How do I change the duration from hours to days Microsoft Project |
- How do I change the duration from hours to days
- replacing resources across multiple tasks and projects
- Duration and finish date
- Filtering for Critical Path of Specific Task
- Over-allocation indicator - for specific task duration.
- The 60 day trial period ended after 2 hours of use!
- Linking multiple projects
- Copy Picture does not include Legend
- Date Range Filter
- Timescale Macro
- Prj2002: Project more that 20yrs old?
- Calendar and Change Working Time (Use default)
- Out of hours start and finish
How do I change the duration from hours to days Posted: 10 Aug 2004 11:07 AM PDT That macro does not appear in the drop down list. Do you know if I can download it somewhere? Thanks for your response. "JulieS" wrote: |
replacing resources across multiple tasks and projects Posted: 10 Aug 2004 10:12 AM PDT This is one excellent use of the Resource Assignment box. On the standard toolbar is a tool with 2 human heads on it. Click on that, and the Resource Assignment box appears. Select all tasks with the resource you want to replace assigned to them (if there are a lot, apply the "using resource" filer). Select as many of these as you can (this will be limited by available memory, so closing other apps may help do more at once). Select the resource's name in the Resource Assignment box, the click on the "Replace" button. A dialog box will appear, with the same list of resources you just had in the Resource Assignment box. Select the resource you want to replace the other with. Click OK. One of the nice parts of using this method is that any partial assignments on the original resource will be replicated for the replacement resource. Best of luck. David G. Bellamy Bellamy Consulting "Greg" <microsoft.com> wrote in message news:<387101c47efd$317dcc10$gbl>... |
Posted: 10 Aug 2004 08:43 AM PDT Also, in addition to the other comments, you need to reflect that the 20 hours was obtained from 16 hours regular work and 4 hours overtime work. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Muks" <microsoft.com> wrote in message news:com... resource which to |
Filtering for Critical Path of Specific Task Posted: 10 Aug 2004 08:20 AM PDT You have several problems. A major one, IMHO, is your use of Must Finish On constraints for your key deliverables. A constraint in the scheduling engine is not the same thing as a constraint in the world of your project. You are using Must Finish On to mean "this is when we have to have this done by or we are in deep trouble" but that's NOT what a constraint means in Project. To Project, a "constraint" means that this task will ALWAYS be shown happening per the constraint, even if it is physically impossible for it do do so according to the durations and links of the preceeding tasks. Consider task A and B, each 5 days duration, starting next Monday. That task sequence will finish 10 days later. They lead to a finish milestone. Simple FS links A->b->Finish. If I put a MFO constraint on the milestone of 1 September, indicating that's when the contract says we have to finish, guess what Project shows? It shows task A running from 16 Aug to 20 Aug, task B from 23 Aug to 27 Aug and then a gap until the milestone occurs, scheduled on 01 Sep. But when did the milestone REALLY occur? 27 Aug! Using the constraint caused the milestone to be shown occuring at a date that is patently in error. So we take another tack. Let's put a Must Finish No Later Than constraint of 01 Sep on it instead. Now Project shows the milestone occuring 27 Aug, the correct date. But we still have a problem. We blew it and task B was grossly under-estimated and actually takes 10 days instead of 5. Now task B finishes on 03 Sep. But wait, looking at our milestone it shows finishing the project 01 Sep, right on schedule!!!!! Again, obviously an error - we CAN'T be finishing on time because the predecessor that MUST be finished for us to really be done with all the work actually isn't finished until 2 days later! A second problem is the use of the term "critical path." It seems like you are using the term to mean "the important task sequence for producing a deliverable." But that's not it. As Project (and CPM in general) uses the term, the critical path is the sequence of events that determines the overall duration of the entire project. There is no such thing as a "critical path to a deliverable" unless that particular deliverable just happens to lie on the critical path of events to the end of the project. There may be lots of deliverables in a project whose delay to some extent would not result in a delay of the overall completion of the project and by definition they are not critical. For instance, I have an application development project that requires 1 month design, 4 months programming and testing, and 1 month rollout. I can write the user's manual any time after design is done because at that point the functionality is locked down and the programmers write to the design specs. Training is a part of rollout and I won't actually use the user's manual until we begin training. Writing the manual is not a critical task or deliverable, even though it's really really really important, unless it's delayed into the 6th month and the delay causes training and thus completion of rollout to be delayed,. It is not a critical deliverable, does not lie on the critical path, and there is no critical path leading up to it UNLESS it gets delayed more than 4 months from when it could have been started. At that point, its schedule becomes the determining factor in the date of the conclusion of all the project work and so it becomes critical and the critical path shifts to include the sequence leading to and from it. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jeff" <microsoft.com> wrote in message news:371901c47eed$896a23c0$gbl... |
Over-allocation indicator - for specific task duration. Posted: 09 Aug 2004 11:31 PM PDT Hi Steve and thanks for response! There is no importance which task was 'first' - if there is an over-allocation on specific day - all tasks that take place in that place are 'suspicious' - and I want them to be marked (by the indicator field for example). My problem is to recognize onle these tasks that 'involved' in the over-allocation. "Steve House" wrote: |
The 60 day trial period ended after 2 hours of use! Posted: 09 Aug 2004 01:02 PM PDT Could be either of a couple of things Here is the first: http://support.microsoft.com/default.aspx?scid=http://support.microsoft.com:80/support/kb/articles/q285/3/43.asp&NoWebContent=1 If you haven't installed previous versions as described above, then sometimes the trail version has a hardcoded expiration date (this might happen if you are installing off a cd). Try http://www.microsoft.com/office/project/prodinfo/trial.mspx to see if that will work for you. -Jack "johnnycrash" <microsoft.com> wrote in message news:2f3f01c47e85$4fa8cff0$gbl... |
Posted: 09 Aug 2004 07:25 AM PDT Jenn, Wow, at first I though that answer might be too obvious but it just shows to go ya. John P.S. You're welcome |
Copy Picture does not include Legend Posted: 09 Aug 2004 06:02 AM PDT Hi, I use those Print Screen shots in my courses (PPT) -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "jimcal" <microsoft.com> wrote in message news:28fb01c47e26$a8c8b780$gbl... |
Posted: 08 Aug 2004 07:31 PM PDT Thanks for that Steve, using custom auto filters has opened up a pile of possibilities for me. "Steve House" wrote: |
Posted: 08 Aug 2004 07:07 PM PDT I'd simply assign a cost of $1 for each hour of work, then use BCWS -Jack "gbeav" <rr.com> wrote in message news:234601c47db5$9628b7e0$gbl... |
Prj2002: Project more that 20yrs old? Posted: 07 Aug 2004 08:29 PM PDT I did a similar timeline, but I used Excel, partly because of the reason you encountered. "Mike" <reidrik_von(AT)hotmail.com> wrote in message news:<phx.gbl>... |
Calendar and Change Working Time (Use default) Posted: 07 Aug 2004 10:15 AM PDT Use set the "default" start and end times on the Tools, Options, Calendar page. Those defaults do NOT change anything in the working times calendar or modify its defaults. In fact, nothing on that entire page has any effect on the working time calendar at all, contrary to what the names of the fields appear to indicate. Here's what it does do. First of all, make note that ALL date fields are actually date/time fields. You may choose whether to display the times or not but they're always going to be there. When you enter a task name and duration, normally Project calculates its start and end date/time for you based on the Project calendar, predecessor relationships, and resource availability. But you may, for some particular reason, wish to set a constraint on the task and one easy way to do it is to over-ride the calculated start or end date with your own entry (and that's the only time you should EVER enter something in those two columns). If you enter something in the Start field, Project sets a Start No Earlier Than constraint of the date you entered. But it also needs to know what time to include in that entry as well. If you click in the Start field and select a date from the little popup calendar, it uses your Project Calendar's working hours to determine what time on the selected date to use. But if you manually type in the date without explicitly including a time in your entry, it uses whatever you've set as the "Default Start Time" on the calendar options page. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Regis" <microsoft.com> wrote in message news:com... when time. |
Posted: 06 Aug 2004 09:59 PM PDT You are very welcome Maureen. It is a puzzler about the resource calendar though. Glad to have helped. Julie assigning what's re- of |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |