Duration changes with multiple resources Microsoft Project |
- Duration changes with multiple resources
- Duration and Resources
- print entire project on one page pdf format custom size
- how do i compare more than 3 baselines in project?
- Adding task witout adding any times!
- Ms Project Server - Scalability
- how i change in calendar view starting day as saturday?
- Formula for working days to or from
- project change my selected date for the next day!!!!
- Microsoft office project web access crash
Duration changes with multiple resources Posted: 01 Jun 2005 08:56 AM PDT In article <com>, "Doug" <microsoft.com> wrote: Doug, At first I didn't understand what you were asking but then the bulb went on. I was also confused when you said you were entering values for tasks/sub-tasks. In the normal definition the actual effort description is a sub-task under a Summary Line and Summary lines are not tasks, they are simply a summary of the sub-task information indentured under them. So in effect, neither Duration nor Work can be "entered" for Summary Lines, those values are calculated by Project. Now to answer the question. The Work on a Summary Line is the arithmetic sum of the Work for each sub-task under the summary. However, the Duration value shown on a Summary line is the difference in time between the Start of the earliest task (i.e. sub-task) and the Finish of the latest task under the Summary Line. Therefore depending on how the sub-tasks are linked (default is finish-to-start), the Summary Line Duration value can be less than, equal to, or greater than the Summary Line Work value. Hope this helps. John |
Posted: 01 Jun 2005 05:14 AM PDT Actually, I think I have sussed it by entering the duration, then fixed units and setting the percentages for each resource. Thanks for your inspiration, Gerard! "Barny Blue" wrote: |
print entire project on one page pdf format custom size Posted: 31 May 2005 03:55 PM PDT No one has answered the question yet. I've ran my own tests like printing a page through an actual printer and then using adobe. The preview of the print is truelly what you get. So if preview shows missing info, then don't bother creating the pdf. Also, I've tried to utilize forums at adobe's website, but in plain terms: their forums suck! Microsoft forums are the best in terms of responsiveness and usefulness. So, it's just a matter of time before we'll see a response to this post. "Paul" wrote: |
how do i compare more than 3 baselines in project? Posted: 31 May 2005 03:54 PM PDT We have a large staff that do work on multiple projects under one company. We are tracking the estimated loan funding time (original baseline) as compared to the actuall funding times (baselines 1-10). I need to see how accuarate we are in the big picture. "Steve House [Project MVP]" wrote: |
Adding task witout adding any times! Posted: 31 May 2005 08:35 AM PDT Your question shows you need to rethink how you're using Project as you are violating one of the most fundamental principals behind any scheduling software application. You should NOT ever be telling Project the dates the you're planning ANY of your tasks for - it's basic reason for living is to tell YOU the dates when you CAN schedule the tasks. You input the date you can start the first task, the estimated length of time you think it will take to do each one, the relationships between the tasks that are dictated by the process logic (ie, you can't put up the roof until you've built the walls to hold it), and when the required resources needed to do the tasks are available to work and and in exchange Project calculates the optimum schedule and outputs it for you. Yes, you can enter dates in the start and finish columns but that ability is there to allow you to handle the special circumstances where tasks need to have constraints applied and you should not be routinely supplying that information for any except the few circumstances where a constraint is required. And that is why you can't have a task shown as "TBA." You input the new task and Project figures out where it should be placed given the information it has about it so far and it is telling you when you should tentatively be planning to do it. As you supply more information, it refines that estimate until at last you have a workable schedule to communicate to the people who will do the work. In a nutshell, YOU don't plan the tasks - Project plans them for you! That's what you (or your employer) paid all that good money it costs to buy it to have it do for you. Let it do its job. -- Steve House [MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Mats Forslund" <Mats microsoft.com> wrote in message news:com... |
Ms Project Server - Scalability Posted: 31 May 2005 02:54 AM PDT Thank you. Will take a look. "Reid McTaggart" wrote: |
how i change in calendar view starting day as saturday? Posted: 30 May 2005 10:12 PM PDT Lina, I tested in Project Pro 2003 and it works fine... What is the version you are working with ? Gérard Ducouret "Lina" <microsoft.com> a écrit dans le message de news:com... saturday. |
Formula for working days to or from Posted: 30 May 2005 08:02 PM PDT Wow, nice. Thanks! bartmacl "JackD" <momokuri@gmail> wrote in message news:phx.gbl... |
project change my selected date for the next day!!!! Posted: 30 May 2005 06:01 PM PDT You can send me the file I shall have a look jandemesATprom-ade.be Greetings, -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "Jéjé" <com> schreef in bericht news:#$phx.gbl... |
Microsoft office project web access crash Posted: 30 May 2005 12:11 AM PDT "Chuck Zito" wrote: Yes. All the other options are working like documents etc. only when I choose projects the program go down. This workstation is the only one that have this problem. |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |