Critical Path of the large complex project file Microsoft Project |
- Critical Path of the large complex project file
- MS-Project 2000 error in date for september month
- unlink calendar from estimated hours?
- Cost vs. client rates
- Renamed and relinked file shows old name
- open pre 1998 project files
- More Questions
- Resource Over Allocation
- Date format in Header
- Resource cost clarification
- Changing work
- setting task starting time by hour?
- Project Hangs
Critical Path of the large complex project file Posted: 07 Aug 2004 01:32 AM PDT It is too large and complex to do what ???? 50 Resources and an estimated duration of 1 year is not an unusually large or complex project by any means. The general process would be to outline the major phases or deliverables to be created in the project and break them down further and further until you get to the level of the individual activities or work packages that describes a specific piece of work that must be done. If the project was to erect an office building, for example, you would detail it down to where an individual task might be "paint room 103." Try to keep focussed on the specific actions that the resource will do. I suggest starting each task name will and action verb - build, dig, polish, write, test - to help you keep focussed on the notion that the tasks all are individual pieces of work done by 1 resource or resource team working as a unit. To create the deppendencies, once you have outlined the tasks and estimated he duration of each one, look at how physical product or information flows throught the project. If a task needs the output of a previous task in order to proceed - we can't test a prototype until we've built the prototype and we can't build it until we design it, for example, that describes the predecessor/successor links. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "neverland" <microsoft.com> wrote in message news:1bf501c47c59$0c176590$gbl... |
MS-Project 2000 error in date for september month Posted: 06 Aug 2004 12:42 PM PDT Hi Regis are you looking at the calendar in tools / change working time or in the gantt chart timescale or ??? Cheers JulieD "Regis" <microsoft.com> wrote in message news:com... |
unlink calendar from estimated hours? Posted: 06 Aug 2004 07:58 AM PDT Ooops. Resource units are calculated to 33% sorry. Julie end and I has |
Posted: 06 Aug 2004 06:20 AM PDT We have developed a billing rates feature that plugs into project and it works very well to accomplish exactly what we want project for: to provide enterprise project management. We build each project estimate in our system. Each estimate tells us how much our cost is, and how much we will bill the client for each resource on each task. And the data is timephased. The trouble with using the cost tables A-E is that you cannot simultaneously do math against the calculated values resulting from each table. You can't portray both values in the same report and do math on them simultaneously. Well, you can, but takes programming. As for G&A, as Steve suggests, that is accounting system data and we do not contain that data in my EPM system. However, because we have time-phase cost AND time-phased billing for each project in the enterprise, my data is that half of the company financial Proforma that provides us with the view of exactly how much gross margin is in the future months and then the accountant applies the G&A section of the data. Together we get very accurate (generally less than 5% margin of error) profit/loss projections that go to the banks and help us to plan for company cash flow. It works very well. Send me an email if I can help you. Matt multiple projects and all 20 of them) standard rate (or At the end of the (by project or by each. I am trying the 'Enterprise resource pool' table rates A-E, but I resource could be on compare the base |
Renamed and relinked file shows old name Posted: 06 Aug 2004 05:53 AM PDT The name of a project is confusing, all right. There's the filename and then there's the Project name from the properties dialog box in the file menu. When you insert a project into a master file or see it referred to in the task list on the consolidation that MSP builds for resource pools, etc, the name is coming from the Project Name field, not the filename. When you create the file, the Project name defaults to the filename. When you subsequently change the filename from inside Project with File, SaveAs, the project name tracks the change as well and becomes the new filename. BUT, if you change the filename outside of Project, for instance using file rename in Windows Explorer, the Project name in the file properties does NOT change and remains the old filename. And just to make it more interesting, if when you explicitly change the Project name to override the default of the filename, that locks it in and it now will not change when the filename changes due to a File SaveAs in Project. Once you have entered something in that field other than the default it becomes "sticky" and will be retained regardless of filename changes unless you again explicitly edit the field. -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "John" <com> wrote in message news:microsoft.com... |
