Pages

Search

Creating a parent/child schedule Microsoft Project

Creating a parent/child schedule Microsoft Project


Creating a parent/child schedule

Posted: 30 Sep 2005 05:33 AM PDT

Thank you.

"Mike Glen" wrote:
 

Unable to import Project tasks from Outlook

Posted: 30 Sep 2005 03:45 AM PDT


You're welcome, Gisela :-)

Mike Glen
MS Project MVP


Gisela wrote: 



Repeating tasks....

Posted: 30 Sep 2005 02:47 AM PDT

OK Jan,

Thanks for taking time to reply back.

"Jan De Messemaeker" wrote:
 

How can I select and move or delete multiple tasks at once?

Posted: 29 Sep 2005 12:39 PM PDT


Hi Reba, you're welcome, :-),

If you are now using professional, next time you might consider posting on
the server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs,
companion products and other useful Project information can be seen at this
web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP

Reba wrote: 



Task as place holder - no date

Posted: 29 Sep 2005 12:05 PM PDT

Hi Jess,

Sorry no. Project is a scheduling tool and as such shows dates for all
tasks. A milestone task (0 duration) will show the same start and end
date/time, but non-the-less will still show a date.

If you want to just "hide" the date, you could change the font color to
white.

Perhaps if you tell us more about what you are trying to do, we can assist
further.

Hope this helps. Let us know how you get along.

Julie
"Jess" <microsoft.com> wrote in message
news:com... 


Number of Rows in Microsoft Project

Posted: 29 Sep 2005 07:51 AM PDT

In article <googlegroups.com>,
"davegb" <com> wrote:
 

Davegb,
First of all, if you have a project that has more than a few thousand
task lines (i.e. less than 20K), in my opinion you're already in
trouble. Nonetheless, the 1 million number comes right out of my Project
2000 manual (the value is also available directly in the help file but I
don't recall where to look). In the real world, is there really a
difference between 999,999 and 1 million?

John

Project should show resource "non-working time" in Resource Usage

Posted: 29 Sep 2005 05:21 AM PDT

Excellent stuff.
Thanks ever so much - Dank U wel!!

Douglas

"Jan De Messemaeker" wrote:
 

I want to display a task information field in a resource view...

Posted: 29 Sep 2005 04:11 AM PDT

OK, thanks anyways :-)

"Jan De Messemaeker" wrote:
 

Address book

Posted: 28 Sep 2005 09:30 PM PDT

Hello WSH
If i want to assign the resources by using address book it is
not connected to the outlook address book,this is my question.how do i
connect the address book.

"WSH" wrote:
 

please help with partial utilization

Posted: 28 Sep 2005 01:53 PM PDT

Oh, shoot....I see. THanks Julie.

How do I email master project with embedded projects?

Posted: 28 Sep 2005 01:18 PM PDT

Don,

I already knew about that option - but thanks for the reply nonetheless.
I think WSH's solution is more along the lines of what I was looking for
(although I haven't tried it out yet).

Thanks once again ... Steve

"DonL" wrote:
 

Action Items Management

Posted: 28 Sep 2005 10:27 AM PDT


Hi Luc,

Welcome to this Microsoft Project newsgroup :)

See Companion Products at this web address: http://project.mvps.org/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Luc Gestin wrote: