Pages

Search

Full Task Names in Rports Such as To-Do Lists Microsoft Project

Full Task Names in Rports Such as To-Do Lists Microsoft Project


Full Task Names in Rports Such as To-Do Lists

Posted: 04 Nov 2005 09:18 AM PST

Unfortunately the project plan is coming from our corporate headquarters and
our efforts to convince them to do what you've suggested has fallen on deaf
ears. Hence my desire to find a technical solution within Project.

"Paul" wrote:
 

Entreprise calendar

Posted: 04 Nov 2005 01:11 AM PST

Ok thanks

Peter

"Mike Glen" wrote:
 

Cost Loaded Schedule

Posted: 03 Nov 2005 06:09 PM PST

Hello Mike,

Thanks for responding.

Column 1 has no formula, I want it to accept my scheduled value for the task.

Column 2: I want it to accept a decimal number to represent the % complete.

Column 3: I used the buttons in the dialog box to enter: column 1 x coulmn
2. It looks like this: [scheduled value]*[ % complete]. Basically it is field
1 x field 2.

Column 4: I want it to accept a number for the previous month's billing for
that task.

Column 5 looks like this: [Total complete to date]-[previous application for
payment]

For clarification the items in [ ] are the field names. I used/renamed the
fields Number1,2,3,4,5 and added them to the standard Gantt Chart view. I put
in 25,000 in coulmn 1 and .35 in column 2 and nothing calculated in column 3.

Hope this helps you help me.

Thanks again.

Regards,

Bernie

Hope you can help.

"Mike Glen" wrote:
 

Custom Field Calculations

Posted: 03 Nov 2005 01:57 PM PST

I have emailed you a file containing the problem. Thanks for taking a look
at it.

Scott Hanebutt

"John" wrote:
 

MSProject Gantt timescale not saved

Posted: 03 Nov 2005 12:50 PM PST

Thank you - that is what is happening. It is an enterprise project stored in
Project Server 2003.


"Chris Marriott" wrote:
 

Calculating a per calendar week of usage cost for resources

Posted: 03 Nov 2005 10:29 AM PST

Hi Dan,

This sounds lie a job for vba. Try posting on the developer newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


poordan wrote: 



Recurring Tasks frequency

Posted: 03 Nov 2005 08:38 AM PST

In article <dkf5er$lhq$grnet.gr>,
intell1 <gr> wrote:
 

Nikolas,
Well, the simple answer is yes - lay in the tasks individually. But, I
don't think that's the answer you are looking for.

One of my suggestions was for a non-linked version. That meets your
request of "not (a) or (b)". Other than that however, I don't have any
further suggestions. Sometimes you just have to go with what is
available.

John
Project MVP

Hyperlinks on Project

Posted: 03 Nov 2005 07:58 AM PST

Thanks so much for the information! I shall try it out.
"Rod Gill" <rod AT project-systems DOT co DOT nz> wrote in message
news:phx.gbl... 


Need help with flags!

Posted: 03 Nov 2005 07:07 AM PST

It WILL NOT EVER work. Properties of a summary task are NOT automatically
applied to sub-tasks. Project doesn't work like that.
Further, the group summary is not really a summary task at all. It is just a
header in the display.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"New2Project" <microsoft.com> wrote in message
news:com... 
You 
consolidated 
would 
But for 
I'm 
this, 


Capacity of Project

Posted: 03 Nov 2005 05:14 AM PST

Thanks for the information.

"Jan De Messemaeker" wrote:
 

Display Duration in hours?

Posted: 03 Nov 2005 04:35 AM PST

You can change the settings fro the Options/Schedule section to display
future duratiosn in hrs. But the macro would be needed to convet any
previous durations in the form of days to hours.

"Martin Wilkinson" wrote:
 

Subprojects not rolling up (at all)

Posted: 03 Nov 2005 02:49 AM PST

In article <com>,
"Martin Wilkinson" <microsoft.com> wrote:
 


Martin,
My error, yes I did mean SR-1. Project 2003 identifies the first update
as SP1. However, when I ran my tests I was using Project 2000, just so
we would be looking at the same version.

Thanks for answering my questions directly. Unfortunately I find that
many people either don't answer at all or only give partial answers.

Your description of trying the Work field almost sounds like you are
looking at Baseline Work because that's exactly how it will act.
However, that idea doesn't apply for % Complete because there is no
baseline value for % Complete.

If you need to desensitize your file for sending, I can send you a
desensitize macro or you can find an equivalent version on fellow MVP,
Jack Dahlgren's webstie at: http://masamiki.com/project/macros.htm
Jack's macro is called "scrub". You shouldn't need the whole file
(although sometimes size DOES matter). As long as the problem still
shows up with just a single Summary Line and subtasks, that's all I need
for review.

John
Project MVP

Project Standard and Analysis Toolbar

Posted: 02 Nov 2005 01:59 PM PST

Hi Mike,

Thanks for your note. As noted (I believe) in my original request, I had
tried all of those suggestions, except I did not reinstall. I guess I wanted
to make sure that it was a feature of Project 2002 Standard Edition before
trying to reinstall it. Item 46 does not mention any different editions.

"Mike Glen" wrote:
 

Export to Access

Posted: 02 Nov 2005 01:17 PM PST

In article <com>,
"JAY-USC" <microsoft.com> wrote:
 

JAY,
Just an adjunct to what Gerard suggested. An export maps works fine for
static data but it will not work for timescaled data. For that there are
basically two choices - either use VBA or and SQL query directly on the
Project database. For information on the Project database structure,
search your hard drive for the following file (or something similar
depending on what version of Project you are using):
projdb.htm

Hope this helps.
John
Project MVP

Enterprise Customer Fields

Posted: 02 Nov 2005 12:37 PM PST

Hello Julie,
Try this one :
IIf([Baseline Finish]=ProjDateValue('NA');"No
Baseline";IIf(ProjDateDiff([Baseline Finish];[Finish])/480>=5;"Late by more
than 5 days";IIf(ProjDateDiff([Baseline Finish];[Finish])/480>0;"late";"On
schedule")))

It work for me.

Gérard Ducouret

"julie" <microsoft.com> a écrit dans le message de
news:com... 
2003 
doesn't 
returned 


Reminders in Outlook

Posted: 02 Nov 2005 08:28 AM PST

Hi Owl37,

Did you run the wgsetup.exe file? See help in MS Project for "Work group
messaging" and view information on setting up the email system for
collaboration with the team.

Hope this helps. Let us know how you get along.

Julie

"owl37" <microsoft.com> wrote in message
news:com... 


Help with creating a filter for Notes field - test/value to use to check for presence of content

Posted: 02 Nov 2005 04:08 AM PST

Sorry! I gave the answer fo ra formula and not a filter!
(Reading diagonally can seriously harm one's credibility)
Still, I now tried several things and I the use of a formula is the only way
I can find.
So it's a two-step exercice.
First, through Tools, Customize, Fields, customize a number field (f.i.
Number1)
with the formula:
Len([Notes])
Then make a filter for

Number1 does not equal 0

That does it.

Sorry for the misunderstanding.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"com" <com> schreef in bericht
news:googlegroups.com...