I'm using WBS predecessors but project won't let me type them. Microsoft Project |
- I'm using WBS predecessors but project won't let me type them.
- Conditional Predecessors
- Dumbing down MS Project
- Annual Rental Charges
- How do I get cells in Excel to link to cells in MSP?
- Sorting Resource Names in Task Views
- Task Name without Duration etc.
- 10/05/2005
- 2 items on one line
- Project file opens and immediately tries to implement a filter
I'm using WBS predecessors but project won't let me type them. Posted: 06 Oct 2005 02:43 PM PDT In article <phx.gbl>, "JulieS" <passport6847 at maine dot rr dot com> wrote: LMMBLS, It must have been earlier than anything publicly released for Project 2000 because Project 2000 acts the same way as current Project versions. Earlier versions of Project (i.e. Project 98 and earlier didn't even have a WBS Predecessor field). As Julie noted the WBS Predecessors and Successors fields are information fields (i.e. calculated by Project - not editable by the user). Are you sure you're not thinking of Unique ID Predecessors, because that field WILL accept user input. John Project MVP |
Posted: 06 Oct 2005 12:48 PM PDT Thanks, Jack! Exactly what I was looking for! "JackD" wrote: |
Posted: 06 Oct 2005 09:14 AM PDT Phillip Armitage wrote: www.kidasa.com maks a tool called Milestones that is basically a Gantt Charting tool that you might want to look at. -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Posted: 06 Oct 2005 08:04 AM PDT John, I was being dumb - I've now spotted how to assign resources to the summary task! Jerry "John" wrote: |
How do I get cells in Excel to link to cells in MSP? Posted: 06 Oct 2005 07:52 AM PDT In article <com>, "Janicek" <microsoft.com> wrote: Janicek, You're welcome, but I hope you read the thread I suggested. John |
Sorting Resource Names in Task Views Posted: 06 Oct 2005 07:48 AM PDT In article <com>, "Cory Levine" <microsoft.com> wrote: Cory, The only way I know for the option to be disabled is if the other option, namely "Sort resources by project", is unchecked. Try checking that box and then go for the re-numbering. Hope this helps. John Project MVP |
Task Name without Duration etc. Posted: 06 Oct 2005 03:51 AM PDT Or you could just hide the columns. Mike Glen Project MVP JulieS wrote: |
Posted: 05 Oct 2005 08:10 PM PDT That's a great answer and very helpful. Thanks! "John Sitka" wrote: |
Posted: 05 Oct 2005 05:00 PM PDT In article <com>, "Cowtoon" <microsoft.com> wrote: Diana, I agree with Mike on the idea of creating a custom view (although maybe you don't care if you modify the built-in version). I will however comment on your other post about hiding a column in Project. True, in Excel a column can be hidden by simple dragging its vertical bars together and then separating them again to show the column. Project does have this feature but when hiding a column in Project, the data is not "lost", it is temporarily not viewable until the column is added back to the view table. What cannot be hidden in Project are the task rows. Deleting a row in Project does in fact totally delete the information, unless of course "Edit Undo" is performed immediately afterward. With regard to your wish to combine closely related tasks, why not simply modify the task description to include both parts. Don't get to cryptic though or it won't be understandable by those who view the PowerPoint presentation. Another thought, if you are putting together a PowerPoint presentation you probably want a high level overview anyway. Go ahead and create the detail schedule (one task per line) but then include Summary Lines to capture the general idea of related groups of subtasks. When done, collapse the schedule by double clicking the little plus or minus box next to the Summary LInes. Then copy and paste the resulting overview schedule for PowerPoint. Hope this helps even more. John Project MVP |
Project file opens and immediately tries to implement a filter Posted: 05 Oct 2005 11:52 AM PDT Hi, Through View, More Views.. Edit look at the definition of the view that opens. It will havce a filter in it; replace that by All Tasks. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "wacNTN" <microsoft.com> schreef in bericht news:com... project |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |