just to make download a bit quicker - particularly for folks on a dial-up connection. Again, thanks for the feedback and let us know if you have any further questions. Julie "Margaret als" wrote: |
Work schedule progress question Posted: 03 Jun 2005 12:44 PM PDT Why would they object to your posting accurate information into the file? If Joe Resource was scheduled to wax the widgets on July 1st but actually got some of it done last week, shouldn't your file reflect that? Save a baseline before posting the progress and it will show what you'd planned so you can monitor actual versus planned if anybody asks. But progress by definition is what actually takes place and after it's done what you originally thought would take place is irrelevant. Seems like if you base your progress inputs on what actually happens, the calculations in the summary bars will be exactly what your bosses are asking you for. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Tomcat" <microsoft.com> wrote in message news:com... |
How to ask for updates in MS project Posted: 03 Jun 2005 10:44 AM PDT jorge wrote: Just to be clear, Project Server does not require you to post anything on the web. It does require that your project data will be on your internal network for sure but it will be secured so that only the right people have access to the data. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
where can I find a manual for Project 2003 Posted: 03 Jun 2005 10:28 AM PDT There are, of course, 3rd party manuals if you're willing to pay. I think Tim Pyron's Que manual "Using Project 200x" are the most complete and written by someone who knows Project Management. Unlike some of the other manuals, particularly the MS ones. For a simpler, less detailed one, I reccommend "MS Project for Dummies". Best of luck! JackD wrote: |
How do I change cells with #### in Project? Posted: 03 Jun 2005 09:02 AM PDT Joe -- I'm certain Jenna's question was no joke. This question is asked more frequently than you would probably believe and is generally a "newbie" question from someone who doesn't use Excel. Her question was more than appropriate for this group. Your response, however, was totally inappropriate. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com http://www.projectserverexperts.com "We wrote the book on Project Server" "Joe" <microsoft.com> wrote in message news:com... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |