how do I add numbers from two different columns? Microsoft Project |
- how do I add numbers from two different columns?
- Finish Variance
- Is there a master calander for ALL projects?
- How can I apply a project plan shell or template to another, exis.
- Duration does not properly add
- Changing Dur creates a Schedule Conflict?
- Does MS Project allow routing for approval to department heads?
- Any way to reflect teams in Project?
- How to show Activity on Arc Network Diagram?
- tasks report
- MS Project/Project Server
- Pesky Approvals!!!
- Setting resource %
- using projects over
how do I add numbers from two different columns? Posted: 04 Oct 2004 12:25 PM PDT Ben, All you need to do is set up a custom field with a formula that add the two other fields (columns). Go to Tools/Customize/Fields and, depending on what type of data you are using (i.e. cost, duration, number, etc.) pick a spare field (e.g. Number1 if the columns to be added are integer or floating point values) and hit the "formula" button on the Customize Fields windows. Then just set up the formula you want. For example, Number1 = [Number2] + [Number3]. Note that the formula will apply to all task rows, not just a single task and you will need to select the appropriate roll up formula for Summary rows on the Customize Fields window. Hope this helps. John |
Posted: 04 Oct 2004 09:47 AM PDT As Jan said, or phrased another way, to see how you did compared to how your originally thought you were going to do. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Hallie Kay" <microsoft.com> wrote in message news:com... |
Is there a master calander for ALL projects? Posted: 04 Oct 2004 09:12 AM PDT You have a couple of choices. You can set up an Enterprise Global calendar in Project Server if you are using that and want your celndar to be avaiable to all the PMs developing projects, or, if you're not yet using server, create a calendar (I'd suggest using a copy of the Standard calendar so you retain the master, although you could edit the Standard if you wish) in the current project file, could even be a blank project, that shows all the holidays etc for a convenient time period. Then, use the Organizer on the Tools menu to copy the customized calendar in the working project file back into the Global.MPT template to make it available to all other projects. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jason" <com> wrote in message news:%phx.gbl... |
How can I apply a project plan shell or template to another, exis. Posted: 04 Oct 2004 08:57 AM PDT Hi Jan, All settings. I want to "apply" the template with all calculations such as Earned Value (we use some customer calcs and views) and custom views to an existing workplan and resource pool. In my scenario, someone has created a work plan without the custom settings and views. I would like to apply all custom calcs and views to another workplan. "Jan De Messemaeker" wrote: |
Duration does not properly add Posted: 04 Oct 2004 05:39 AM PDT Durations are not additive. The duration of Testing will be the time between when the earliest PreTest starts and the latest PreTest ends. It will be 30 days ONLY if the subtasks occur in sequence with no overlaps or gaps. Also check in the Tools Options Calcualtion page to make sure it's set to Automatic - from your message, Testing should be 10 days, not 5. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "jzis" <microsoft.com> wrote in message news:com... |
Changing Dur creates a Schedule Conflict? Posted: 04 Oct 2004 05:27 AM PDT Posted a partial message somehow - sorry. Could you have any actuals posted to any of the tasks that are scheduled later than the task you're trying to change? Once an actual is entered that fixes the task to the dates where it is posted as having taken place. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Coop" <microsoft.com> wrote in message news:com... |
Does MS Project allow routing for approval to department heads? Posted: 03 Oct 2004 11:23 PM PDT You're welcome, Terecy:-) Mike Glen MS Project MVP Terecy Joyce Chia wrote: |
Any way to reflect teams in Project? Posted: 03 Oct 2004 10:34 AM PDT I suppose you could set up two resources to indicate the same individual, then put him in 2 different teams. i.e. Bill-Design and Bill-Process Engineering Reporting would be odd - could I view a consolidated cost report on Bill as a whole? |
How to show Activity on Arc Network Diagram? Posted: 02 Oct 2004 08:44 PM PDT Don't know about other products but this is not a feature of MS Project. Activity on Arrow diagramming is falling into disuse these days anyway. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Katie" <microsoft.com> wrote in message news:37a401c4a8fb$4c3a8de0$gbl... |
Posted: 02 Oct 2004 01:07 AM PDT Hi, Auto Filter, filter Name on contains "Excavation" (ore whichever) -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "raduga_fb" <microsoft.com> schreef in bericht news:com... specified to tasks be |
Posted: 01 Oct 2004 01:13 PM PDT Thank you for your time and assistance, gentlemen. E |
Posted: 01 Oct 2004 10:10 AM PDT Allen -- There is no default method within Project Server to automatic the processing of task updates into each project plan. The closest that you can come to automation is for each project manager to create one or more Rules in Project Web Access, but the PM must still click the Run Rules Now button to process the updates. Hope this helps. -- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Allen" <com> wrote in message news:google.com... |
Posted: 01 Oct 2004 06:42 AM PDT Adding a bit to Julie's excellent answer ... I'm a believer that the resource's calendar should reflect the hours that they are "on the property" as they used to call it in the old railroad days, i.e., physically present. So a full-time employee would have an 8 hour a day calendar, assuming typical working conditions. A part-time working 4 hours per day would have a calendar reflecting a 4-hour workday, etc. If a full timer was only available to the project 4 hours a day, their calendar would still show 8 hours but their maximum availability would be 50%. This shows that in each workday they will accomplish up to a maximum of 4 man-hours work on my project but I'm going to let them organize their own workday and decide for themselves which hours during the day they're going to do project stuff and which hours will be spent on other things. Also note, Project will never change the duration estimate for a task with the first resource assignment, regardless of the percentage you specify. It assumes that whatever percentage you say the resource will be working at, that was what you had in mind when you came up with the initial duration estimate. So a 4-day task will stay at 4 days whether you assign the resource to it 100%, 50%, 25%, or what have you. At that first assignment the work is calculated. If you then *modify* the assignment later, the duration, work, or effort will get recalculated based on the task type settings. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Pam" <microsoft.com> wrote in message news:2d7c01c4a7bc$741a56f0$gbl... |
Posted: 30 Sep 2004 11:39 AM PDT THanks Jan, The gretat majority of task dates were adjusted; a minority were not. I will do more testing to see if I can discover why. "Jan De Messemaeker" wrote: |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |