How do I get my project summary bar back after deleting it in erro Microsoft Project

How do I get my project summary bar back after deleting it in erro Microsoft Project


How do I get my project summary bar back after deleting it in erro

Posted: 22 Jul 2005 12:57 PM PDT


Hi Lois,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../View tab and at the bottom, tick the box for Show
Project Summary.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Lois07 wrote: 



Why is BCWP zero?

Posted: 22 Jul 2005 12:17 PM PDT

JackD wrote:
 

This would be a great utility for those that need to correct the rate for
resources.

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

vba datedifference type mismatch?

Posted: 22 Jul 2005 10:46 AM PDT

Hey

Jack, you seems to be the expert.

yeah i noticed that i missed the parantece. but its not that.

Sorry if ive explained the problem a little bit diffuse.
but its not a problem to get a object to a string. but the problem is to get
"activity.calendar" to be an object.

but it is possible to write Activity.Calendar in VBA?

if i dont get this to work , it is possible to send you a sample project
file. so that you can try it? just see if its just my computer or
something....

Thanks

- Bjorn








"JackD" <momokuri@gmail> skrev i melding
news:%phx.gbl... 


Removing tasks from a timesheet

Posted: 22 Jul 2005 07:52 AM PDT

Joe --

What you say is absolutely true. There is no default method in Project
Server to delete completed tasks for an individual project only. Thanks for
clarifying that for everyone! :)

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"Joe" <microsoft.com> wrote in message
news:com... 


filter blank lines in gantt chart

Posted: 22 Jul 2005 07:48 AM PDT



"Brian K - Project MVP" wrote: 

Thanks for that Brian, I can stop searching then. Will give your tip a try
and as it's the only solution it will have to do.

Viewer for Project?

Posted: 22 Jul 2005 07:47 AM PDT


You're welcome, Bill :-)

Mike Glen
MS Project MVP


Bill Starbuck wrote: 



Material Resource overload

Posted: 21 Jul 2005 02:21 PM PDT

How could you set a max even if Project allowed it? Material resources are
things that are incorporated into the deliverable or consumed during its
production. If I have a wall that will require 500 bricks I can't just
arbitrarily stop building when I've used 250. If I did the wall won't ever
be finished and the project will be deemed a failure. Project's tracking of
material resources is to insure you know how many to order so you will have
enough on hand to do the job required. Essentially you can't load based on
materials - if the budgeted allowance isn't sufficient to complete the
required deliverables you only have three options - buy more materials,
reduce the project scope, or abandon it altogether.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Hadi" <microsoft.com> wrote in message
news:com... 

Slip task

Posted: 21 Jul 2005 11:17 AM PDT

Reading your post a question came to mind - was any work performed on the
11th? The task was originally scheduled to start on the 11th. If work was
NOT performed on it, we don't have a task being interrupted, we have a
task's start being delayed which is not the same thing at all. A task is
interrupted if work starts and then stands-down for some reason. If work
was performed on the 11th, the day of work for the 11th is "used up" in the
overall task duration and the interruption begins with the first moment work
should have happened but didn't, which is to say, the morning of the 12th,
NOT the moment the work that was performed finished, the afternoon of the
11th. If we work 8-5, work was done the 11th from 8 to 5 and the
interruption begins 8am the morning of the 12th, not 5pm the afternoon of
the 11th because non-working time, the hours from 5pm->8am, is ignored by
the calendars and might as well not even exist as far as the project is
concerned. The easiest way to post this to your schedule would be to enter
any actual work for that task on the day(s) it took place and then with that
task selected, use from the menu Tools / Tracking / UpdateProject and with
the radio button for "Selected Tasks" in the dialog box selected, use the
"Reschedule Uncompleted Work to Begin After..." option.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sandieve" <microsoft.com> wrote in message
news:com... 

How to change pjDate_Www_dd ?

Posted: 21 Jul 2005 10:16 AM PDT

Well, it sounds strange, but the first date will be Dec 27'04, for 2005
calendar. This is, thas last week of Dec will be w1/1 ->w1/7. Part of the
problem could be that the last week of Dec is in MP, as of today, w53, and a
lot of companies only use 52 weeks for a calendar year. One of those
companies that use this format, that I know , is Intel

"Rod Gill" wrote:
 

How can I get the Adobe PDF Maker 7.0 toolbar into MS Project 03?

Posted: 21 Jul 2005 08:27 AM PDT

The PDF Maker toolbar for Project is a feature of Acrobat Professional only
and not available with Acrobat Standard.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"ClairNeedsHelp" <microsoft.com> wrote in message
news:com... 

Can I network 2 computers 1 with ME and one with XP?

Posted: 21 Jul 2005 08:06 AM PDT

In article <com>,
"ssmalley" <microsoft.com> wrote:
 

ssmalley,
This is a Microsoft Project newsgroup. I suggest you try a newsgroup
that deals with various operating system configurations.

John
Project MVP

Automatic Gannt Bar formatted based on the resource assigned?

Posted: 21 Jul 2005 07:01 AM PDT


Hi Tom,

Welcome to this Microsoft Project newsgroup :-)

You might like to see FAQ Item: 31. Customizing Task Bars.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP

tom s wrote: 



Resourcing will not feed through to pool

Posted: 21 Jul 2005 02:08 AM PDT



Rod Gill wrote: 

Rod, where were you when I needed you? Last year, I asked here if
anyone had experience with RP's going unstable, didn't get much in the
way of useful replies. You must have been on vacation! :)
Seriously, that's some good information. Thanks.

connect failed to project server from project profession

Posted: 20 Jul 2005 11:58 PM PDT


You're welcome, Randy :-)

I don't know how you got to this site, but you managed to post a quation
here. You get to the microsoft.public.project.server in exactly the same
way. I use Outlook Express for my newsreader, and it's just a matter of
adding the site to the account.

Mike Glen
MS Project MVP


Randy wrote: 



Create Project by Person

Posted: 20 Jul 2005 11:36 AM PDT

What will you do when two or more people are working together on a task?
The method you're thinking about is going to have multiple entries for the
same task, distorting the timeline of your work.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"microsoft.com" <please.reply@group> wrote in message
news:phx.gbl... 

Sending info to client without including cost data

Posted: 20 Jul 2005 11:20 AM PDT

Cindy wrote:
 

I would do a File Save As and make a copy of the current state of your
Project. I would then change the rates for everyone to $0 or $1 and then
do a Tools | Tracking | Clear Baseline and clear the baselines you might
have saved while the rate was higher. Then manually remove any values from
Fixed Cost fields.

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

MSProject crashes when monitor display settings change.

Posted: 20 Jul 2005 09:23 AM PDT

I found a previous posting on 4/20/05 that answers this question... at least
I think.
"Crash Loop with PowerPoint and Projector" 4/20/2005

"DEslinger" wrote:
 

HOW TO SAVE A IMAGE OF MS PROJECT AS SCREENSAVER

Posted: 20 Jul 2005 08:29 AM PDT

If you mean MS Project you can use Edit, Copy Picture, to make a .gif file.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"sumit" <microsoft.com> schreef in bericht
news:com... 
the 


MSP2003 - linking tasks using % complete to drive start date

Posted: 20 Jul 2005 08:07 AM PDT

Following other's suggestions, I prefer to show such situations as FS-25%.
Buty there's a consideration to keep in mind regardless of how you do it. A
link is a permissive control. It does not exist to force the schedule to
fit a particular timetable. When you have a predecessor linked FS to a
successor, it says that there is some physical reason that the predecessor
must complete before the precessor is even ABLE to start. Maybe the
predecessor produces some parts that the successor requires, for example.
Lead times like we're talking about modify that relationship slightly saying
that you can go ahead and start the successor when the predecessor has
produced enough parts to proceed even if it hasn't finished all of them that
it's going to produce. So when you enter the lead times as we've suggested,
make very very sure that it's physically possible for it to happen that way
and you're not just using the technique to force the schedule into what
you'd like it to be without regard to whether it's realistic to do it that
way or not.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"hostrows" <microsoft.com> wrote in message
news:com... 

Why doesn't my Office 2000 Professional have PROJECT on it?

Posted: 20 Jul 2005 07:51 AM PDT

Project is sold separately from Office Pro.
Visio is the same way.
They are in the office "family" but they aren't part of the "Office"
product.
If they weren't then microsoft would probably charge a fortune for Office.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
"Kate" <microsoft.com> wrote in message
news:com... 


Displaying Quarters

Posted: 20 Jul 2005 07:45 AM PDT

Philg wrote:
 

There is no such thing as Q0. There is Q1 and before that there is Q-1.
The project starts at a single point in time (by default on 8am on the day
you specify as the Project Start Date) The 'clock' for quarters, weeks,
etc starts there. This is the same idea that said that the millenium ended
on December 31st 1999 when really it ended at the end of 2000 since there
was no year 0. :-|

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com

MS Project gives gbui://blank.htm error. Registry patch not work

Posted: 20 Jul 2005 06:48 AM PDT

Jim:

See the following FAQ:
http://www.projectserverexperts.com/Shared%20Documents/gbuierror.htm

--


Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

For Project Server FAQs visit
http://www.projectserverexperts.com

For Project FAQs visit
http://www.mvps.org/project


"Jim Aksel" <microsoft.com> wrote in message
news:com... 


$1 cost rate

Posted: 20 Jul 2005 05:37 AM PDT

In article <com>,
Jan M. <microsoft.com> wrote:
 

Jan,
You're welcome.
John

I'm losing bar format colours when using Gantt Chart Wizard

Posted: 20 Jul 2005 03:50 AM PDT

Hi,

On your first question, the answer is yes. The reason lies in the answer to
your second question.
A view holds ALL the formatting items, generic (i.e. via Bar Styles) or
individual.

hth

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"jkn" <f9.co.uk> schreef in bericht
news:googlegroups.com... 
this a 
Bar'. 
Gantt