Notes Tab Microsoft Project |
- Notes Tab
- adjusting the row hight
- Resource only available % of time
- "Advanced" project course?????
- Predessor occurs after task
- wrong start date shown
- how to require resources to work on assignment at same time?
- Coding iterations
- Start 10 days After
- scheduling query - task with ff dependency starting too late
- Project 2003 - Can a default be set to start each task at 8:00 AM
- Sharing Microsoft Projects
- Start-to-Finish dependancy looks odd in Gantt Chart
- Data Access 2003 PJDB.htm
- incorrect value in summary tasks for the baseline cost fields.
- Having to access the Web for help with MS Project is a pain and a.
Posted: 24 Sep 2004 09:02 AM PDT Hello Una, Have you tried the "Task Note" button in the tool bar (small yellow label) ? Gérard Ducouret [Project MVP] "Una" <microsoft.com> a écrit dans le message de news:com... help |
Posted: 24 Sep 2004 08:32 AM PDT Hi John, I have 40 tasks that I want to be printed in one page. Obviousely I can adjust the page in page set up section but It was easire to have the row hight to be adjusted lower. Regards, Majid less than 1? sure the Gantt less space, sometimes the Gantt |
Resource only available % of time Posted: 24 Sep 2004 07:14 AM PDT Thanks for the help. Unfortunately, I still can't get it to work. I've created a Test resouce, let it at 100%, changed the calendar to only be 8-12. I created a Task, set the Work hours to 16 (so it will take Test 4 days to complete the task), entered Test as my resouce and now the Resource column shows Test[200%] and the Start/Finish dates cover two days. So, I'm still stuck! working 1/2 the time assign them to a however the duration show the work over 4 saying to Project effort - ie only do 1 message their can I |
"Advanced" project course????? Posted: 24 Sep 2004 06:51 AM PDT Hi Agnus, On my website is a rather comprehensive paragraph list of the courses I give; compare it to what people have seen as "basic". HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Angus Duncan" <com> schreef in bericht news:phx.gbl... of |
Posted: 24 Sep 2004 02:41 AM PDT You are reversing yourself. You first said the successor is coming before the predecessor, in this message you said "the predecessor comes before the task" which seems to say the task in question comes after the predecessor. Which is it? In a Finish-to-Start link, the predecessor normally does finish before the successor starts, unless there is a lead time in the link or a constraint on the successor that overrides the normal behavior. This all assumes you are scheduling from start date forward. A lot changes when you schedule from finish date backwards and such scheduling is rarely a good idea even if you have very strong deadlines. You didn't mention which you are doing. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Paul Moloney" <com> wrote in message news:phx.gbl... |
Posted: 23 Sep 2004 11:35 PM PDT Does it have an Actual Start date? -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "ngs1" <microsoft.com> schreef in bericht news:com... for usage blank The the |
how to require resources to work on assignment at same time? Posted: 23 Sep 2004 11:29 PM PDT Who knows? I'we listed and supported it as much as I could.. "When a pilot is on holiday, the plane does the flying by itself and the pilot performs his part of the work when he comes back" -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "JulieD" <net.au> schreef in bericht news:phx.gbl... that want the the |
Posted: 23 Sep 2004 06:23 PM PDT The *same* task cannot take part in multiple iterations. *Similar* tasks might occur, but a task is a block of work taking place between time A and time B. It requires both the type of work and the start and end time frame to define a task. A repetition, with the same sort of work taking place between time C and time D, a different time frame, is actually a different task even though it may have the same name. After all, if I have to repeat the widget waxing I could put substitute a new resource for the second round. Since the purpose of the plan is to produce a schedule, every iteration of the tasks must appear individually at the time frame where they will be scheduled to occur. Otherwise, you have no way to advise the resources when they will be expected to engage in that particular activity. This means you really can't put in an iteration as a task with a counter because that will appear in the schedule at only one spot rather than recurring for each iteration. The best way might be to make a best-guess, worst-case scenario of the number of interations likely and enter them all in the plan. Then when you get closer to the events you can refine your estimate and add or remove iterations as needed. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Juan Roman Escamilla" <microsoft.com> wrote in message news:com... |
Posted: 23 Sep 2004 04:44 PM PDT Hi Josh (and the rest of the gang) Perhaps we are applying too narrow an interpretation on Josh's question. I'll be making a bit of an assumption, but here goes: T2 earliest start is March 1st OR 10 days after the finish of T1 - whichever is the later. If this is correct, then it can be programmed by applying the contraint of FNLT of Feb 15th on T1. Then on T2 you'd apply the constraint of SNET March 1st, complete with the T1+10 days predecessor. If T1 is scheduled to finish earlier than 10 days before the March 1st, and your T1 duration extends, Project will extend the bar length up until the end the specified FNLT date. If T1 duration continues to extend, then the bar length wil begin to start the task earlier, as per requirements. If T1 is driven by a predecessor, say T-1, and Rescheduling Uncompleted Work drives the task durations into conflict, you will then get the warning message. Moreover, if progress has started on T1, and you have to Reschedule Uncompleted Work or amend the duration of T1 such that the end-date of T1 goes beyond the FNLT date, you will be given a warning....thereby having T1 drive out the start date of T2. Overall, it seems to work reasonably well...but like anything else, you have to keep an eye on it. To make monitoring it a little easier, I inserted a Deadline arrow on T2. If I've got this all wrong, please beat me with a spiked club. James.G "Sascha Wald" wrote: |
scheduling query - task with ff dependency starting too late Posted: 23 Sep 2004 02:13 PM PDT Hi Jan, Thanks for your advice, I reached the same conclusion myself and have successfully scheduled this now by splitting the task into 2. "Jan De Messemaeker" wrote: |
Project 2003 - Can a default be set to start each task at 8:00 AM Posted: 23 Sep 2004 12:21 PM PDT Hi i've used a little "trick" occassionally in a project to force a task to move to a certain time, but i don't know how to do it for every task. What i've done is create a new calendar that has a working time of 1minute (8am to 8.01 am) then when i've had to "force" a task to move say to the next morning i've added a task (Task A) between this task (Task 2) and it's predecessor (Task 1) with the duration of 1 minute and then assigned the calendar to it .. this makes the TaskA go to 8am on the next day and then Task 2 follows it. - you can then change row height & format the row so it can't been seen when printing - but as i said, it wouldn't be a solution if you had to do it for every task in the project Cheers JulieD "Dick4b" <microsoft.com> wrote in message news:com... the the the 5:00 at a be |
Posted: 23 Sep 2004 10:15 AM PDT Hi, If your users only need to VIEW the information, try saving your plan as an HTML and placing in a public folder (email it). Hope this helps. Ybriggs "Topio" <microsoft.com> wrote in message news:com... project users only |
Start-to-Finish dependancy looks odd in Gantt Chart Posted: 23 Sep 2004 09:32 AM PDT Hi Steve, Thanks for your assistance. You'll need 3 tasks to test this (I think). Task 1 and Task 2 are normal Finish-to-Start dependancy. Task 1 needs a duration longer than the "tuesday" task (Task 3), I set it to 10 days (while Task 3 will be 1 day). Task 2 then has a Start-to-Finish dependancy with Task 3. You should see the abnormal behavior with this setup. Task 3 appears to stretch out over multiple days, even though it has only 1 day duration. Oh and I am setting up a special "tuesday" calendar that Task 3 uses (Tools->Change Working Times->New. Then just assign the calendar to Task 3). After reading your explanation I think you may be seeing the long bar as well ("The bar is there over Wed and Thur just like it flows over the weekend for a 2 week task but the task is a 1 day duration task"). I do not want the bar, I want an arrow (1 day bar, several days arrow going to the next task). If you do the same thing with all Finish-to-Start dependancies the 1 day task bar never stretches over 1 day, even if the next task doesn't start for several days afterwords. If you want an explanation as to why I need my project set up like this: We have a project with several Phases (6 to be exact), each with a main Construction Task. The Construction tasks need to happen one right after the next (standard Finish-to-Start dependancies). However, before each Construction phase, the phase must be approved in a commision meeting (which only takes place on tuesdays). This meeting needs to happen just soon enough that the Construction phase will be able to start immediately after the previous construction phase ends. I want the project Gantt Chart to accurately show that this task only occurs on a Tuesday and is complete on that day, but I want the dependancies so that it moves if Construction phases finish early or late. Hope that explains my problem better. Ryan "Steve House [MVP]" <send.hotmail.com> wrote in message news:eWW0$phx.gbl... any is occur place? Tues 1 once draws For take |
Posted: 23 Sep 2004 08:04 AM PDT Yes 2003 version.... but like you say stay calm, read, read and reread the PJDB.htm. "Rob Schneider" <net.net> wrote in message news:phx.gbl... |
incorrect value in summary tasks for the baseline cost fields. Posted: 22 Sep 2004 11:57 PM PDT Hello, I think it's the normal behavior of a baselined data : The summary was baselined at $10000 for instance with 3 children tasks. You delete a children task which was baselined at $2000. The summary baseline stays at $10000 but Project displays a Variance of - 2000 . Anyway, you can baseline the project a second time and clear the variance. Gérard Ducouret [Project MVP] "Rob Schneider" <net.net> a écrit dans le message de news:uSS$phx.gbl... |
Having to access the Web for help with MS Project is a pain and a. Posted: 22 Sep 2004 04:02 PM PDT Hi aggravated, You can ask Project (and other Office 2003) products to search the local help files first instead of going out to the web. Go to help menu and choose "Microsoft Project Help." In the Project Help task pane, click the "Online Content Settings..." hyperlink. Remove the check from "Search online content when connected." You will still have the option of searching online if you don't find the answer you need searching the local help files. Hope this helps. Julie other applications) is the help files with updates to the local |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |