Pages

Search

Exporting Simple Gantt Diagram to HTML page Microsoft Project

Exporting Simple Gantt Diagram to HTML page Microsoft Project


Exporting Simple Gantt Diagram to HTML page

Posted: 01 Dec 2004 03:07 AM PST

Hi Barry,

Welcome to this Microsoft Project newsgroup :-)

Please see FAQ Item: 16. Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP



Barry McConnell wrote: 



How to enter duaration 4h and 32 min?

Posted: 01 Dec 2004 01:48 AM PST

In article <phx.gbl>,
"Mindaugas Bliûdþius" <lt> wrote:
 

Mindaugas,
Project will support either hours or minutes in time based fields but
not both. In other words, you will need to enter the duration in hours
and fractional hours or in minutes. To facilitate the conversion of all
Duration values to minutes you can run the built-in macro called "Format
Duration". Go to Tools/Macro/Macros and find "Format Duration" in the
selection list. Then hit "run".

You should be aware that Project calculates all time related data to the
nearest minute so even if a duration is entered as "hours" it is
actually treated as minutes. For example, internally Project stores 1
hour as 60 minutes. The setting suggested by Andrew in his response
applies only to the visual presentation in the view.

Hope this helps.
John

custom field formula question

Posted: 30 Nov 2004 05:43 PM PST

Hi Kris R.
See Jack Dahlgren's site:
http://masamiki.com/project/customfieldFAQ.htm

Hope this helps. Let us know how you get along.
Julie

"Kris R." wrote:
 

Finish-to-Start link not calculating new start time

Posted: 30 Nov 2004 02:55 PM PST

Steve, I read another discussion on this topic where you went through the
options settings, not having dates hardcoded, flexible contraints: and it
seems that I have done everything right, but still the tasks do not move, no
matter whether the update is automatic or manual and I hit F9.

"Steve House [MVP]" wrote:
 

Copy & pasting data into Excel from project 2000

Posted: 30 Nov 2004 02:05 PM PST

In article <com>,
Carmen <microsoft.com> wrote:
 

Carmen,
What type of data are you trying to copy and paste? If it is static data
(i.e. not timescaled from one of the Usage views), you can use the
export map method suggested by Andrew. However, if the data is
timescaled you should try using the "analyze timescaled data in Excel"
add-in/utility found on the Analysis toolbar. A third option is to
develop a VBA macro to export and format the exact data you need. In my
opinion, if you are dealing with timescaled values and need to do the
transfer on a regular basis, a macro is the way to go.

Hope this helps.
John
Project MVP

is there a way to limit outdenting task in project

Posted: 30 Nov 2004 10:39 AM PST

Are you asking if one can prevent selected users from outdenting or are you
saying one user has a problem outdenting while another user can do it ok?

--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Mark" <microsoft.com> wrote in message
news:com... 

Project Central 2000 Installation

Posted: 30 Nov 2004 10:33 AM PST

I actually went to that website but it doesn't address my problem. It seems
to only address when SQL is installed, not MSDE.

I will post on the server site. Thanks,

jeff

"Mike Glen" wrote:
 

archiving completed projects

Posted: 30 Nov 2004 10:23 AM PST

OK. Kim. Whne you click File/Open, the dialof opens in the directory where
the files are stored. This is controlled via Tools/Options.../Save tab/File
locations. So just move the file to a different directory or move it to a
CD.

Mike Glen
Project MVP

Kim wrote: 



PjSvrNPE Errors

Posted: 30 Nov 2004 09:31 AM PST

Hey Mike thanks for providing the faq link. I figured this posting was
better suited for the Pro_and _Server group but it had previously been posted
there with no response so I thought (hoped) that I might actually get a
response if I posted in the general section as well. Just trying to increase
my odds at finding some information as I have found NOTHING on the Microsoft
site regarding this error.


"Mike Glen" wrote:
 

Urgent Deadline Scheduling Problem

Posted: 30 Nov 2004 08:19 AM PST

This still did not solve the problem. Any other suggestions?

"Steve House [MVP]" wrote:
 

Columns..limit

Posted: 30 Nov 2004 07:45 AM PST

Hi Anna,

Welcome to this Microsoft Project newsgroup :-)

You can create a column for every field that you can insert via
Insert/Column/... click the dropdown arrow and browse through the fields
available. ( You can insert duplicates but this would seem pointless!)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :-))

Mike Glen
MS Project MVP



Anna wrote: 



Somebody please explain actual work to me....

Posted: 30 Nov 2004 07:17 AM PST

Hi ProjectNewbie,

Welcome to this Microsoft Project newsgroup :-)

I can't explain why Project does what it does, but you are assuming a lot!
Firstly, work is done by resources and thus to enter manhours of work
without the man does not make any sense. Equally, entering actual work
without a worker doesn't make sense. Finally, as you have an 8-hour day,
trying to force Project to squeeze 9 hours into 8 hours makes even less
sense. I doubt whether the developers even considered anyone entering such
fallicies :) No, please use Project in the way it was designed and then
post your problems. If you don't know how to enter the details, I strongly
suggest you attend a 2 or 3 day course to get an good inroduction to how it
works. At least have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP



FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :-))

Mike Glen
MS Project MVP



Joe wrote: 



Urgent Circular References

Posted: 30 Nov 2004 06:37 AM PST


Andrew,
I'm not sure what a "bugbear" is but I will assume it is something to
avoid. Actually, MSP does not behave in random fashion. One problem we
humans have with computers is that they tend to behave in exact ways
based on a strict set of rules and that of course is counter to the way
we think (i.e. we are more adaptable and assume a lot of things true or
not). You are correct though that a large plan will likely have many
linkages which can be difficult to manage. Such a plan requires care and
feeding by its human caretaker.

John

basline and earned value analysis

Posted: 30 Nov 2004 06:21 AM PST

Is it really an issue? You would understand that if you have changed your
plan, you can no longer make a meaningful comparison against the original
plan.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
"Tom" <microsoft.com> wrote in message
news:com... 
and 
as 
several 
to 
Of 


Outline text in text fields

Posted: 29 Nov 2004 11:41 PM PST

They don't look here!

Mike Glen
Project MVP

Andrei wrote: 



Task Start Date

Posted: 29 Nov 2004 07:55 AM PST

Not true - ASAP means as soone as possible after the project start date, not
the current date. The default placement of tasks to either the project
start date or the current date only applies to the date it will be scheduled
to start when it is first entered into the plan. Once it's there that
setting has no effect and tasks won't be rescheduled simply by opening the
file on a later date.

--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"russellmcox" <microsoft.com> wrote in message
news:com... 
.......snip......... 

Connection to project server failed

Posted: 29 Nov 2004 07:41 AM PST

Hi,

Following from this we tried installing the latest version of MDAC (2.8)
however this has similarly caused a connection failure ---

Connection Failed:
SQL State '28000'
SQL Server Error 18456
[Microsoft][ODBC SQL Driver][SQL Server]Login Failed for user
"MSPojectUser1395"

We want to try the earlier version of MDAC (2.7 SP1) however I cannot find
any unistall utility for MDAC and trying to install the old version doesnt
work.

Does anyone know of an uninstall utility for MDAC??

Cheers for any help

Lee


"Lee Newson" <com> wrote in message
news:phx.gbl... 


Why would my trial version expire in 3 days??

Posted: 29 Nov 2004 05:33 AM PST

When you edit the value and exit regedit the change is automatically saved.
Don't know what else to tell you as that's the only info I have.

S
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Bsymes" <microsoft.com> wrote in message
news:com...