Posted: 05 Aug 2004 02:10 PM PDT Hi John, thanks for the offer. I cannot share the files. So I will see if I can find a copy of 98. Again, thanks bartmacl "John" <com> wrote in message news:microsoft.com... |
Posted: 05 Aug 2004 12:46 PM PDT Just to further clarify the above descriptions: Free Slack is the amount of time a task can slip and not effect any other task. Total Slack is the amount of time a task can slip and not effect the end date. Total Slack is calculated as described above. Free slack is a little harder to describe in writing. It is the earliest Early start of the task in question's successor tasks minus the Early Finish of the task in question. (Pretty confusing, I know). They are used for somewhat different purposes. Total slack tells you how much you can either put off a task or extend it's duration without impacting the project end date. In the real world, it is often traded to remove Resource Overallocations or to relieve pressures elsewhere in the schedule. Free slack is considered usually with regard to resource scheduling. If one task slips and forces another task(s) to slip also, even though it doesn't effect the project end date, it forces you to reschedule the resources on the downstream task(s). Sometimes this is easy, sometimes nearly impossible. These numbers help you to properly plan and execute the project and also tell you, to some degree, how tightly scheduled your project is, and, by inference, relative schedule risk. Hope this helps a bit. David G. Bellamy Bellamy Consulting "JackD" <momokuri@gmail> wrote in message news:<phx.gbl>... |
Posted: 05 Aug 2004 09:45 AM PDT Hi, 1. Yes 2. Both Resource Graph and Resource Usage views have the option to show Remaining Availability. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Bo" <microsoft.com> wrote in message news:com... overallocations. Based on the nature of the projects it appears the easiest way to do this is to assign by groups not individuals. My thought process is to make resources such as Engineering, Testing, QC, etc. I have a couple of questions regarding this approach: the number of individuals in the Group. Such as if there are 10 Engineers the max unit % would be 1,000? day/week? |
Posted: 05 Aug 2004 09:29 AM PDT Thanks Rajkumar, I tried that but it changes the dates displayed in the entire chart/view rather than just the header. I'm fine with the way the date displays in the chart body, but was trying to automate the header to show the file saved date in a different format (i.e. independent of the date fields within the chart). For now, each time I save a version of the chart I manually type in the save date in the header as "Updated 5 August, 2004". It's a little thing, but it's something I was asked to do that should have been easy to automate (i.e. &[Saved Date \@ "MMMM d, yyyy"]. Unless someone knows of a way of using field switches in the header, I guess I'm stuck typing it. The to |
Posted: 05 Aug 2004 08:39 AM PDT In addition to Julie's suggestion, for resources whose total consumption is related to the task duration, like fuel that is burned at 10 litres/hr for the duration of the task, instead of entering total units to be used in the resource assignment dialog box, enter the rate of usage. In my example, the resource name would be gasoline, the type would be material, the units would be litres, and the standard rate would be the cost/litre. When entered into the resource assignment dialog you would put "10/hr" in the units column. Then the total used will change as the task gets longer or shorter. Just entering the number without the "/hr" means that number of units will be used over the duration of the task regardless of its duration, exactly what should happen with your pipe (to get from Here to There will require 30 feet of pipe, 3 units, regardless of whether it takes you 4 hours or 6 hours to install it). -- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Jamie Hart" <net> wrote in message news:phx.gbl... |
Posted: 05 Aug 2004 04:03 AM PDT Thanks for your help for R1 is is 30.77hrs 0.5= 49.24hrs assignments have a HAVE MULTIPLE RESOURCES does. |
setting task starting time by hour? Posted: 04 Aug 2004 08:15 PM PDT Andy, Go to Tools, then Change Working Time. Select any day that is NOT a working day for your project (Mon-Thur) and click Nonworking Time. On the working days select the time frame you want in From and TO areas. "andy colb" <microsoft.com> wrote in message news:04c101c47a9a$68758120$gbl... |
Posted: 04 Aug 2004 06:55 PM PDT Hi, If there are no Resource Pools ivolved and the hanging is not linked to leveling I give up. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/index.htm 32-495-300 620 "Anne Thomas" <microsoft.com> wrote in message news:08c301c47ae8$ee3d90b0$gbl... |
You are subscribed to email updates from TextNData Forums - Microsoft Project To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |