Wrestling Part Time Resources with MS Project 2003 Microsoft Project

Wrestling Part Time Resources with MS Project 2003 Microsoft Project


Wrestling Part Time Resources with MS Project 2003

Posted: 24 Oct 2005 03:34 AM PDT

Hi Dougal,

Correct I do not know but DEFINITELY NOT RECOMMENDED.
I do not like to enter percent complete.
I enter actual work and check the accuracy of remaining work.
Why make the division yourself?
The most precise way is to enter actual work timephased (Insert the actual
work row in task Usage or Resource Usage View)
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Dougal" <microsoft.com> schreef in bericht
news:com... 
up 
only 
who 

week) 
time 
working 
in 
work 


find all successors of a task

Posted: 21 Oct 2005 01:43 PM PDT

Many thanks. I see a few more macros on your site that will help me.

Cheers,
Tamara

"JackD" wrote:
 

Can you apply a calendar to a group in MS Project?

Posted: 21 Oct 2005 01:37 PM PDT

Thank you both!

"Jan De Messemaeker" wrote:
 

text wrapping problems

Posted: 21 Oct 2005 12:43 PM PDT

Thanks for the responses.

"JohnF" wrote:
 

Broken Project Installation

Posted: 21 Oct 2005 11:49 AM PDT

"Thor Kottelin" wrote: 

I had a look in the registry, there are a lot of entries containing
"Project". Any hint which ones I have to delete and which ones I must not
delete?
Thanks, Philipp

Empty Project Work Area

Posted: 21 Oct 2005 11:44 AM PDT

No, I didn't uninstall first, just upgraded.

"Reid McTaggart" wrote:
 

Cannot get divided Work to reflect Assignment Unit percentage

Posted: 21 Oct 2005 08:06 AM PDT

Ah, I see... Thanks for your help.

"Jan De Messemaeker" wrote:
 

timesheet entry: current view displays all tasks

Posted: 21 Oct 2005 07:09 AM PDT

No...I do not have an administrative project set up...I should note that if I
use the custom filter on the 'current' view, the future tasks are excluded...

"Reid McTaggart" wrote:
 

How to get formulas and functions to work systematically

Posted: 21 Oct 2005 06:46 AM PDT

tools menu / options / calculation tab.
My point about current date is that it won't change until the next day. That
might not be noticeable.
Even so I'd stick to project status date if I were you.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Cynthis PMP" <microsoft.com> wrote in message
news:com... 
for 
you 
formula 
duration 
show it 
and 
complete. 
the 
fuctions 
Obviously, 


Export data to Excel

Posted: 21 Oct 2005 04:30 AM PDT

Thank you very much,

I am more than willing to pay. It is after all your time. And as they
say time is money.
I will contact you in due course. Thank you.

any way to highlight every other row in a project.

Posted: 20 Oct 2005 08:27 AM PDT

 

Chuck,
You're welcome.

To see all the options for the Font Method, open the VB Editor and hit
the "Object Browser"icon or select it from the View menu. When the
object browser appars, in the upper selection box on the far upper left,
select "MSProject". In the selection box immediately below it, type in
"font". Then hit the binocular icon. The Search Results will list
several "finds" with the first one already selected. Hit the question
mark (Help) icon. The complete VB syntax for the Font Method will appear.

Hope this helps.
John
Project MVP

why are tasks and work duplicated in task usage report?

Posted: 19 Oct 2005 02:46 PM PDT

Hi eng master,

Are the tasks duplicated on the Resource Usage view? Or the Task Usage view?
Or both?

If you are seeing duplicated task names (actually they are assignments) on
the Resource Usage view and there are multiple resources working on tasks,
this is expected. The assignment (represented by the name of the task
indented under the Resource's name) shows for each resource who is assigned
to the task.

Are you using a resource pool file for your resources? I have frequently
seen assignments repeated in the Resource Usage view when a resource pool
file is used and someone renames (through File > Save As) one of the
projects that is connected to the pool file. The resource pool file then
maintains the connection to *both* project files.

You may want to add the [Project] field to the task usage view to view the
name of the project that the duplicate tasks are coming from. Are they the
*exact* same project name?

Hope this helps. Let us know how you get along.
Julie