resource sheet - max unit column's and calculation of duration Microsoft Project |
- resource sheet - max unit column's and calculation of duration
- Critical path does not trace to beginning of project
- Summary Task Durations
- Pocket PC version of Project
- Export Time Phased Data
- Protecting the detail
- Error msg - overwrite default version of a project
- Adding an Enterprise Project Text Field to the Timesheet View
- resource availability conflict - Project doesn't show me!!!
- properly close ms project file opened by other user
- Can you disable row/ID numbers from printing on a Project Report?
- Adding an additional resource that is available after the task sta
resource sheet - max unit column's and calculation of duration Posted: 20 Jul 2005 12:18 AM PDT Thanks for the immediate answer and feedback. Yes agreed, it does change the max units for this resources assignment for all activities, but it would be of great help if you could confirm whether the change in max units will have impact on the finish date, since the duration is same , and percentage allocation varies., we feel the start and end dates shoud get re-calculated. example .... Activity - Design duration - 2 days with 100% allocation of 8 work hours start date - 20th July working day finish date - 22 July working day Resource assigement done Now changing the Max units for the resource to less than 100 units will it have impact on finish date ? in case u need any further details, we can provide the same for our understanding. Thanks and regards "Rod Gill" <rod AT project-systems DOT co DOT nz> wrote in message news:phx.gbl... the |
Critical path does not trace to beginning of project Posted: 19 Jul 2005 06:38 PM PDT Hi, When a task on the critical path gets a constraint, and hence is postponed, the preceeding tasks now have slack (since they can now be postponed) and thus are no longer critical. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "David" <microsoft.com> schreef in bericht news:com... this cases the back to |
Posted: 19 Jul 2005 11:30 AM PDT Try Tools/Options.../Schedule tab and Durations in entered in minutes. If you have small durations, this should show the Duration in minutes. if it stll zero, you have other problems. We need to discover whether your project is at fault, whether it is Project at fault, or whether it's your PC. Does the symptom occur with other projects on this PC? Does it occur with this project on other PCs? Does it occur with other projects on other PCs? Mike Glen MS Project MVP Mike wrote: |
Posted: 18 Jul 2005 03:03 PM PDT stupidquestion wrote: Not from MS but CyWren systems has some cool stuff. I have not tried anything from them in a very long time but I have heard good things. www.cywren.com -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com |
Posted: 18 Jul 2005 12:37 PM PDT In article <com>, Cheryl <microsoft.com> wrote: Cheryl, Sorry if this is duplicate post - I had a power outage last night and it messed up my clock. Unfortunately the "Analyze" utility exports data by assignment. Therefore, unassigned task data is not exported. There are two choices. The easiest is to temporarily assign a dummy resource to "unassigned" tasks and then use the utility, or use an advanced feature of Project, namely VBA, and create a custom macro to export the exact data you need. I prefer the latter because it gives me total flexibility, but then, not everybody knows how or wants to use VBA. Text fields are another matter. They are not timescaled so the utility will not work for them. Again you have two choices. One simple method is a cut and paste from Project to Excel. The second is to use an export map to export the static (i.e. non-timescaled) data from Project to Excel. Once in Excel the timescaled and static data can be combined as desired. Hope this helps. John Project MVP |
Posted: 18 Jul 2005 08:48 AM PDT Jon, There may be another way that you can also automate. Couple of questions first: Are you required to send them the gantt chart? Can you send only the task names and dates? Cheryl "Mike Glen" wrote: |
Error msg - overwrite default version of a project Posted: 18 Jul 2005 07:16 AM PDT Thanks Julie... I posted over there. "JulieS" wrote: |
Adding an Enterprise Project Text Field to the Timesheet View Posted: 18 Jul 2005 07:00 AM PDT its easy,, create that code and go to Tools> Customize and select Published Fields.. Found ur field in the list and say ok "JulieS" wrote: |
resource availability conflict - Project doesn't show me!!! Posted: 18 Jul 2005 01:58 AM PDT Thanks for your support. I guess a smart formula would do the trick, but that's too complex for me. I fully agree that Project should show a red flag in this case. Is there any way to ask Microsoft directly? Wim |
properly close ms project file opened by other user Posted: 15 Jul 2005 03:09 PM PDT No I don't I just store projects in sql database and use a ressource project CB "Gérard Ducouret" wrote: |
Can you disable row/ID numbers from printing on a Project Report? Posted: 15 Jul 2005 11:01 AM PDT I'm certain that you have good reasons for not printing ID's and row numbers, but having done this myself, let me explain what happened. This was a 600 task file that we mailed to suppliers [without ID's] and then over the phone, had many discussions about those tasks. Trying to find and discuss particular entries without a row number became almost impossible. Never did it again. "Will" <microsoft.com> wrote in message news:com... not this? |
Adding an additional resource that is available after the task sta Posted: 15 Jul 2005 09:12 AM PDT Hi Rickey, I think Gérard misses a step for you . From the Gantt Chart view, Window/Split will give you the Task form in the bottom pane. Right click in the pane and select Resource Schedule. Mike Glen Project MVP |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |